Christopher Nantista ILC 2 nd Baseline Assessment Workshop (BAW-2) SLAC January 18, 2011. …… …… …… … ….

Slides:



Advertisements
Similar presentations
Breakdown Rate Dependence on Gradient and Pulse Heating in Single Cell Cavities and TD18 Faya Wang, Chris Nantista and Chris Adolphsen May 1, 2010.
Advertisements

11/27/2007ILC Power and Cooling VM Workshop Mike Neubauer 1 RF Power and Cooling Requirements Overview from “Main Linac Power and Cooling Information”
5th Collaboration Meeting on X-band Accelerator Structure Design and Test Program. May 2011 Review of waveguide components development for CLIC I. Syratchev,
KCS Ongoing R&D Christopher Nantista SLAC LCWS11 Granada, Spain September 29, …… …… …… … ….
CARE07, 29 Oct Alexej Grudiev, New CLIC parameters. The new CLIC parameters Alexej Grudiev.
1 X-band Single Cell and T18_SLAC_2 Test Results at NLCTA Faya Wang Chris Adolphsen Jul
Design of Standing-Wave Accelerator Structure
Beam loading compensation 300Hz positron generation (Hardware Upgrade ??? Due to present Budget problem) LCWS2013 at Tokyo Uni., Nov KEK, Junji.
Global Design Effort - CFS Baseline Assessment Workshop 2 - SLAC Reduced Bunch Number 1 BASELINE ASSESSMENT WORKSHOP 2 CONVENTIONAL FACILITIES.
Christopher Nantista Chris Adolphsen SLAC TILC09 Tsukuba, Japan April 20, 2009.
Christopher Nantista 2011 Linear Collider Workshop of the Americas (ALCPG11) University of Oregon, Eugene March 20, …… …… …… … ….
KCS Operational Issues Chris Adolphsen, Chris Nantista and Faya Wang GDE PAC Review at KEK 12/12/12.
RF Distribution Alternatives R.A.Yogi & FREIA group Uppsala University.
November LCWS08 S. Fukuda 1 KEK HLRF Status and S1- global S. FUKUDA KEK.
Global Design Effort - CFS Baseline Assessment Workshop 2 - SLAC Positron Source Relocation 1 BASELINE ASSESSMENT WORKSHOP 2 CONVENTIONAL FACILITIES.
Chris Adolphsen 10/03/09 MLI and HLRF Summary. Vladimir Kashikhin.
Proposed machine parameters Andrei Seryi July 23, 2010.
Christopher Nantista ARD R&D Status Meeting SLAC February 3, …… …… …… … ….
Proposed TDR baseline LLRF design J. Carwardine, 22 May 2012.
Clustered Surface RF Production Scheme Chris Adolphsen Chris Nantista SLAC.
Baseline Workshop Preparation At the close of each BAW, we would like to write down a summary that is based on our common understanding of the issues.
Klystron Cluster RF Distribution Scheme Chris Adolphsen Chris Nantista SLAC.
Vladimir Kashikhin. FLASH Cavity Gradient Stability Comparison of beam-off measurements of pulse-to-pulse cavity gradient jitter during the flattop.
Thickness of the Kamaboko Tunnel Shield Wall under Different Assumptions Ewan Paterson Technical Board June 23,
Anders Sunesson RF Group ESS Accelerator Division
Klystron Cluster RF Distribution Scheme Chris Adolphsen Chris Nantista SLAC.
NLC Status and Milestones D. L. Burke ISG9 KEK December 10-13, 2002.
1 SPL Collaboration Meeting dec 08 - WG1 Introduction First SPL Collaboration Meeting Working Group 1 High Power RF Distribution System Introduction.
Power Distribution System R&D at SLAC Christopher Nantista ILC08 Chicago, Illinois November 18,
L-band (1.3 GHz) 5-Cell SW Cavity High Power Test Results Faya Wang, Chris Adolphsen SLAC National Accelerator Laboratory
