TESTING & COMMISSIONING

Slides:



Advertisements
Similar presentations
THAI TOKO ENGINEERING CO.,LTD.
Advertisements

Testing Relational Database
Final Competence Assessment Assessment Documents Assessment strategy (SummitSkills) Assessment methodology (SQA) Assessment guidelines (SQA)
Commissioning Approach Integrated Service Solutions
Barhale Procedure for Site Establishment
Course Material Overview of Process Safety Compliance with Standards
Background Presenters Work done in preparation for WHS changes
Radiopharmaceutical Production
Today’s Meeting There are approximately 25 people killed by electricity per year in Australia (average for the last 7 years), 700 people are hospitalised.
EQUIPMENT VALIDATION.
MAIN ELECTRICAL SURVEY ITEMS, GENERATORS AND GOVERNORS,, CIRCUIT BREAKERS, SWITCHBOARDS AND FITTINGS (Adapted from:D.T. Hall:Practical Marine Electrical.
Inspection & Test Overview suite412.
IEC Substation Configuration Language and Its Impact on the Engineering of Distribution Substation Systems Notes Dr. Alexander Apostolov.
Mr. Harethe El Ouadhane IEC member for IEC MT14. |Infrastructure Business | Germany | Test Engineer & Expert (Internal Arc, Making, Breaking.
MBA (Trimester) Term V Module Title : Project Finance and Management
Project Phases of an EPIC Contract Pre Project Basic EngDetailed Eng Procurement Long Lead Items MC Prep Installation PC Execute PC and Commissioning Preparation.
Proposed Design and the Operation of a Disconnecting Device for Small EG Installations Prepared by Hendri Geldenhuys.
MC and Commissioning Preparation
INTRODUCTION TO SWITCHGEARS
1 PCA2 On-load Protection Condition Analyser. 2 PCA2 online testing concept Concept introduction: PCA2 is a new system test approach intended to save.
Process Engineer’s Role in Project Management Dr Abdullah Malik.
Unit-3 SUBSTATIONS.
Commissioning of Fire Protection and Life Safety Systems Presented by: Charles Kilfoil Bechtel National Waste Treatment Plant Richland WA.
Unit 201: Health and safety in building services engineering
Software Configuration Management
NERC Lessons Learned Summary April NERC lessons learned published in April 2015 Two NERC lessons learned (LL) were published in April 2015 LL
SENG521 (Fall SENG 521 Software Reliability & Testing Software Product & process Improvement using ISO (Part 3d) Department.
ISO / IEC : 2012 Conformity assessment – Requirements for the operation of various types of bodies performing inspection.
Software Quality Assurance
Paul Hardiman and Rob Brown SMMT IF Planning and organising an audit.
Substation Inspection Program. Mission Substation Incident The event occurred on December 20, 2003 during the peak Christmas shopping season A fire occurred.
Utility Engineers, PC.  Generation  Transmission  Distribution.
What is POWERGRID??? The Power Grid Corporation of India Limited (POWERGRID), is an Indian state-owned electric utilities company headquartered in Gurgaon,
PORTABLE & TRANSPORTABLE ELECTRICAL EQUIPMENT. Legal Requirement and References Abu Dhabi RSB Electrical Regulations - makes reference to the need to.
Introduction to switchgears
TOTAL QUALITY MANAGEMENT
Distribution Systems-General
Department of Electrical Engineering
A Training Presentation On 132 KV GSS JAIPUR Submitted in partial fulfillment For the award of the degree of BACHELOR OF TECHNOLOGY Submitted To:- Submitted.
132KV GSS PIPAR CITY JODHPUR
A SEMINAR ON 400 KV GSS(RRVPNL) BIKANER.
CABLING SYSTEM WARRANTY REGISTRATION. PURPOSE OF CABLING REGISTRATION.
Submitted To:- Submitted By:- Mr.
Testing of Low Voltage Installations
McDonough Bolyard Peck Educational Series HVAC Commissioning Presented by: Doug Wren Steve Baxter September 30, 2003.
SYNERGY INSTITUTE OF ENGINEERING AND TECHNOLOGY
Power System Protective Relaying-Part One
Contestability in Connections Contestability Working Group Meeting NIE/SONI Joint Presentation 9 September
PRODUCT VERIFICATION Adapted from the NASA Systems Engineering Handbook for CSULB EE 400D by Alia Bonetti.
HNC/D Engineering Science
Chapter 8. Electrical Systems
Introduction High Voltage!!.
Principles of Information Systems Eighth Edition
Sub Station.
Agenda TSOG 8th November
Chapter # 25 Sub-Stations risemark.pbworks.com.
Administration of a FIDIC Contract - Project Control
Administration of a FIDIC Contract - Pre-Contract Phase -
DESCRIPTION AND GUIDE TO OPERATIONS
Temporary Works Co-ordination
Hazardous Areas & Hazards of Electricity
ELECTRICAL INSTALLATION AND MAINTENANCE (EIM) 5 INSTALL ELECTRICAL PROTECTIVE DEVICES FOR DISTRIBUTION, POWER, LIGHTING, AUXILIARY, LIGHTNING PROTECTION.
Indian Grid Code and Commissioning Test Procedure Dr
Training on Dr. Sudhir Kumar Grid Connected Rooftop PV Systems
From AS :   Part 4— Commissioning, operation and asset management
PSS verification and validation
POWER SYSTEM COMMISSIONING AND MAINTENANCE PRACTICE
Electrical components and systems
Management of Change GROUP HSE RULE (CR-GR-HSE-302)
Presentation transcript:

TESTING & COMMISSIONING DET310 CHAPTER ONE COMMISSIONING MANAGEMENT

TESTING & COMMISSIONING Introduction The commissioning of electrical power systems may, in the first instance, be thought of a purely engineering activity, associated with understanding and proving the technical integrity, it is however, also a management process, requiring such qualities as; setting of objectives; planning; organising; documentation control; and, most important, the creation of team work.

1.0 COMMISSIONING OBJECTIVES COMMISSIONING MANAGEMENT The objectives of commissioning is to prove that the individual items of equipment, which are interconnected to form systems, circuits and substations, are suitable for their intended purpose and acceptable for commercial service. COMMISSIONING MANAGEMENT

COMMISSIONING OBJECTIVES COMMISSIONING MANAGEMENT This global objective can be subdivided into Verifying that the equipment has not been damaged in transit, that it has been properly installed, and performs as specified Obtaining test data as the basis for comparison with future maintenance and fault investigations results COMMISSIONING MANAGEMENT

COMMISSIONING ACTIVITIES COMMISSIONING MANAGEMENT Commissioning activities includes Off load commissioning test Objectives: To prove the integrity of the installed equipment, hence its suitable for connection to the power system, by observing its performance under test conditions which, as far as practicable, simulate in service conditions and requirements. COMMISSIONING MANAGEMENT

COMMISSIONING ACTIVITIES COMMISSIONING MANAGEMENT b) On-Load Commissioning Test Tests which are carried out with the equipment connected to the power system. Objectives: This test utilized the power system itself to demonstrate that the installation is technically acceptable for commercial operation COMMISSIONING MANAGEMENT

COMMISSIONING ACTIVITIES COMMISSIONING MANAGEMENT c) Inspection: -Pre-energisation Inpection: Process which are carried out before the circuit being energised Objectives: To ensure that all equipment are properly connected and in proper condition before energisation - Post Commissioning Inspection: Process which are carried out after circuit/system has been energised Objectives: To ensure and recheck that the equipments have been left in the service condition COMMISSIONING MANAGEMENT

1.2 COMMISIONING PANEL The commissioning panel is responsible for managing the whole commissioning process. The commissioning panel typically consists of the following representation: Chairman, usually project manager Technical engineer from the supply company capable of defining the required tests and accepting the test results. Contractor representatives supply company power system operations department (mainly concerned with the energisation process) representatives of any companies whose equipment interfaces with that being commissioned.

1.3 COMMISSIONING PROGRAM The commissioning program is the key activity to be progressed by the commissioning panel. It should ideally cover the following stages: Pre-commissioning inspection 2. Off load commissioning test program 3. Pre-energised inspection 4. Energisation and on load commissioning tests (usually covered by the switching program) 5. Post commissioning inspection

COMMISSIONING PROGRAM ISSUE TENDER DOCUMENT AND AWARD CONTRACT (ESC) MANUFACTURE EQUIPMENT (CONTRACTOR) PREPARE DESIGN SPECIFICATIONS (ESC) OFF LOAD COMMISSIONING TEST (CONTRACTOR/ ESC) PRE-COMMISIONING INSPECTION (CONTRACTOR/ESC) ERECT EQUIPMENT ON SITE (CONTRACTOR/ESC) POST COMMISSIONING INSPECTION (CONTRACTOR/ ESC) PRE-ENERGISATION INSPECTION (CONTRACTOR/ ESC) ON-LOAD COMMISSIONING TEST (CONTRACTOR/ ESC) * ESC=electric Supply Company

