Ph. Lebrun - 100426 Issues, methods and organization for costing the CLIC accelerator project Philippe Lebrun Meeting on costing of CLIC detector CERN,

Slides:



Advertisements
Similar presentations
CLIC CDR Schedules & Value Estimates Philippe Lebrun on behalf of the CLIC Cost & Schedule WG LCWS 12 University of Texas at Arlington, USA 22 – 26 October.
Advertisements

Report on Accelerator Plenary Session “Power Consumption” Chris Adolphsen & Philippe Lebrun LCWS 12 University of Texas at Arlington, USA 22 – 26 October.
ASIPP Zhongwei Wang for CFETR Design Team Japan-US Workshop on Fusion Power Plants and Related Advanced Technologies February 26-28, 2013 at Kyoto University.
Global Manufacturing and Materials Management
Industry and the ILC B Barish 16-Aug May-05ILC Consultations - Washington DC2 Why e + e - Collisions? elementary particles well-defined –energy,
A. Bay Beijing October Accelerators We want to study submicroscopic structure of particles. Spatial resolution of a probe ~de Broglie wavelength.
Report from ILC GlobalGroup 5: Cost and Engineering (Updates since Snowmass) Wilhelm Bialowons, Peter Garbincius and Tetsuo Shidara · GDE December 8, 2005.
5 th CLIC X-band collaboration meetingWalter Wuensch16 May 2011 CLIC rf structure program.
The LHC: an Accelerated Overview Jonathan Walsh May 2, 2006.
CLIC CDR Schedules & Value Estimates Philippe Lebrun on behalf of the CLIC Cost & Schedule WG CLIC Workshop, CERN 28 January – 1 February 2013.
INTEGRATION OF RF STRUCTURES IN THE TWO-BEAM MODULE DESIGN G. Riddone, CERN, Geneva, Switzerland A. Samoshkin, D. Gudkov, JINR, Dubna, Russia Abstract.
On project probabilistic cost analysis from LHC tender data Ph. Lebrun CERN, Geneva, Switzerland TILC’09, Tsukuba, Japan April 2009.
Report from GG5, Dec. 20, 2005 Report from ILC GG 5: Cost and Engineering (Updates since Snowmass) Wilhelm Bialowons, Peter Garbincius and Tetsuo Shidara.
CLIC Cost & Schedule WG: mandate, organization, activities 2009 Ph. Lebrun CERN, Geneva, Switzerland TILC’09 Tsukuba, Japan.
CLIC-ILC Cost & Schedule Working Group Meeting TILC09 – Sunday, April 19, 2009 reported by Peter H. Garbincius CLIC_ILC_phg_21april09.ppt.
1 Update on cost-related issues Philippe Lebrun Joint CLIC-ILC meeting on costs CERN, 12 June 2009 Peter’s notes: Thursday, 16july09 PHG - 16july09: added.
Doing business with CERN Anders Unnervik 3 November 2014.
Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"
International Linear Collider The ILC is the worldwide consensus for the next major new facility. One year ago, the choice was made between the two alternate.
1 The Design & Value Costs SRF Technology The XFEL as a Prototype Japan as a Host International Linear Collider Status Mike Harrison.
Status Update Outline  General remarks - reminder  Progress since last Annual Meeting – June 2010  Next steps - timeline EUROnu Costing Ilias Efthymiopoulos.
CLIC RF structure development meeting Structure cost study (introduction) G. Riddone,
CLIC-ILC meeting on costs Cost learning curves: from theory to practice Ph. Lebrun Webex meeting 17 July 2009.
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
Project Management Mark Palmer Cornell Laboratory for Accelerator-Based Sciences and Education.
CLIC cost estimate Hans-H. Braun, CLIC-GDE meeting, February 8, 2008  Cost model goals  Methodology  Cost distribution  Future improvements.
1 Tunnel implementations (laser straight) Central Injector complex.
Current CLIC Energy Stages D. Schulte1. Main Beam Generation Complex Drive Beam Generation Complex Layout at 3 TeV D. Schulte2.
