Blackstone Hydropower Status Report 3 rd Annual River Users Conference Blackstone Valley Tourism Council Tricia Jedele, Conservation Law Foundation Bruce.

Slides:



Advertisements
Similar presentations
Washington Department
Advertisements

BC Hydros: Reservoir Archaeology Program CRT facilitated workshop Nov 19, 2013.
Gold Ray Dam Interagency Technical Team Meeting. NEPA Update Deconstruction Plans Hydraulic Modeling Next Steps Agenda.
New York State Jack Nasca, New York State Department of Environmental Conservation GLWC Offshore Wind Workgroup Advancing Regional Collaboration Webinar.
FLOW 2008 Oct. 7-9, 2008 San Antonio, TX Housatonic River Case Study Melissa Grader U.S. Fish and Wildlife Service.
General Information on Permitting Electric Transmission Projects at the California Public Utilities Commission June 2009 Presentation created by the Transmission.
Narragansett Bay Estuary Program Narragansett Bay CCMP  Original done 1992  Stakedholder-developed goals, objectives, actions  Many key actions implemented.
Conservation Commissions and the Kinder Morgan Proposed Gas Pipeline PRESENTATION TO NORTHEAST MUNICIPAL GAS PIPELINE COALITION SEPTEMBER 22, 2014 MASSACHUSETTS.
Tidal Energy in Alaska Permitting Issues Michael Murphy Devine Tarbell & Associates.
Wild and Scenic Rivers “ LESSONS LEARNED TO AVOID LITIGATION”
Multi-Sector Ocean Use: Traditional and Alternative Energy MAFAC Meeting May 13, 2009.
Longmeadow Parkway Fox River Bridge Corridor
FERC & Hydrokinetic Projects Ocean Energy for New England Conference Hosted by the Marine Renewable Energy Center at the Advanced Technology and Manufacturing.
Hydroelectric Power
Federal Energy and Environmental Regulation Agencies and Laws
In-conduit Hydropower: Public Sector meets Private Inventions
Challenges and opportunities for dam removal projects in Texas Lessons that can be learned from other states Ryan McGillicuddy – Texas Parks and Wildlife.
The Brownfield Opportunity Area Program OER-NPCR Capacity Building Workshop November 23, 2010.
Our mission ead and execute environmental programs and provide expertise that enables Army training, operations, acquisition and sustainable military communities.
Institutions and Processes for Scaling Up Renewables: Run-of-River Hydropower in British Columbia Mark Jaccard, Noel Melton and John Nyboer Energy & Materials.
MassDOT P3 Project Overview. MassDOT Project Mobility.
Emerging Legal Issues Chuck Sensiba, Van Ness Feldman LLP Northwest Hydroelectric Association Annual Conference February 18, 2014.
Illinois RC & D Introduction to R esource C onservation & D evelopment Module 3: What makes it run?
Financing Renewable Energy Projects OVERVIEW OF PROJECT DEVELOPMENT ISSUES 5 June 2014 Tony Colonnese Director of Engineering Services.
State of Oregon New Hydroelectric Projects Mary Grainey October 2008 Oregon Water Resources Department.
Lake Planning …the health of your lake depends on it! French Planning Services Inc
Eagle Crest Energy Company February Page 2 New Hydro: Making it Happen Background on the Eagle Mountain Pumped Storage Project Need for Eagle.
Columbia River Water Management Program (CRWMP) Review of Year One Upper Crab Creek Planning Unit Meeting April 17, 2007.
State Permitting Issues for Wind Developments Southeast and Mid-Atlantic Regional Wind Summit 19 September 2005 Jennifer A. DeCesaro Energy Policy Specialist.
Bay Area Integrated Regional Water Management Plan North Bay Watershed Association Meeting November 3, 2006 Working together to enhance sustainable water.
Citizens Advisory Committee to the Chesapeake Executive Council November 29, 2012.
Marine Spatial Planning for Wave Energy Development in Oregon Kate Sherman, M.S. Candidate Marine Resource Management College of Earth, Ocean, and Atmospheric.
Development of Micro-Hydro Projects Stacey Simms Associate Director, Programs CREA Energy Innovations Summit.
Energy, Environmental Impacts, and Sustainable Development Presented by Cat Shrier, Ph.D., P.G. Water Resources Planner (403)
