Northeast Hospital Expansion Penn State AE Senior Thesis Project Joshua Miller | Construction Management Option Faculty Advisor | Craig Dubler Courtesy.

Slides:



Advertisements
Similar presentations
| Michael Gallagher | Construction Management AE Faculty Consultant: Dr. Riley The Pennsylvania State University AE Senior Thesis Project.
Advertisements

Aria Health | Torresdale Campus Emergency Department | Expansion Robert M. Stano | AE | Construction Option Adviser | Dr. Chimay Anumba Senior Thesis Presentation.
Jeremiah Ergas AE 482 – 5 th Year Senior Thesis Structural Option April 15 th, 2008 Faculty Consultant: Dr. Ali Memari Northside Piers – Brooklyn, NY Structural.
A Medical Office Building For The Primary Health Network Daniel Goff I Structural Option Dr. Thomas Boothby l Faculty Advisor Sharon, Pennsylvania Source:
Penn State Hershey Medical Center Children’s Hospital Hershey, Pennsylvania Matthew Vandersall Structural Option AE Senior Thesis Dr. Richard Behr.
West Virginia University Alumni Center Gregory Smithmyer | Mechanical Option | Penn State University | April 15, 2009 | Advisor: Dr. Srebric.
C AMPUS S QUARE H ARRISBURG, P ENNSYLVANIA A NDREW M ARTIN | C ONSTRUCTION M ANAGEMENT | A PRIL 12, 2010.
Coppin State University Physical Education Complex Kaylee Damico – Mechanical Option April 12 th, 2011 Presentation Outline Project Team Project Overview.
Bowie State University Fine and Performing Arts Center Zachary Lippert Faculty Advisor: Dr. Stephen Treado.
The Edward St. John Student Center Zachary Haupt Faculty Advisor: Dr. William Bahnfleth 11 April 2011.
The Warrenton Aquatics and Recreation Facility Warrenton, Virginia Derek DiPiazza Construction Management.
Daniel Suter Construction Management AE Senior Thesis Presentation The Pennsylvania State University Unknown Data Center Somewhere, USA
LOCKWOOD PLACE BALTIMORE, MARYLAND Monica Steckroth- Structural Option.
Bethesda Triangle Brian Groark Construction Management Faculty Consultant: Dr. Messner.
Fisk Corporate Headquarters Houston, Texas Penn State AE Senior Capstone Project Stephen Blanchard – Construction Management Option Advisor: Dr. John Messner.
William H. Gates Hall University of Washington School of Law Katie Jenkins The Pennsylvania State University Architectural Engineering Lighting/Electrical.
Jeremy Feath Construction Option University Engineering Building Mid-Atlantic University, United States ( Courtesy of Owner)
The New RLPS Architects Office Building Lancaster, PA Brice Ohl – Mechanical Option Presented on 4/10/13.
SENIOR THESIS PRESENTATION
Introduction Connected to existing Benton Hall via skywalk Size: 103,154 SF above grade on 4 levels 82,661 SF below grade parking on 3 levels Cost: $23,651,159.
Student Life Building Northampton Community College Introduction Project Overview Braced Frame Analysis Fire Suppression Analysis Roofing Analysis Project.
Berks Classroom and Lab Building Reading, Pennsylvania Julia Broskey Mechanical Option AE 482 – Senior Thesis Faculty Advisor :Dr. William P. Bahnfleth.
The Office Building Washington, D.C. Penn State Architectural Engineering Senior Capstone Project Brett Miller | Construction Option Advisor: Dr. Ed Gannon.
David Sivin – Mechanical Bellevue Ambulatory Care Pavilion AE 882 Senior Thesis Faculty Advisor: Dr. Jelena Srebric The Pennsylvania State University.
Kennedy Krieger Institute Outpatient Medical Center Baltimore, Marylan d Katie Sennett Construction Management Dr. Messner Spring 2008.
Council Rock High School South Seth Glinski Construction Management Spring 2003 Thesis.
Charles Miller Construction Option Spring Dr. Riley WestEnd25.
SEAN BEVILLE STRUCTURAL OPTION ADVISOR: PROF. BOOTHBY APRIL 13, 2009 TEMECULA MEDICAL CENTER “STRUCTURAL SYSTEM OPTIMIZATION” THE DEPARTMENT OF ARCHITECTURAL.
Paul Roberts Senior Thesis 2010 Construction Management.
The Health Care Center Dauphin County, PA Ken Lorenz Penn State University Architectural Engineering Construction Management April 17, 2007.