High gradient acceleration Kyrre N. Sjøbæk * FYS 4550 / FYS 9550 – Experimental high energy physics University of Oslo, 26/9/2013 *k.n.sjobak(at)fys.uio.no.
Status of the Rebaselining D. Schulte for the Rebaselining Team D. Schulte, CLIC Rebaselining, October 2013.
Recent news from CLIC C&S WG and CLIC-ILC WG on General Issues Ph. Lebrun CLIC Project Meeting 1 June 2011.
Cost Model including Civil Engineering and Conventional Facilities Hans-H. Braun, CLIC ACE, June 20, 2007  Cost model goals  Methodology  Scaling assumptions.
CLIC cost & power consumption issues Philippe Lebrun on behalf of the C&S WG CLIC Meeting 11 December 2009.
ESS RF System Design Stephen Molloy RF Group ESS Accelerator Division SLHiPP2 4-May-2012.
CLIC cost drivers Philippe Lebrun on behalf of the C&S WG CLIC Technical Committee 3 November 2009.
S. Claudet - 31st May 2007Power refrigeration for LHC Power refrigeration at 4.5K & 1.8K for the LHC S. Claudet, CERN AT-ACR.
CLIC Energy Stages Meeting D. Schulte1 D. Schulte for the CLIC team.
CLIC Energy Stages D. Schulte1 D. Schulte for the CLIC team.
1 Future Circular Collider Study Preparatory Collaboration Board Meeting September 2014 R-D Heuer Global Future Circular Collider (FCC) Study Goals and.
LHC-CC Validity Requirements & Tests LHC Crab Cavity Mini Workshop at CERN; 21. August Remarks on using the LHC as a test bed for R&D equipment.
Update on cost-related issues Philippe Lebrun Joint CLIC-ILC meeting on costs CERN, 12 June 2009.
Issues, methods and organization for costing the CLIC accelerator project, with particular focus on BDS & MDI Philippe Lebrun Special BDS-MDI meeting CERN,
24-July-10 ICHEP-10 Paris Global Design Effort 1 Barry Barish Paris ICHEP 24-July-10 ILC Global Design Effort.
ILC 2007 Global Design Effort 1 Planning Damping Rings Activities in the Engineering Design Phase Andy Wolski Cockcroft Institute/University of Liverpool.
EuCARD-2 is co-funded by the partners and the European Commission under Capacities 7th Framework Programme, Grant Agreement High Efficiency Work.
Global Design Effort ILC Damping Rings: R&D Plan and Organisation in the Technical Design Phase Andy Wolski University of Liverpool and the Cockcroft Institute,
Energy consumption and savings potential of CLIC Philippe Lebrun CERN, Geneva, Switzerland 55th ICFA Advanced Beam Dynamics Workshop on High Luminosity.
Lucio Rossi The High Luminosity LHC Project Distinguished Lecturer 2013.
Technical External Management Requirements Technology Complexity Interfaces Reliability / Performance Quality Planning Controlling Funding / Resources.
Review of Alignment Tolerances for LCLS-II SC Linac Arun Saini, N. Solyak Fermilab 27 th April 2016, LCLS-II Accelerator Physics Meeting.
Fort Stanwix National Monument Energy Audit Contract
Doing business with CERN Anders Unnervik
Purchasing supplies at CERN
1st FCC Infrastructure & Operation meeting
Chapter 18 Maintaining Information Systems
Purchasing supplies at CERN
CLIC Rebaselining at 380 GeV and Staging Considerations
CLIC Klystron-based Design
Ways to industry participation in CLIC 24th October, 2017
CERN-ITER Workshop CERN Procurement Anders Unnervik 16 Jan 2017
CLIC: from 380 GeV up to 3 TeV Will also study klystron based machine for initial stage.
Why are particle accelerators so inefficient?
LCWS 2017 – 26th October C. Rossi
Measurements, ideas, curiosities
Cost Optimization Models for SRF Linacs
CEPC RF Power Sources System
Advanced Research Electron Accelerator Laboratory
Explanation of the Basic Principles and Goals
Barry Barish Paris ICHEP 24-July-10
ERL Director’s Review Main Linac
Presentation transcript:

Ph. Lebrun Issues, methods and organization for costing the CLIC accelerator project Philippe Lebrun Meeting on costing of CLIC detector CERN, 26 April 2010

Contents Cost of high-energy accelerators Cost estimate methods, organization & tools Feedback to technical design & optimization Large series, manufacturing techniques & learning curves Elements of cost risk analysis Coping with exchange rates & cost escalation Ph. Lebrun

Contents

Development of circular accelerators Lawrence’s first cyclotron (1930) 80 years 10 5 increase in size 10 8 increase in beam energy Large Hadron Collider (2009)

Ph. Lebrun Cost of projects keep increasing Limit of funding capability ?

Ph. Lebrun Cost structure of LEP and LHC Accelerator components account only for ~1/3 of the cost of large accelerators projects Most of the budget goes into civil engineering, infrastructure and services, for which market prices are usually available LHC is atypical –re-use of tunnel and some infrastructure from LEP –large absolute cost of superconducting technology further reduces proportion of infrastructure

Contents Ph. Lebrun

Cost estimate methods Analytical –Based on project/work breakdown structure –Define production techniques –Estimate fixed costs –Establish unit costs & quantities (including production yield and rejection/reprocessing rates) –In case of large series, introduce learning curve (see later) Scaling –Establish scaling estimator(s) and scaling law(s), including conditions & range of application Empirical « First-principles » based –Define reference project(s) and fit data, mutatis mutandis In most cases, hybrid between these methods Ph. Lebrun

CLIC analytical costing based on PBS Component level List of systems standardized Contact experts per system Coordinators per domain/subdomain Identified for analytical costing based on level 5 description

Costing multi-MW klystrons Ph. Lebrun

Scaling klystron cost E. Jensen

Ph. Lebrun Optimizing klystron initial cost E. Jensen

Ph. Lebrun Optimizing klystron cost including replacement E. Jensen

Some issues in estimating operation costs Utilities & consumables –Variability of electricity costs: operation schedule needed –Include externalities in marginal cost Distribution losses Heat rejection Carbon footprint? –Inventory losses & replenishment (fluids) Maintenance & repair –Periodic maintenance MTBF of equipment Cost of spares and scheduled replacement –Emergency repair Comprehensive cost impact of accidents: risk analysis Model for down time and repair interventions Personnel –Staff model for operations group/team –Out- or insourcing? –Personnel stability & investment in training Ph. Lebrun

Organization for CLIC cost estimate CLIC Cost & Schedule WG established Communication and reporting lines defined Web node active (access protected) PBS updated and completed for 3 TeV and 500 GeV phases, including standardization of level 4 technical systems

Ph. Lebrun CLIC Cost & Schedule WG Communication & reporting lines CLIC Cost & Schedule WG CLIC Steering Committee CLIC Technical Committee Other CLIC WG System group ILC GDE Cost Team Other CLIC WG System group reports to PBS, developments & alternatives Configuration Analytical costing Information, methodology Technical design

Ph. Lebrun CLIC Study Costing Tool CLIC Study Costing Tool developed & maintained by CERN GS-AIS Operational, on-line from C&S WG web page (access protected) Includes features for currency conversion, price escalation and uncertainty Demonstrations to users in C&S WG meetings

Contents Ph. Lebrun

Cost drivers, models and optimization Limitation of PBS/WBS-based approach: does not look at interplay between technical systems ⇒ risk of local (« mountain lake ») optimization Hence importance of communication among experts to develop global view –cost WG –informal discussion with system specialists, –understanding of rationale behind scaling laws –pluridisciplinary models –feedback to project team Cost scaling models only exist for limited number of components or subsystems Targeted cost studies by industrial companies important for –providing up-to-date, relevant data –establishing limits of validity of scaling laws –exploring technical alternatives & breakthroughs

Cost & efficiency optimization for CLIC RF frequency RF phase advance per cell Accelerating gradient (loaded) Cavity iris aperture Cavity iris thickness Bunch charge Bunch separation Surface field < 260 MV/m Surface heating < 56 K Power input < 18 MW/mm ns 0.33 Wakefields Emittance growth Luminosity per input power Cost N Y iterate Ph. Lebrun