Town of Orleans Wind Energy Project Berkshire Renewable Energy Summit June, 2005 Kevin Galligan
1 Potential Project Betterments to be studied further during Relicensing June 20, 2006 Stakeholder Meeting Middle Fork American River Hydroelectric Project.
GKRSE law offices of GKRSE 1 Federal Regulatory Issues Affecting the Development of Hydro in the Northeast Nancy J. Skancke Law Offices of GKRSE Washington,
Ontario Waterpower Policy Initiatives The importance of being earnest Paul Norris President Ontario Waterpower Association.
Vermont Community Development Association March 14, 2007 Hydro-electric in your community The Cutting Edge.
U.S. Army Corps of Engineers Decision Authority l All permit decisions, scope of analysis, 404(b)(1), mitigation, alternatives, jurisdiction -- Corps.
Kilarc-Cow Creek Hydroelectric Project Decommissioning FERC Project No. 606 Technical Meeting May 16, 2007, 1-4 pm Red Lion Redding, CA.
1 | Program Name or Ancillary Texteere.energy.gov Percheron Power, LLC’s Proof of Power Project on Potholes East Canal (POP ‐ PEC) 2011 Water Power project.
1 Implementing the Concepts Environment Pre-Conference Workshop TRB MPOs Present and Future Conference August 27, 2006 Michael Culp FHWA Office of Project.
Siting Ocean and Tidal Energy Projects Cherise M. Oram STOEL RIVES LLP Oregon Law Institute Going Green: Advising Clients in the New World of Sustainability.
Overview of Alabama Power’s Tallapoosa River Operations Martin Dam Relicensing Informational Meeting April 1, 2008 Andy Sheppard, P.E. Project Mgr. - Hydro.
R E T I Coordinating Committee California’s Renewable Energy Transmission Initiative: Status Update California Public Utilities Commission California Energy.
Kilarc-Cow Creek Hydroelectric Project Decommissioning FERC Project No. 606 Shasta County Board of Supervisors March 4, 2008.
NOAA RESTORATION CENTER The NOAA RC seeks to make the process of regulatory review and permitting of environmentally beneficial habitat restoration projects.
1 Poseidon Resources (Channelside), LLC Carlsbad Desalination Project Marine Life Mitigation Plan (MLMP) Marine Life Mitigation Site Selection and Preliminary.
Kilarc-Cow Creek Hydroelectric Project Decommissioning FERC Project No. 606 Public Meeting May 15, 2007, 6-9 pm Millville Grange Palo Cedro, CA.
Northeast Corridor Greenway Acquisition Project – Design and Permitting Status Update City Council Workshop August 25, 2015.
Hydroelectric Energy Brooke Edwards, Steve Reinauer, Heather Shutt, Daniel Weigner, & Kathleen Widmer.
Micro-hydropower for the home, farm, or ranch: A brief overview
C A L I F O R N I A E N E R G Y C O M M I S S I O N Integrated Energy Policy Report Workshop Landscape-Scale Environmental Evaluations for Energy Infrastructure.
Water Quality Certification for hydropower licensing in Wisconsin.
GALVESTON BAY ESTUARY PROGRAM A CATALYST FOR PARTNERSHIPS AND COLLABORATION Sarah Bernhardt, Ph.D. Lower Rio Grande Valley 18 th Annual Water Quality Management.
Atlantic Coast Pipeline NCEDA MidWinter Conference March 9, 2016.
Atlantic Coast Pipeline Fayetteville Regional Association of Realtors March 15, 2016.
> Las Vegas Valley Watershed Advisory Committee Regional Water Quality Plan.
NAVFAC PACIFIC March st North American Wildlife and Natural Resources Conference National Military Fish and Wildlife Association Marine Conservation.
1 Yolo Bypass Salmonid Habitat Restoration & Fish Passage Environmental Impact Statement Environmental Impact Report Yolo Bypass Fisheries Enhancement.
Source: Stream Corridor Restoration Manual WATERSHED MANAGEMENT.
GOOSE CREEK WATERSHED LEVEL I STUDY SCOPING MEETING
The Oregon Watershed Council Model, USA
Savannah River Projects
ISSUES RELATED TO THE FEDERAL RENEWABLE GOAL
Environmental Considerations
How Small Developers and EPC Contractors Can Add PPA Financing to their Arsenals John Langhus, VP Business Development Midwest Solar Expo 2019 New Energy.
MINI -HYDROPOWER Climate friendly but not devoid of environmental and social risk.
Lake Elsinore Hydro Project
Presentation transcript:

Blackstone Hydropower Status Report 3 rd Annual River Users Conference Blackstone Valley Tourism Council Tricia Jedele, Conservation Law Foundation Bruce DiGennaro, The Essex Partnership

Provide cost effective, environmentally sustainable, local renewable energy Protect & enhance environmental resources Advance Watershed Restoration Goals Fish passage & protection Water Quality & Instream Flows Maintain & enhance public access Protect & enhance cultural/historic resources Blackstone Hydro Goals & Objectives 2

3

Phase I Completed (Dec. 2010) Preliminary Permit Applications Filed (Spring 2011) Manville (P-13944) - Valley Affordable Housing Ashton (P-14213) – Ashton Hydro LLC Albion (P-14212) – Albion Hydro LLC Elizabeth Webbing (P-14211) - RIDEM Phase II Investigation Initiated (Summer 2011) Status Overview 4

Phase I: Summary of Results 5 Site Capacity (MW) Annual Energy (MWH) Dev. Costs IRR (%) 20-yr NPV Elizabeth Webbing 0.704,360$1.8M51%$8,117,000 Ashton 0.833,023$6.3M9%$2,563,000 Albion 1.13,974$6.3M13%$4,680,000 Manville 1.44,976$6.2M17%$6,948,000

Phase I: Summary of Results (contd) 6 Portfolio Capacity (MW) Annual Energy (MWH) Dev. Costs 20-yr NPV Avg. Annual Revenues Ashton, Albion & Manville 3.311,973$18.9M$9.9M$725,000 Albion, Manville & Webbing 3.213,310$14.3M$12.7M$925,000 Ashton, Albion, Manville & Webbing 4.016,333$20.7M$14M$1,000,000

7

1. Finalize/Formalize Collaborative Structure (on-going) 2. Initiate Formal Public Outreach and Regulatory Proceedings (Winter ) 3. Environmental Assessment / Scoping / Studies ( ) 4. Engineering & Optimization (2013) 5. Detailed Project Configurations & Operational Protocols (2013) Next Steps (Phase II & Beyond ) 8

Environmental Considerations Instream Flows / Water Quality Fish Passage & Protection Wetlands & Floodplains Shoreline Erosion & Mgt. RT&E spp. & Wildlife Cultural, Historic & Aesthetic Resources Recreational Resources 9

Regulatory Requirements FERC License or Exemption 2-3 year process - extensive consultations & NEPA State Approvals S. 404 Waterways S. 401 Water Quality Cert. Wetlands Protection Act Other Electrical Interconnection Agreement LIHI & DPUC (for REC’s) Local Building & Zoning 10

Federal Energy Regulatory Commission (FERC) Three Stage Consultation Process – Diverse Stakeholder Consultation Requirements – Environmental, Social, Economic & Power – Dam Safety – Clean Water Act (s. 401 & s. 404) Typically 3+ yr process (pre-construction) Consultations Studies Protection, Mitigation & Enhancement 11

FERC / RI Hydropower MOU Partners working with RI EDC to develop a MOU with FERC to streamline FERC process Conceptually the MOU will: Create state-level screening program to ID low impact hydro opportunities (RI Hydro) Establish standards for environmental protection & performance Simplify and streamline FERC review process for eligible projects 12

Schedule Complete Phase II StudiesWinter

Thank-you Q&A 14