KSC Operation Control of Cavity Gradients Failure Analysis Near and Long Term R&D Effect on Beam Emittance Chris Adolphsen SLAC 9/7/2010 Going Native in.
Christopher Nantista ILC10 Beijing, China March 27, 2010.
SINGLE-STAGE BUNCH COMPRESSOR FOR ILC-SB2009 Nikolay Solyak Fermilab GDE Baseline Assessment Workshop (BAW-2) SLAC, Jan , 2011 N.Solyak, Single-stage.
Ding Sun and David Wildman Fermilab Accelerator Advisory Committee
Aug 23, 2006 Half Current Option: Impact on Linac Cost Chris Adolphsen With input from Mike Neubauer, Chris Nantista and Tom Peterson.
John Carwardine 21 st October 2010 TTF/FLASH 9mA studies: Main studies objectives for January 2011.
1Matthias LiepeAugust 2, 2007 Future Options Matthias Liepe.
The NLC RF Pulse Compression and High Power RF Transport Systems Sami G. Tantawi, G.Bowden, K.Fant, Z.D.Farkas, W.R.Fowkes J.Irwin, N.M.Kroll, Z.H.Li,
KCS and RDR 10 Hz Operation Chris Adolphsen BAW2, SLAC 1/20/2011.
BEAMLINE HOM ABSORBER O. Nezhevenko, S. Nagaitsev, N. Solyak, V. Yakovlev Fermi National Laboratory December 11, 2007 Wake Fest 07 - ILC wakefield workshop.
KCS Main Waveguide Testing Chris Adolphsen Chris Nantista and Faya Wang LCWS12 Arlington, Texas October 25, 2012.
Jan Low Energy 10 Hz Operation in DRFS (Fukuda) (Fukuda) 1 Low Energy 10Hz Operation in DRFS S. Fukuda KEK.
A Multi-Moded RF Delay Line Distribution System for the Next Linear Collider S. G. Tantawi, G. Bowden, Z.D. Farkas, J. Irwin, K. Ko, N. Kroll, T. Lavine,
HLRF R&D Towards the TDR Christopher Nantista ML-SCRF Webex meeting June 29, 2011.
Summary of Relative RF Distribution Costs with Gradient Considerations (Work in Progress) Chris Adolphsen SLAC.
Project X High Power 325 MHz RF Distribution and Control Alfred Moretti, Nov 12, 2007 Project X Workshop.
Feasibility and R&D Needed For A TeV Class HEP e+e- Collider Based on AWA Technology Chunguang Jing for Accelerator R&D Group, HEP Division, ANL Aug
ESS Linac Upgrade Dave McGinnis Chief Engineer / Accelerator Division May 27, 2014.
Christopher Nantista SLAC Project X Workshop November 12, 2007 Fermilab.
A CW Linac scheme for CLIC drive beam acceleration. Hao Zha, Alexej Grudiev 07/06/2016.
1 DR 10 Hz Repetition Rate S. Guiducci (LNF) AD&I webex, 23 June 2010.
HLRF: KCS option Christopher Nantista SLAC ILC ML&SCRF Baseline Technical Review KEK, Tsukuba, JAPAN January 19, …… …… …… … ….
ILC Power and Cooling VM Workshop
ILC High Power Distribution
Klystron Cluster System (KCS)
Abstract EuSPARC and EuPRAXIA projects
Q &A for the questions from CFS of April 29,2011
Application of moderate (5 MW) X-band power sources for the CLIC accelerating structures testing program and other projects I. Syratchev, CERN.
A frequency choice for the SPL machine: Impact on hardware
Second SPL Collaboration Meeting, Vancouver May 2009
Chris Adolphsen Sergei Nagaitsev
Application of the moderate peak power (6 MW) X-band klystron’s cluster for the CLIC accelerating structures testing program. I. Syratchev.
DRFS and Low Energy 10 Hz Option
CLIC Klystron based. Updates 2017.
Update of CLIC accelerating structure design
CW Operation of XFEL Modules
CEPC RF Power Sources System
ATF project meeting, Feb KEK, Junji Urakawa Contents :
CLIC Feasibility Demonstration at CTF3
ERL Director’s Review Main Linac
Presentation transcript:

Christopher Nantista ILC 2 nd Baseline Assessment Workshop (BAW-2) SLAC January 18, …… …… …… … ….

downstream upstream shaft CTO surface rf power cluster building service tunnel eliminated underground heat load greatly reduced accelerator tunnel TE 01 waveguide surface ~1.06 km Klystron Cluster System Basic Layout Main linac rf power is produced in surface buildings and brought down to and along the tunnel in low-loss circular waveguide. Many modulators and klystrons are “clustered” to minimize surface presence and required shafts. Power from a cluster is combined and then tapped off in equal amounts at 3-cryomodule (RDR rf unit) intervals.

With 12 rf units from the RTML added to each of the main linacs and 4 more in the e - linac than the e + linac for undulator losses, they have 294 and 290 rf units, respectively. The following would seem to be a reasonable modified KCS layout. -- main facilities shaft -- additional KCS shaft 27 e - beam 27 KCS Shafts and RF Units per KCS e + beam undulator

Couplings ranging from ~1 to 1/33 to the TE 01 (low loss, no surface E-field) mode are required. Combining and Distributing Power CTO (Coaxial Tap-Off) “3-port” coupler For combining, the tap-offs are installed backwards. Proper phase and relative amplitude needed for match (mismatched power goes to circulators). determines coupling A pair of 3-dB CTO’s. A CTO connecting WR650 waveguide to 48cm-diameter circular waveguide.

Main Waveguide Bends For KCS, we need to bend the main rf waveguide at full power through multiple 90˚ bends to bring it down to and along the linac tunnel. Demonstration of such a bend is crucial to establishing the feasibility of KCS. Though we’ve considered other options, including a more compact design with significantly higher surface fields, the leading contender is a scaled modification of the following X-band SLAC design*. Smooth, properly spaced circular-elliptical and elliptical-rectangular tapers convert the circular TE 01 mode into the rectangular TE 20 mode, which is preserved around a swept bend. * S. Tantawi, V. Dolgashev, C. Nantista  1.73 m

CTO customizable coupler feed 1feed 2 hybrid load Local RF Power Distribution Scheme Power from each CTO is distributed along a 3-CM rf unit containing 26 cavities through a local PDS. Distribution is tailored to accommodate gradient limits of cavities. Original VTO (Variable Tap-Off) Pair-Feeding Concept manually adjustable by pairs requires pair sorting circulators can be eliminated Alternate Scheme w/ Folded Magic-T’s and Motorized U-Bend Phase Shifters remotely adjustable by pairs requires pair sorting circulators can be eliminated Folded Magic-T’s and Motorized U-Bend s for Each Cavity remotely adjustable by pairs no pair sorting required circulators necessary

294.3 kW(nominal to beam per cavity = 31.5 MV/m  1.038m  9 mA) × (for flat gradient w/ cavity gradient spread and common timing) × (for statistical spread in feed/rf unit requirements w/ fixed couplings) × 26 (cavities/rf unit) ÷ 0.95(~5% local distribution losses) = 9.06 MW/rf CTO × 27 (rf units) ÷ (6.5% main waveguide losses) = beginning of linac run ÷ 0.983(shaft and bends) ÷ 0.993(combining CTO circular waveguide losses) ÷ 0.965(input circulator and WR650 losses) ÷ 0.977(CTO coupling/klystron amplitude mismatches) MW from klystrons ~8% klystron-to-tunnel Peak RF Power Required from Klystrons per 27 RF Unit KCS (full current)