The Apartment Building Rockville, MD Penn State AE Senior Capstone Project Brian Bernens | Construction Option Advisor: Dr. Rob Leicht Courtesy DAVIS.
The Towers at the City College of New York Robin Scaramastro - Structural Option - Advisor: Dr. Memari Senior Thesis Final Presentation – Spring 2007.
Bronx School for Law Government & Justice Yulien Wong Mechanical Option 2006 Senior Thesis Bronx, New York.
Architectural Engineering Senior Thesis Mechanical System Redesign Saint Joseph Medical Center Chris Nicolais.
Government Office Center Mid-Atlantic U.S. Penn State AE Senior Thesis Project Alexander Ward | Construction Management James Faust | CM Advisor.
Todd McCaskey Spring 2006 Senior Thesis Construction Management Penn State University Todd McCaskey’s Senior Thesis The Pennsylvania State University Architectural.
Sullivan Trail Junior High Pocono Summit, Pennsylvania Andrew Mellow Goals Background Drawings Site Plan Schedule April 13, 2005.
APPELL LIFE SCIENCES York College of Pennsylvania Joshua Martz | Dr. Srebric | April 11, 2011 Image Courtesy of RLPS, Ltd.
Brad Oliver – Structural Option Advisor – Professor Memari.
Craig Owsiany Architectural Engineering – Construction Management STEM Building Hagerstown Community College Hagerstown, Maryland Science Technology.
Oklahoma University Children’s Medical Office Building Oklahoma City, Oklahoma AE Senior Thesis Final Report April 14, 2014 Jonathan Ebersole Structural.
151 First Side William J. Buchko introduction overview proposal structural depth acoustics breadth cm breadth conclusions 151 First Side Pittsburgh, PA.
The Mary J. Drexel Home Assisted Living Addition Bala Cynwyd, PA Penn State AE Senior Capstone Project Gjon Tomaj – Construction Management Option Advisor:
Eastern USA University Academic Center Alexander AltemoseIStructural Option.
Arts & Humanities Instructional Building Noah J. Ashbaugh Construction Management 2006.
Widener University Metropolitan Hall
Twin Rivers Elementary/Intermediate of McKeesport Area School District Tessa Bauman Mechanical Option Technical Consultant: Laura Miller 1600 Cornell St.,
BUILDING: LOCATION: SIZE: OCCUPANT: ARCHITECT: ENGINEERS: St. Francis Friary Hanceville, Alabama 59,900 square feet, 2 floors above grade Archdiocese.
Hamot Women’s Hospital Erie, PA Michael Galleher Mechanical Option l AE-Senior Thesis l April 12, 2011 l Advisor Dr. Jelena Srebric.
Michael A. Troxell Structural Option Senior Thesis 2006 The College of Business Administration Northern Arizona University Flagstaff, Arizona.
THE NORTHBROOK CORPORATE CENTER Redesign of the Lateral Load Resisting System.
PENN STATE AE SENIOR CAPSTONE PROJECT Adam Lasher │Construction Management Dr. Robert Leicht Susquehanna Health Patient Tower Expansion Williamsport, PA.
The New Student Housing Building at The Mount St. Mary’s University Emmitsburg, Maryland Erik Shearer Mechanical Option Advisor: Dr. Srebric Spring 2007.
ANTONIO DESANTIS VERNE STRUCTURAL OPTION ADVISOR: PROF. PARFITT APRIL 14, 2008 BRIDGESIDE POINT II PITTSBURGH, PA “BUILDING SYSTEM OPTIMIZATION” THE DEPARTMENT.
Manoa Elementary School Amanda Cronauer Faculty Advisor: Dr. William Bahnfleth 14 April 2010.
Michael Reilly, Jr. – Mechanical Option Advisor – James Freihaut, PhD & Dustin Eplee The Pennsylvania State University Nassau Community College Life Sciences.
Villanova University: School of Law Jason Greer The Pennsylvania State University Architectural Engineering Lighting/Electrical Option Senior Thesis –
Mountain State Blue Cross Blue Shield Headquarters
ENVIROCENTER PHASE II JESSUP, MD
Advisor: Professor M. Kevin Parfitt
Grunenwald Science and Technology Building
Introduction James W. & Frances G. McGlothlin Medical Education Center
Acterna Headquarters John M Sekel, EIT Germantown, Maryland
Biobehavioral Health Building, University Park, PA
LONGWOOD AT OAKMONT HEALTHCARE CENTER
Senior Thesis Presentation
JAKE POLLACK NEW YORK POLICE ACADEMY STRUCTURAL OPTION
the Franklin Square Hospital Center
Justin Pennycoff AE Senior Thesis 2008 Construction Management
RiverView Condominiums II Chicago, IL
Presentation transcript:

Northeast Hospital Expansion Penn State AE Senior Thesis Project Joshua Miller | Construction Management Option Faculty Advisor | Craig Dubler Courtesy of Smith Group JJR

I.Introduction Project Background Analysis Overview II.Analysis 1: Implementing an Integrated Project Delivery Current Delivery Method Case Studies of Similar Projects Using IPD Suggested Methods for Implementation III.Analysis 2: Patient Room Re-Design for Shared Wet Wall Existing/Proposed Patient Room Layout Mechanical Breadth: Piping Re-Sizing Cost and Schedule Impact IV.Analysis 3: SIPS Utilization for Patient Floors Original Crew Sizes & Proposed Work Zones Workflow Balancing Cost and Schedule Impact V.Conclusions & Recommendations VI.Acknowledgements AE Senior Thesis Project Joshua Miller | Construction Management Option Introduction Northeast Hospital Expansion 123 Medical Lane, USA Project Background Key Elect. Main Water Main Const. Parking Ambulance Bay/Access Const. Access Res. Zoning New Const. Building Information 234,000 SF 10 Stories 120 Private Patient Rooms $230 Million ($121 million for new patient tower) Project Schedule Start Date: January 2013 Completion Date: September 2015 Total Duration: 973 work days Project Manager Whiting-Turner Construction Manager at Risk Guaranteed Maximum Price

AE Senior Thesis Project Joshua Miller | Construction Management Option Introduction Northeast Hospital Expansion 123 Medical Lane, USA Analysis Overview Analysis 1: Implementing an Integrated Project Delivery Observing how similar projects in the US are implementing IPD strategies that could have been used to create a more efficient project team and suggesting how apply these methods. Analysis 2: Patient Room Re-Design for Shared Wet Wall Re-evaluating the plumbing design for the private patient rooms to create a more efficient design that potentially saves on labor time and material costs. Mechanical Breadth: Re-sizing the sanitary, vent, and the cold and hot water supplies Analysis 3: SIPS Utilization for Patient Floor s Applying short interval production scheduling to the MEP installations and finishes on the private patient floors for an accelerated schedule and more balanced workflow. Analysis 4: Preassembled Steel Connection Bridge Identifying sections of the bridge connecting the existing hospital to the patient tower addition for preassembly in order to create a safer work environment and reduce the time spent on steel erection. Structural Breadth: Verifying the preassembled sections can be picked by the crane and designating pick points. I.Introduction Project Background Analysis Overview II.Analysis 1: Implementing an Integrated Project Delivery Current Delivery Method Case Studies of Similar Projects Using IPD Suggested Methods for Implementation III.Analysis 2: Patient Room Re-Design for Shared Wet Wall Existing/Proposed Patient Room Layout Mechanical Breadth: Piping Re-Sizing Cost and Schedule Impact IV.Analysis 3: SIPS Utilization for Patient Floors Original Crew Sizes & Proposed Work Zones Workflow Balancing Cost and Schedule Impact V.Conclusions & Recommendations VI.Acknowledgements