Cost & efficiency optimization for CLIC Ph. Lebrun

Feedback to technical design: some cost drivers & potential saving options for CLIC Cost driverCost saving impact Cost mitigation optionAlternativeRisk/benefit of alternative Specific actions Accelerating structure stacked disc construction HQuadrant constructionTechnical validation pending Industrial cost studies, prototyping Accelerating structure vacuum tank MSealed constructionLeakagePrototyping Production yield of accelerating structures M to HProduction control and testing Industrial prototyping & preseries production Replacement of 80 MV/m accelerating structures MReinstall and reuse 80 MV/m structures Maximum energy PETS on-off mechanismMDevelop and industrialize Drive beam quadrupoles: unprecedented number MAutomated manufacturing Customization to position in decelerator Allows series powering To be developed Specification from beam physics, industrial study Powering of drive beam quadrupoles MNovel powering scheme ("intelligent bus") Series powering (plus trim windings?) Reduce cabling, limit power consumption Specification from beam physics Reliability of power converters MHot sparesImproved availability of CLIC Specification from beam physics Cost impact LOrder of 10 MCHF MOrder of 100 MCHF HOrder of 1 BCHF Ph. Lebrun

Contents

CLIC two-beam modules Complexity, number, integration CLIC 3 TeV (per linac) Modules: Accelerating str.: 71406PETS: MB quadrupoles: 1996DB quadrupoles: CLIC 3 TeV (per linac) Modules: Accelerating str.: 71406PETS: MB quadrupoles: 1996DB quadrupoles: CLIC 500 GeV (per linac) Modules: 2124 Accelerating str.: 13156PETS: 6578 MB quadrupoles: 929DB quadrupoles: 4248 CLIC 500 GeV (per linac) Modules: 2124 Accelerating str.: 13156PETS: 6578 MB quadrupoles: 929DB quadrupoles: 4248 G. Riddone

Ph. Lebrun CLIC vs LHC components: different solutions for different series numbers Flexible cells, manual work Flexible workshops Automatic chains CLIC AS CLIC PETS CLIC Quads CLIC TBM AS quadrants AS discs

Ph. Lebrun Learning curve: theory T.P. Wright, Factors affecting the cost of airplanes, Journ. Aero. Sci. (1936) Unit cost c(n) of nth unit produced c(n) = c(1) n log 2 a with a = « learning percentage », i.e. remaining cost fraction when production is doubled Cumulative cost of first nth units C(n) = c(1) n 1+log 2 a / (1+log 2 a) with C(n)/n = average unit cost of first nth units produced n = number per production line ≠ total number in project

Experimental learning curve: LHC superconducting dipole magnets P. Fessia Collared coils Cold masses Ph. Lebrun

Learning coefficients P. Fessia

Ph. Lebrun Effect of learning coefficient on average unit cost up to rank N

Ph. Lebrun Saturation of learning process has little impact on total cost

Contents Ph. Lebrun

Cost variance factors Technical design –Evolution of system configuration –Maturity of component design –Technology breakthroughs –Variation of applicable regulations Industrial execution –Qualification & experience of vendors –State of completion of R&D, of industrialization –Series production, automation & learning curve –Rejection rate of production process Structure of market –Mono/oligopoly –Mono/oligopsone Commercial strategy of vendor –Market penetration –Competing productions Inflation and escalation –Raw materials –Industrial prices International procurement –Exchange rates –Taxes, custom duties Engineering judgement of responsible Tracked and compensated Decreasing control of project responsible Outside project control Procurement Contract adjudication Technical definition Reflected in scatter of offers received from vendors (LHC experience)

Ph. Lebrun Observed tender prices for LHC accelerator components Adjusted to mean (1.46) and total number (218) of sample

Ph. Lebrun Sampling from an exponential PDF (m=0,  =1) In response to an invitation to tender, consider n (valid) offers distributed according to an exponential PDF: application of the CERN purchasing rule will lead to select the lowest bidder What is the PDF of the lowest bidders, i.e. of the prices effectively paid? In the following, reasoning on the integral PDF