With 31 klystrons and 30 on, we have MW available (2.2% to spare). However, we also need 7% (5% usable) overhead for LLRF to be harnessed via phase control of the rf drives, oppositely dephased in pairs, such that the combined power is reduced as P = P max cos 2 , with  nominally 15˚. Klystrons Needed per 27 Unit KCS (full current) However, we want to be robust against a single klystron failure per system. With N sources combined in a passive network, failure of one source leaves combined the equivalent of (N-1) 2 /N sources. The calculation/estimate suggests we need MW worth of klystron power. At 10 MW each, 29 klystrons would give us 290 MW (2.0% to spare). The maximum power requirement rises to MW ÷ = MW, With 33 klystrons and one off, we have MW (1.9% to spare).  -- V 2n V 2n-1 V tot (30 klystrons for the 24 unit KCS and 25 klystrons for the 20 unit KCS) TOTAL: 20× = 715 klystrons installed (693 on)

27 Unit KCS Average Power Diagram (full current) cavity reflection loads distribution end loads local distribution waveguide main KCS tunnel waveguide shaft & bends combining waveguide (CTO’s) klystron waveguides klystron collector (.65) modulator (.95) beam “wall plug” power supplies (.92) MW (31.5MV/m  1.038m  9mA  0.969ms  5Hz  26cav/unit  27units) combining loads MW 353 kW 203 kW MW 87.6 kW 17.0 kW 319 kW 35.4 kW kW 95.6 kW kW kW heat loads flow (MW) tunnel 320 MW peak Includes power mismatched due to spare and overhead misphasing. beam (~23%)

Reduced Beam Current Halving the number of bunches in the ILC beam pulse is considered as a way to reduce the (initial) cost of the machine. The direct impact on the luminosity might be ameliorated by introduction of a traveling focus scheme. In this reduced beam current “low power” scenario, site power is reduced, along with water cooling requirements. Additionally, for the high-power rf system, the amount of installed rf production equipment can be significantly reduced. The impact depends on the bunch frequency, f B, which affects: beam pulse current: I b = N e e f B beam pulse duration: t b = (n B – 1) f B -1 rf power per cavity: rf pulse duration: and thus

KCS Low Power KCS is very flexible. Combining tens of klystrons allows us to adjust installed power with relatively fine granularity. Simply eliminating every other bunch (halving f B ) maintains the beam duration and halves the current, cutting in half the required peak power. However, it also doubles the cavity fill time., thereby increasing the required rf pulse width at full gradient by 38%. It’s preferable to adopt parameters which allow use of the modulators and klystrons developed for full RDR beam specifications, i.e. to stay within the ~1.6 ms pulse width. This can be achieved by reducing the bunch spacing to increase the current to 0.69 I 0. The rf peak power required at the cavities is reduced from that for the full beam by this factor. Fixed t b : Fixed t rf : beamfill -- full beam -- ½ current -- retains rf pulse width (P rf → ½ P rf0, t rf → 1.38 t rf0 ) (P rf → 0.69 P rf0, t rf → t rf0 )

With 22 klystrons and 21 on, we have MW available (2.2% to spare). However, we also need 7% (5% usable) overhead for LLRF to be harnessed via phase control of the rf drives, oppositely dephased in pairs, such that the combined power is reduced as P = P max cos 2 , with  nominally 15˚. Klystrons Needed per 27 Unit KCS (1/2 bunches) However, we want to be robust against a single klystron failure per system. With N sources combined in a passive network, failure of one source leaves combined the equivalent of (N-1) 2 /N sources. Scaling from the full current case, we need (0.69×284.2=) MW worth of klystron power. At 10 MW each, 20 klystrons would give us 200 MW (2.0% to spare). The maximum power requirement rises to MW ÷ = MW, With 23 klystrons and one off, we have MW (0.12% to spare).  -- V 2n V 2n-1 V tot (21 klystrons for the 24 unit KCS and 18 klystrons for the 20 unit KCS) TOTAL: 20× = 499 klystrons installed (477 on) 30.2% reduced from full current