AE Senior Thesis Project Joshua Miller | Construction Management Option Northeast Hospital Expansion 123 Medical Lane, USA Analysis 1: Implementing an Integrated Project Delivery I.Introduction Project Background Analysis Overview II.Analysis 1: Implementing an Integrated Project Delivery Current Delivery Method Case Studies of Similar Projects Using IPD Suggested Methods for Implementation III.Analysis 2: Patient Room Re-Design for Shared Wet Wall Existing/Proposed Patient Room Layout Mechanical Breadth: Piping Re-Sizing Cost and Schedule Impact IV.Analysis 3: SIPS Utilization for Patient Floors Original Crew Sizes & Proposed Work Zones Workflow Balancing Cost and Schedule Impact V.Conclusions & Recommendations VI.Acknowledgements

AE Senior Thesis Project Joshua Miller | Construction Management Option Analysis 1: Implementing an Integrated Project Delivery Northeast Hospital Expansion 123 Medical Lane, USA Current Delivery Method Owner Smith Group JJR Architect Whiting -Turner Construction Manager at Risk Southland Industries Mech/Plumbing Contractor Dynalectric Electrical Contractor Other Subcontractors McMullan & Associates, Inc. Structural Engineer Leach Wallace Associates, Inc. MEP/FP Engineering Syska Hennessey Group MEP/FP Engineering Loiederman Soltesz Associates Civil Engineers Project Multi- Party contract Liability Waivers Risk/ Reward Pool Integrated Team Structure Early Involvement of Key Players Co- location Network Sharing Northeast Hospital Expansion   9 miles 16.4 miles 13 miles 24 miles McMullan & Associates, Inc. Syska Hennessey Group Leach Wallace Associates, Inc. Smith Group JJR Loiederman Soltesz Associates 26 miles I.Introduction Project Background Analysis Overview II.Analysis 1: Implementing an Integrated Project Delivery Current Delivery Method Case Studies of Similar Projects Using IPD Suggested Methods for Implementation III.Analysis 2: Patient Room Re-Design for Shared Wet Wall Existing/Proposed Patient Room Layout Mechanical Breadth: Piping Re-Sizing Cost and Schedule Impact IV.Analysis 3: SIPS Utilization for Patient Floors Original Crew Sizes & Proposed Work Zones Workflow Balancing Cost and Schedule Impact V.Conclusions & Recommendations VI.Acknowledgements

AE Senior Thesis Project Joshua Miller | Construction Management Option Analysis 1: Implementing an Integrated Project Delivery Northeast Hospital Expansion 123 Medical Lane, USA Case Studies of Similar Projects Using IPD Project Multi- Party contract Liability Waivers Risk/ Reward Pool Integrated Team Structure Early Involvement of Key Players Co- location Network Sharing Northeast Hospital Expansion   Cardinal Glennon Children's Hospital Expansion   Cardinal Glennon Children’s Hospital Courtesy of Christer Inc. I.Introduction Project Background Analysis Overview II.Analysis 1: Implementing an Integrated Project Delivery Current Delivery Method Case Studies of Similar Projects Using IPD Suggested Methods for Implementation III.Analysis 2: Patient Room Re-Design for Shared Wet Wall Existing/Proposed Patient Room Layout Mechanical Breadth: Piping Re-Sizing Cost and Schedule Impact IV.Analysis 3: SIPS Utilization for Patient Floors Original Crew Sizes & Proposed Work Zones Workflow Balancing Cost and Schedule Impact V.Conclusions & Recommendations VI.Acknowledgements

