Jon S Kapustinsky 11/17/2010 Jon S Kapustinsky FVTX Commissioning Plan 1.71 Jon S Kapustinsky 1.

Slides:



Advertisements
Similar presentations
FVTX Transition to Operations PHENIX FVTX Close Out April 23, 2012 BNL 1 FVTX Close Out Review Ed OBrien April 23, 2012.
Advertisements

3 Oct Cost and Schedule Update Craig Ogilvie, Iowa State University Analysis of system risks Update schedule  Critical path.
MICE CM Berkeley 9-12 Feb February 2005 Edda Gschwendtner 1 Control/Monitoring and DAQ for PIDs Edda Gschwendtner.
Jianchun (JC) Wang, 08/21/99 RICH Electronics and DAQ Chip Carrier Short Cable Transition Board Long Cable Data Board Crate J.C.Wang Syracuse University.
Time Meeting 1/20/2015 PHENIX Run-15 Preparations Douglas Fields PHENIX Run-15 Run Coordinator University of New Mexico.
FVTX Power and cabling – a work-in-progress Task 1.0 – Pre-populate the Racks (Boose/Lenz/Jimmy) Low Voltage Racks2 (on order) Bias Voltage Rack1 (shared.
Electrical Integration WBS Eric J. Mannel Columbia University Electronics Project Engineer VTX and FVTX.
Electrical Integration WBS Eric J. Mannel Columbia University Electronics Project Engineer VTX and FVTX.
Jin Huang Los Alamos National Lab for the FVTX Group.
1/12/20121 PHENIX WEEKLY PLANNING 1/12/2012 Don Lynch.
1 HBD Commissioning (II) Itzhak Tserruya HBD group meeting November 28, 2006 Progress from October 3 to November 28, 2006.
Columbia University IN THE CITY OF NEW YORK Environmental Monitoring DOE Review June 2-3, 2009.
PHENIX WEEKLY PLANNING 2/15/2007 Don Lynch. 2/15/207 Weekly Planning Meeting 2 Remaining Schedule StartComplete Cosmic Ray Run (Run 6.9)In Progress All.
Time Meeting 2/3/2015 PHENIX Run-15 Status Douglas Fields PHENIX Run-15 Run Coordinator University of New Mexico.
U N C L A S S I F I E D FVTX Detector Readout Concept S. Butsyk For LANL P-25 group.
Oct C. Smith - PCAL/EC Commissioning 1 PCAL/EC Commissioning Document
Gerd J. Kunde - LANL1 The FVTX Technology  Outline Overall Picture Silicon Detector –Geometry, Layout, Process Readout Chip –FNAL Chips, New Chip PHX.
DC12 Commissioning Status GOALS: establish operating conditions, determine initial calibration parameters and measure operating characteristics for the.
FVTX Review Nov FVTX Review Homeworks. FVTX Review Nov When is Project Complete; how will it be determined?
1 1/13/2011 PHENIX WEEKLY PLANNING 1/13/2011 Don Lynch No Meeting Today Due to snow shortened work week, today’s planning meeting has been cancelled. Slides.
1/5/20121 PHENIX WEEKLY PLANNING 1/5/2012 Don Lynch.
Roman Pot Engineering Design Review CERN, 14 February 2006 M.Oriunno, CERN PH-TOT Installation, Commissioning and Schedule.
Muon trigger upgrades, missing since not aimed towards DOE funding PHENIX upgrades: view presented to DOE R&D $3.5M Construction $16.6M Au-Au p-p 200 Si-Si.
12/5/ PHENIX WEEKLY PLANNING Dec. 5, 2013 Don Lynch.
12/29/20121 PHENIX WEEKLY PLANNING 12/29/2011 Don Lynch.
David Lee, FVTX Review Nov Cost and Schedule WBS 1.0 David M. Lee Los Alamos National Lab Deputy Project Leader.
The PHENIX Forward Silicon Vertex Tracker Eric J. Mannel IEEE NSS/MIC October 29, 2013.
FVTX Electronics (WBS 1.5.2, 1.5.3) Sergey Butsyk University of New Mexico Sergey Butsyk DOE FVTX review
11/15/20121 PHENIX WEEKLY PLANNING 11/15/12 Don Lynch.
Forward Muon Installation and Commissioning Dmitri Denisov Fermilab Director’s review 7/12/1999 Plan Forward muon detectors Mini-drift tubes installation.
All Experimenters MeetingDmitri Denisov Week of July 7 to July 15 Summary  Delivered luminosity and operating efficiency u Delivered: 1.4pb -1 u Recorded:
LM Feb SSD status and Plans for Year 5 Lilian Martin - SUBATECH STAR Collaboration Meeting BNL - February 2005.
11/8/20121 PHENIX WEEKLY PLANNING 11/8/12 Don Lynch.
Tasks and time scale T. Tsuboyama (KEK). DSSD production Test production by Micron and SINTEF (Talk by M. Valentan) HPK decided to restart DSSD business.