RDR-Like Fallback Low Power With the KCS and DRFS schemes in development, an RDR-like layout w/ 10 MW klystrons, modulators, etc. in the (enlarged) single tunnel is considered the fallback plan. For half bunches operation, one could double the bunch spacing and install half the modulators and klystrons, each feeding 6 CM’s, rather than 3. This would double the fill time, increasing the required rf pulse width by 38%. The installed modulators and klystrons would then be overspec.ed for the upgrade. FULL BEAM HALF BEAM P rf → ½ P rf0 t rf → 1.38 t rf0 every other klystron omitted

Alternatively, one could install 2/3 of the rf production equipment, with each klystron feeding 4 ½ CM’s. This would reduce the available power per cavity, and thus the acceleratable beam current or bunch frequency, by a factor of ~2/3 vs. RDR. The beam pulse duration (  n B /I b → ½ / 2/3) is then shortened by a factor of ¾, and the fill time increased by a factor of 3/2, yielding an rf pulse width increase of only ~3.5%. every 3 rd klystron omitted P rf → 2/3 P rf0 t rf → t rf0

250 GeV/beam # of bunches bunch spacing beam current beam duration rf peak power fill time, t i rf pulse duration full beam ns9 mA0.969 ms294.2 kW0.595 ms1.564 ms ½ bunches A ns4.5 mA0.969 ms147.1 kW1.190 ms2.159 ms (up 38%) ½ bunches B KCS ns6.21 mA0.702 ms203.0 kW0.862 ms1.564 ms ½ bunches B RDR ns6 mA0.727 ms196.1 kW0.893 ms1.619 ms (up 3.5%) -- full beam 0% -- ½ bunches A 40.6% -- ½ bunches B (KCS) 1.9% -- ½ bunches B (RDR) 31.5 MV/m cryo load increase * * Only includes dynamic load of fundamental rf in cavity. Additional contributions come from coupler (linear w/ power and time) and HOM (current dependent). Parameter Summary Parameter choice also impacts cryogenic load.

Installation for Reduced Bunches KCS: Everything in the tunnel is installed % (499/715) of high power rf production equipment (klystrons, modulators, power supplies, etc.) in KCS surface buildings, upstream from shaft, with main waveguide runs traversing the region where the rest will go. 68.8% (477/693) of “wall plug” power for main linac high power rf. 75%* of water cooling capacity for heat load from high power rf. RDR-Like Fallback: 66.7 % of high power rf production equipment in the linac tunnels, with additional power dividers and waveguide. 69% (1.035 × 2/3) of “wall plug” power for main linac high power rf. ~ 75%* of water cooling capacity for high power rf heat load. full current rf power: P rf0 beam power: P b0 = 0.23P rf0 (see slide 9) heat load: P h0 = P rf0 - P b0 = 0.77P rf0 1/2 bunches rf power: P rf = 0.69P rf0 beam power: P b = 0.5P b0 = 0.115P rf0 heat load: P h = P rf - P b = 0.575P rf0 = 0.747P h0 *

HPRF heat load distribution (from slide 9): above ground – 68.3% below ground – 31.2% (65.7% fixed, 34.3% power dependent) HPRF heat load reduction factor: above ground – 0.69 below ground – ( ×0.69) = Total – (0.683× ×0.894 ) = full beam -- ½ bunches A -- ½ bunches B (KCS) -- ½ bunches B (RDR) Heat Load Breakdown for KCS The rf energy deposited per pulse into the cavity reflection loads (circulator loads), being the product of P rf (  I b ) and t i (  I b -1 ), is, for a given gradient, constant across the parameter sets. For the RDR-like layout the total reduction is the same, 0.75, all below ground.

Transition to Full Beam Current KCS: Upgrade is all above ground. Install remaining 31% of “wall plug” power capacity. Install remaining 25% of cooling capacity. Install remaining 30.2% of high-power rf hardware in the KCS buildings. Most, up to the point of connecting the sources into the main waveguide, can be done while running. RDR-Like Fallback: Install remaining 31% of “wall plug” power capacity. Install remaining 25% of cooling capacity. Install remaining 33.3 % of high-power rf hardware in the linac tunnels. ILC is shut down during installation.