AE Senior Thesis Project Joshua Miller | Construction Management Option Analysis 1: Implementing an Integrated Project Delivery Northeast Hospital Expansion 123 Medical Lane, USA Case Studies of Similar Projects Using IPD Project Multi- Party contract Liability Waivers Risk/ Reward Pool Integrated Team Structure Early Involvement of Key Players Co- location Network Sharing Northeast Hospital Expansion   Cardinal Glennon Children's Hospital Expansion   St. Clare Health Center    Courtesy of Kwame Building Group. I.Introduction Project Background Analysis Overview II.Analysis 1: Implementing an Integrated Project Delivery Current Delivery Method Case Studies of Similar Projects Using IPD Suggested Methods for Implementation III.Analysis 2: Patient Room Re-Design for Shared Wet Wall Existing/Proposed Patient Room Layout Mechanical Breadth: Piping Re-Sizing Cost and Schedule Impact IV.Analysis 3: SIPS Utilization for Patient Floors Original Crew Sizes & Proposed Work Zones Workflow Balancing Cost and Schedule Impact V.Conclusions & Recommendations VI.Acknowledgements

AE Senior Thesis Project Joshua Miller | Construction Management Option Analysis 1: Implementing an Integrated Project Delivery Northeast Hospital Expansion 123 Medical Lane, USA Case Studies of Similar Projects Using IPD Project Multi- Party contract Liability Waivers Risk/ Reward Pool Integrated Team Structure Early Involvement of Key Players Co- location Network Sharing Northeast Hospital Expansion   Cardinal Glennon Children's Hospital Expansion   St. Clare Health Center    Encircle Health's Ambulatory Care Center    Encircle Health’s Ambulatory Care Center Courtesy of HGA I.Introduction Project Background Analysis Overview II.Analysis 1: Implementing an Integrated Project Delivery Current Delivery Method Case Studies of Similar Projects Using IPD Suggested Methods for Implementation III.Analysis 2: Patient Room Re-Design for Shared Wet Wall Existing/Proposed Patient Room Layout Mechanical Breadth: Piping Re-Sizing Cost and Schedule Impact IV.Analysis 3: SIPS Utilization for Patient Floors Original Crew Sizes & Proposed Work Zones Workflow Balancing Cost and Schedule Impact V.Conclusions & Recommendations VI.Acknowledgements

AE Senior Thesis Project Joshua Miller | Construction Management Option Analysis 1: Implementing an Integrated Project Delivery Northeast Hospital Expansion 123 Medical Lane, USA Case Studies of Similar Projects Using IPD Project Multi- Party contract Liability Waivers Risk/ Reward Pool Integrated Team Structure Early Involvement of Key Players Co- location Network Sharing Northeast Hospital Expansion   Cardinal Glennon Children's Hospital Expansion   St. Clare Health Center    Encircle Health's Ambulatory Care Center    Cathedral Hill Hospital  Courtesy of Smith Group I.Introduction Project Background Analysis Overview II.Analysis 1: Implementing an Integrated Project Delivery Current Delivery Method Case Studies of Similar Projects Using IPD Suggested Methods for Implementation III.Analysis 2: Patient Room Re-Design for Shared Wet Wall Existing/Proposed Patient Room Layout Mechanical Breadth: Piping Re-Sizing Cost and Schedule Impact IV.Analysis 3: SIPS Utilization for Patient Floors Original Crew Sizes & Proposed Work Zones Workflow Balancing Cost and Schedule Impact V.Conclusions & Recommendations VI.Acknowledgements

AE Senior Thesis Project Joshua Miller | Construction Management Option Analysis 1: Implementing an Integrated Project Delivery Northeast Hospital Expansion 123 Medical Lane, USA Case Studies of Similar Projects Using IPD Project Multi- Party contract Liability Waivers Risk/ Reward Pool Integrated Team Structure Early Involvement of Key Players Co- location Network Sharing Northeast Hospital Expansion   Cardinal Glennon Children's Hospital Expansion   St. Clare Health Center    Encircle Health's Ambulatory Care Center    Cathedral Hill Hospital  Health Sciences Facility III   Courtesy of the University of Maryland I.Introduction Project Background Analysis Overview II.Analysis 1: Implementing an Integrated Project Delivery Current Delivery Method Case Studies of Similar Projects Using IPD Suggested Methods for Implementation III.Analysis 2: Patient Room Re-Design for Shared Wet Wall Existing/Proposed Patient Room Layout Mechanical Breadth: Piping Re-Sizing Cost and Schedule Impact IV.Analysis 3: SIPS Utilization for Patient Floors Original Crew Sizes & Proposed Work Zones Workflow Balancing Cost and Schedule Impact V.Conclusions & Recommendations VI.Acknowledgements