PHENIX WEEKLY PLANNING 3/22/2007 Don Lynch. 3/22/2007 Weekly Planning Meeting 2 Schedule Re-Start 5 man shifts 3/20/07 Beam: blue ring 3/8/07, in yellow.
Robert Pak, FVTX Annual Review Nov Mechanical Integration WBS Robert Pak Brookhaven National Laboratory.
1 FVTX Detector Assembly Stephen Pate New Mexico State University (FVTX Assembly Management WBS 1.7) Stephen Pate, NMSU – FVTX Review – 16-Nov-2009.
Muon Tracker Responsibilities This Year South arm commissioning through this year’s run Analysis Software oversight and development North Arm station 2.
D. M. Lee, LANL 1 07/10/07 Forward Vertex Detector Cost and Schedule.
R. Boyd 1 February  Dr. M. Saleem  D. Jana  M. R. Meera Labbai  R. Boyd.
Forward Vertex Detector Cost, Schedule, and Management Plan Participating Institutions Organizational plan Cost Basis R&D Costs Cost Schedule.
PHENIX WEEKLY PLANNING 10/20/06 Don Lynch. 10/20/06 Weekly Planning Meeting 2 PHENIX Shutdown Overview Task_NameStart_DateFinish_Date PHENIX Shutdown.
1 12/30/2010 PHENIX WEEKLY PLANNING 12/30/2010 Don Lynch.
1 Onsite Status Itaru Nakagawa RIKEN/RBRC. 2 Schedule.
D. M. Lee, LANL 1 07/10/07 Forward Vertex Detector Overview Technical Design Overview Design status.
Melynda Brooks, FVTX Closeout Review, April FVTX Project Overview Cost & Schedule Deliverables Melynda Brooks Los Alamos National Laboratory FVTX.
9/17/2008TWEPP 2008, R. Stringer - UC Riverside 1 CMS Tracker Services: present status and potential for upgrade Robert Stringer University of California,
12/6/20121 PHENIX WEEKLY PLANNING 12/6/12 Don Lynch.
Robert Pak VTX Meeting Sept. 7, 2004 VTX. Robert Pak VTX Meeting Sept. 7, 2004 PHENIX Central Region From VTX Proposal (dims in mm) HBD is standalone.
PHENIX WEEKLY PLANNING 3/15/2007 Don Lynch. 3/15/2007 Weekly Planning Meeting 2 Schedule Cosmic Ray Run (Run 6.9) Done All Up Commissioning On Going Re-Start.
Columbia University IN THE CITY OF NEW YORK FVTX Electronics Oversight and Integration Eric J. Mannel Columbia University.
Robert Pak VTX Meeting June 3, Robert Pak 1 VTX Meeting June 3, 2005 General Progress Started general integration meetings for detector upgrades.
March 25, FVTX Monthly/Quarterly Report June, 2009 Technical Status, Cost & Schedule Melynda Brooks, LANL.
David M. Lee Forward Vertex Detector Cost, Schedule, and Management Plan Participating Institutions Organizational plan Cost Basis R&D Costs.
HBD Report Craig Woody BNL DC Meeting January 7, 2009.
1 HBD Commissioning Itzhak Tserruya DC meeting, BNL December 13, 2006 Progress from October 3 to November 28, 2006.
Robert Pak, FVTX Annual Review, Nov WBS Mechanical Integration Personnel: Walt Sondheim: Mechanical Project Engineer Don Lynch: PHENIX Chief.
Preparations to Install the HBD for Run 6 Craig Woody BNL PHENIX Weekly Meeting January 26, 2006.
SPHENIX MECHANICAL D. Lynch, R. Ruggiero June 12, /12/2014sPHENIX Mechanical Design.
3/7/20131 PHENIX WEEKLY PLANNING 3/7/2013 Don Lynch.
PHENIX WEEKLY PLANNING 3/1/2007 Don Lynch March: in like a lion Out like a lamb.
12/08/20111 PHENIX WEEKLY PLANNING 12/08/2011 Don Lynch.
Columbia University IN THE CITY OF NEW YORK VTX Electronics Integration E.J. Mannel Columbia University DOE Review June 2-3, 2009.
Evelyn Thomson Ohio State University Page 1 XFT Status CDF Trigger Workshop, 17 August 2000 l XFT Hardware status l XFT Integration tests at B0, including:
1 11/25/2010 PHENIX WEEKLY PLANNING 11/25/2010 Don Lynch.
PHENIX Plan for Run13 Kieran Boyle RSC 01/11/20131.
1 FVTX Quarterly/Monthly Report July 2008 Melynda Brooks, Dave Lee.
Melynda Brooks, FVTX Annual Review, November FVTX Project Overview Cost & Schedule Melynda Brooks Los Alamos National Laboratory FVTX Project Manager.
CLAS12 Calibration and Commissioning (CALCOM)
BESIII EMC electronics
Presentation transcript:

Jon S Kapustinsky 11/17/2010 Jon S Kapustinsky FVTX Commissioning Plan 1.71 Jon S Kapustinsky 1

4 half-cages assembled and tested in the FVTX lab in the Physics Building (metrology and survey complete). Full data acquisition system chain tests and cosmic runs on the bench and with bias and low voltage and cooling system, and in the IR. Integrate the FVTX into the VTX support structure outside the IR. Install the VTX/FVTX into the IR with PHENIX techs and engineers (Coordination with the PHENIX Integration Group led by Don Lynch). Installation and Commissioning Overview 11/17/2010Jon S Kapustinsky 2

One half-cage of the FVTX – 3 views 4 detector stations per FVTX assembly, each off-set in phi. Each station has its own cooling circuit. 11/17/2010Jon S Kapustinsky 3

Installation FVTX/VTX in PHENIX IR Installation procedure developed by BNL tech staff Installation procedure approved by CAD 11/17/2010Jon S Kapustinsky 4

FVTX rack layout in the IR Services installed in the IR Chillers will be installed in the assembly hall Dry gas storage tank outside PHENIX 11/17/2010Jon S Kapustinsky 5

Timing calibration, performance optimization, pulser calibration and cosmic runs on the bench Dave Winter, Doug Fields, Sergey Butsyk, Imran Younas, Melynda Brooks, Pat McGaughey, Hubert van Hecke, Jon Kapustinsky, Steve Pate, students and PD’s Install and populate electronics racks in the IR with LV/HV power supplies and power distribution cards BNL techs, Eric Mannel, Robert Pak, Walt Sondheim, Don Lynch Connect FVTX cooling system and dry gas system and safety interlocks BNL techs, Eric Mannel, Robert Pak, Walt Sondheim, Don Lynch Install cabling and optical fibers from the IR to the DAQ in the PHENIX rack room BNL techs, Eric Mannel, Robert Pak, Steve Boose Major tasks and personnel (1) 11/17/2010Jon S Kapustinsky 6