Ph. Lebrun From distribution of offers to distribution of prices Consider two valid offers X1, X2 following same exponential distribution with P(Xi<x) = F(x) = 1 – exp[-a(x-b)] ⇒ m = b + 1/a and  = 1/a Price paid (lowest valid offer) is Y = min(X1, X2): what is the probability distribution of Y? Estimate P(Y<x) = P(X1<x or X2<x) = G(x) Combined probability theorem P(X1<x or X2<x) = P(X1<x) + P(X2<x) – P(X1<x and X2<x) If X1 and X2 uncorrelated, P(X1<x and X2<x) = P(X1<x) * P(X2<x) Hence, P(X1<x or X2<x) = P(X1<x) + P(X2<x) – P(X1<x) * P(X2<x) and G(x) = 2 F(x) – F(x) 2 = 1 – exp[-2a(x-b)] ⇒ Y follows exponential distribution with m = b + 1/2a and  = 1/2a By recurrence, if n uncorrelated valid offers X1, X2,…Xn are received, the price paid Y = min (X1, X2,…Xn) will follow an exponential distribution with m = b + 1/na and  = 1/na

Ph. Lebrun Dispersion of prices due to procurement uncertainties For LHC accelerator components –48 contracts –218 offers, i.e offers per contract on average From exponential fit of statistical data on offers, m = 1.46,  = 0.46 We can therefore estimate the expected relative dispersion on paid prices  = 0.46/4.54 ≈ 0.1 ⇒ based on LHC experience, the relative standard deviation on component prices due to procurement uncertainties can be taken as 50/n %, where n is the expected number of valid offers

Contents Ph. Lebrun

Exchange rates and cost escalation Exchange rate fluctuations should ideally reflect evolution of purchasing power of currencies, but –Economic parities offset by financial effects –Variety of escalation indices in each currency Choose « reference currency » (CHF) and apply relevant escalation indices in reference country (Office Fédéral de la Statistique) Currency A Time 1 Currency B Time 1 Exchange rate 1 Currency A Time 2 Currency B Time 2 Exchange rate 2 Escalation Index a Escalation Index b ? Ph. Lebrun

Industrial price indices (CH)

Ph. Lebrun Swiss vs CERN indices

Ph. Lebrun Proposed method for CLIC cost risk assessment Separate cost risk factors in three classes, assumed independent –Technical design maturity & evolution of configuration Judgement of « domain responsible » Rank in 3 levels, defining numerical values of  config –Price uncertainty in industrial procurement Estimate n number of valid offers to be received Apply  industry = 50/n % –Economical & financial context Deterministic Track currency exchange rates and industrial indices Estimate r.m.s. sum of  config and  industry Compensate economical & financial effects –Choice of CHF as reference currency –Applications of compound indices from Office Fédéral de la Statistique (CH) Arts et métiers – Industrie for technical components Construction for civil engineering

Ph. Lebrun A few references I. Chvidchenko, Gestion des grands projets, Cours de Sup’Aéro, CEPADUES Editions, Toulouse (1992) C. Roche, Government, industry, accelerators, Frontiers of Accelerator Technology, World Scientific (1996) pp Ph. Lebrun, Estimation du coût marginal de l’énergie consommée par la cryogénie du LHC, LHC Project Note 92 (1997) S. Claudet et al., Economics of large helium cryogenic systems: experience from recent projects at CERN, Adv. Cryo. Eng. 45B Plenum Publishers (2000), pp Management de projet: gestion du risque, norme FD X , AFNOR, Saint Denis (2003) Project Risk Management, in PMBOK ® Guide, 3rd edition, Project Management Institute, Newton Square (2004), pp P. Fessia et al., Industrial learning curves: series production of the LHC main superconducting dipoles, IEEE Trans. Appl. Superconductivity 17 2 (2007) pp The CLIC Study Team, CLIC 2008 parameters, CLIC Note 764 (2008) GAO Cost Estimating & Assessment Guide, United States Government Accountability Office, GAO-09-3SP (2009) P. Garbincius et al., Assessing risk in costing high-energy accelerators: from existing projects to the future linear collider, submitted to IPAC’2010, Kyoto (2010)