COMMISSIONING MANAGEMENT COMMISSIONING PROGRAMME 1.31 Pre-Commissioning Inspection This would consists of an inspection of the installation to determined whether work is complete and satisfactory to the point where off-load commissioning test can commence 1.32 Off-load commissioning Test A programme of test which include: Test associated with AC circuit diagram i) Test on current and voltage Transformer ii) Primary Injections Test associated with DC circuit diagram i) Secondary injection on DC relays ii) Circuit diagram logic tests COMMISSIONING MANAGEMENT

COMMISSIONING MANAGEMENT COMMISSIONING PROGRAMME c) Equipment Secondary Injections d) Power Supplies i) 110V battery and distribution board ii) 48 V battery and distribution board iii) Diesel Generator iv) low voltage AC supplies e) High Voltage equipment test i) Circuit Breaker ii) Switches iii) Disconnectors iv) Earth Switches v) Transfomers COMMISSIONING MANAGEMENT

COMMISSIONING PROGRAMME COMMISSIONING MANAGEMENT vi) Reactors vii) Busbars viii) Cables f) Common Equipment i) Busbar Protection ii) Interlocking iii) Synchronizing iv) air system v) Substation Control Systems g) Earthing System i) Substation earthing mat ii) interconnection of earthing system iii) Tower earthing COMMISSIONING MANAGEMENT

COMMISSIONING PROGRAMME COMMISSIONING MANAGEMENT h) High-voltage pressure Test Auto-switching off-load simulation tests End to end Test i) Power Line Carier ii) Intertripping iii) Protection System iv) Substation Control System k) Insulation resistance Test associated with the above COMMISSIONING MANAGEMENT

COMMISSIONING PROGRAMME COMMISSIONING MANAGEMENT 1.33 Pre-Energization Inspection Pre-energisation inspection must be carried out prior to the circuit being energised Example: Confirmation of circuit nomenclature Confirmation that equipment phase connections are in accordance with the phasing diagram Application of locks Checking the correct position of all valves Ensuring satisfactory indication of all pressure valves Checking that all equipment is satisfactorily earthed Ensuring the satisfactory conditioned of all battery supplies Checking that all test connections have been removed Confirmation of the tightness of all terminations Confirmation that all current transformers are normal COMMISSIONING MANAGEMENT

COMMISSIONING PROGRAMME COMMISSIONING MANAGEMENT k) Confirmation that all current transformers links are normal l) All realay settings have been applied correctly m) Confirmation that all commissioning documentation is completed. 1.34 Switching Programme This is a formal and precise worded procedure which specifies the sequence of events required to energise the circuit and carry out the on-load commissioning test. It needs to be circulated to all parties concerned to ensure unanimityof agreement and understanding. It should be provided and approved by the commissioning panel. COMMISSIONING MANAGEMENT

COMMISSIONING PROGRAMME COMMISSIONING MANAGEMENT 1.35 Post-Commissioning Inspection The purpose of this inspection is to double check that the commissioned equipment has been left in the in service position. Example: Ensuring that all temporary commissioning equipment has been removed. Ensuring that all current transformers links are normal Checking the correct position of all IN/OUT switches and transformers tap position Ensuring that all relay settings are normal General visual inspection Ensuring that all commissioned equipment are clearly identify COMMISSIONING MANAGEMENT

COMMISSIONING MANAGEMENT 1.4 DOCUMENTATION An essential requirement of the commissioning process is the formal documentation on both the management activities and the commissioning test. Two type of documentation are Commissioning report- The commissioning report is the formal record of the managerial process. It should consists of A contents sheet, updated as the project progress A copy of high level design specifications Formal minutes of commissioning meetings The programmed of work to be carried out, showing planned and actual completion dates A schedule of commissioning test A commissioning completion documentation, to certify that all work is completed. COMMISSIONING MANAGEMENT

COMMISSIONING MANAGEMENT 1.4 DOCUMENTATION b) Commissioning Log Is the record of the technical process, comprising the complete commissioning test schedule, test certificates, inspection report, switching programme and other relevant technical document COMMISSIONING MANAGEMENT

COMMISSIONING MANAGEMENT 1.5 COMMISSIONING CERTIFICATES Acceptance Certificate This certificate declares that The equipment is ready to be connected to the power system The equipment has been energised and subject to on-load commissioning tests Contract Taking Over certificate When the work has been completed satisfactorily and the equipment commissionied, a contract taking-over certificte or similar documents will require completion. This document notifies the contractor that the supply company has accepted and that the warranty period has commence COMMISSIONING MANAGEMENT