Test cooling system, thermocouples and interlocks BNL techs, Eric Mannel, Robert Pak, Walt Sondheim, Don Lynch Test power distribution systems, bias and low voltage and interlocks Eric Mannel, Paul Giannotti, Pat McGaughey, Steve Boose Test fiber optics and signal integrity for all channels BNL techs, Eric Mannel Slow controls and integration into the PHENIX DAQ Eric Mannel, Martin Purschke, John Haggerty, Ed Desmond Timing calibration, performance optimization, pulser calibration and cosmic runs in the IR Dave Winter, Doug Fields, Sergey Butsyk, Imran Younas, Melynda Brooks, Pat McGaughey, Hubert van Hecke, Jon Kapustinsky, Steve Pate, students and PD’s Major tasks and personnel (2) 11/17/2010Jon S Kapustinsky 7

*RequirementMetricMethod Mini strips active>80% (expect ~99%)calibration/cosmics Hit efficiency>85% (expect~99%)cosmics Radiation length per wedge < 2.4 %by design Detector hit resolution < 25  m cosmics Random noise hits/chip <0.1%calibration (threshold:noise~5:1) Level-1 latency 4  s Level-1 Multi-Event buffer depth 4 events Read-out time < 40  s Read-out rate> 10 kHz *Primary bench test requirements from the Management Plan. The last four have been validated by extensive tests of the FPGA code. FVTX Functional Requirements 11/17/2010Jon S Kapustinsky 8

Additional goals to complete commissioning FVTX fully integrated into PHENIX DAQ. ~99% channels operational, timed in and calibrated. Fully operational on-line monitoring. Expert shift procedures developed for beam runs, detector operations and data acquisition. The FVTX collaboration 11/17/2010Jon S Kapustinsky 9

TaskStart-FinishComments Mechanical support structure and installation hardwareDone for VTX Cable trays in IRDone for VTX Chiller in Assembly HallDone for VTX Dry gas systemDone for VTX Install cables and plumbing and racks (pre-populated)07/01/11-08/01/11* will start asap after the shutdown Cages fully bench tested First cage complete Last cage complete 04/08/11-04/22/11 06/09/11-06/16/11 Bench system tests with cooling and power distribution All FVTX detector, support, installation, alignment and survey parts and assemblies complete, ready for installation 06/16/11-07/1/2011 Install FVTX into the VTX support structure08/01/11-08/10/11 Assembly will be done outside the IR Install and align FVTX/VTX assembly in the IR08/10/11-08/24/11 Installation nearly identical to VTX in 2010 Connect cables and plumbing08/24/11-08/31/11 Test and commission08/31/11-09/27/11 FVTX manpower FVTX Installation and Commissioning Schedule *Shutdown is a month later than even recently expected Assumption is that IR will close 10/01/11 11/17/2010Jon S Kapustinsky 10

Jon S Kapustinsky11/17/2010Jon S Kapustinsky 11 Summary Before installation into the IR – FVTX personnel  Assembled, pre-surveyed, bench-tested FVTX installed into the VTX support. Before Installation into the IR BNL techs and integration personnel  Cooling and dry gas system, HV/LV racks, cables and fibers, FVTX/VTX installation hardware installed in the IR. After installation of the FVTX/VTX in the IR – FVTX and BNL techs and integration personnel  Services hookup and testing, cabling and testing, timing, calibration and integration into the PHENIX DAQ.

Jon S Kapustinsky11/17/2010Jon S Kapustinsky 12 Backup Slides

Jon S Kapustinsky11/17/2010Jon S Kapustinsky 13 On-line monitoring commissioning tasks Histogram sensor hits  hot channels  dead channels  thresholds vs noise  update chip registers as needed Pulser timing  adjust clock to readout (~20 ns window) Cosmics tracking  refine alignment constants Charge sharing/ clusters  tracking software Much of this was already developed for the FVTX cosmic ray tests at LANL