MSU/MCTC Law Enforcement and Criminal Justice Center March 10, 2010
Agenda - Schedule - Quality - Financial -Literary Quotations -Monument Sign -Spandrel Panel Issue -Additional Contracts - Progress Photos
ActivityDate Start ConstructionMay 7, 2009 Substantial CompletionJune 19, 2010* Inspections/Punchlist WorkJune 20 – July 20, 2010 FF&E InstallationJune 20 – July 20, 2010 Move-inJuly 20 – August 9, 2010 Fall Semester BeginsAugust 21, 2010 Master Schedule Milestone Dates * Excludes pending request for time extension
ActivityScheduled Completion% Done/anticipated completion CurtainwallMarch 1275%/March 19 Ceramic TileMarch 2665%/March 26 Plumbing FixturesMarch 235%/March 23 Architectural CaseworkMarch 155%/March 15 Ceiling Grid InstallationMay 1120%/May 11 Contractor’s Schedule – Activity Comparison Dates:
UPCOMING WORK -Complete Curtain wall Installation - Mechanical and Electrical Equipment - Soffit Framing - Painting - Ceiling Grid/Light Fixtures/Diffusers - Ceramic Tile - Firing Range Equipment
QUALITY Material Testing Window Testing Roof Inspections/Testing Waterproofing Inspection General Conformance Commissioning
Literary Quotations
Monument Sign Option A Option B
Spandrel Panel Thermal Barrier
Additional Contracts Elert & Associates- $8,250 – Commissioning of technology systems Midwave- $34,750 – Design of the building’s LAN Intereum – Furniture plan and installation coordinator- $14,100
Acoustic Separation of Private Offices
Overview
South Curtain Wall
Casework Delivered
Ceiling Grid Installation
Main Street Corridor
2 nd Floor Mechanical Room
Overlooking Main Street
1 st Floor Restroom