AE Senior Thesis Project Joshua Miller | Construction Management Option Analysis 1: Implementing an Integrated Project Delivery Northeast Hospital Expansion 123 Medical Lane, USA Suggested Methods for Implementation Project Multi- Party contract Liability Waivers Risk/ Reward Pool Integrated Team Structure Early Involvement of Key Players Co- location Network Sharing Proposed Northeast Hospital Expansion   Northeast Hospital Expansion   Cardinal Glennon Children's Hospital Expansion   St. Clare Health Center    Encircle Health's Ambulatory Care Center    Cathedral Hill Hospital  ˜˜ Health Sciences Facility III   Smith Group JJR Architect Whiting -Turner CM at Risk Southland Industries Mech/Plumb Dynalectric Electrical Other Subcontractors McMullan & Associates, Inc. Struct. Eng. Leach Wallace Associates, Inc. MEP/FP Eng. Syska Hennessey Group MEP/FP Eng. Loiederman Soltesz Associates Civil Eng. Owner Negotiated Space for Part-Time Co-Location I.Introduction Project Background Analysis Overview II.Analysis 1: Implementing an Integrated Project Delivery Current Delivery Method Case Studies of Similar Projects Using IPD Suggested Methods for Implementation III.Analysis 2: Patient Room Re-Design for Shared Wet Wall Existing/Proposed Patient Room Layout Mechanical Breadth: Piping Re-Sizing Cost and Schedule Impact IV.Analysis 3: SIPS Utilization for Patient Floors Original Crew Sizes & Proposed Work Zones Workflow Balancing Cost and Schedule Impact V.Conclusions & Recommendations VI.Acknowledgements

AE Senior Thesis Project Joshua Miller | Construction Management Option Northeast Hospital Expansion 123 Medical Lane, USA Analysis 2: Patient Room Re-Design for Shared Wet Wall I.Introduction Project Background Analysis Overview II.Analysis 1: Implementing an Integrated Project Delivery Current Delivery Method Case Studies of Similar Projects Using IPD Suggested Methods for Implementation III.Analysis 2: Patient Room Re-Design for Shared Wet Wall Existing/Proposed Patient Room Layout Mechanical Breadth: Piping Re-Sizing Cost and Schedule Impact IV.Analysis 3: SIPS Utilization for Patient Floors Original Crew Sizes & Proposed Work Zones Workflow Balancing Cost and Schedule Impact V.Conclusions & Recommendations VI.Acknowledgements

AE Senior Thesis Project Joshua Miller | Construction Management Option Analysis 2: Patient Room Re-Design for Shared Wet Wall Northeast Hospital Expansion 123 Medical Lane, USA Existing/Proposed Patient Room Layout Existing Patient Room Layout Proposed Patient Room Layout ADA 2010 Considerations Change of Water Closet and Carrier Josam Series Patient Quality of Care Pittsburgh’s UPMC Study on Patient Room Size Patient Room Area = 220SF is Optimum Reduces Patient falls Decrease in readmission rate Proposed patient room area = 228SF I.Introduction Project Background Analysis Overview II.Analysis 1: Implementing an Integrated Project Delivery Current Delivery Method Case Studies of Similar Projects Using IPD Suggested Methods for Implementation III.Analysis 2: Patient Room Re-Design for Shared Wet Wall Existing/Proposed Patient Room Layout Mechanical Breadth: Piping Re-Sizing Cost and Schedule Impact IV.Analysis 3: SIPS Utilization for Patient Floors Original Crew Sizes & Proposed Work Zones Workflow Balancing Cost and Schedule Impact V.Conclusions & Recommendations VI.Acknowledgements

AE Senior Thesis Project Joshua Miller | Construction Management Option Analysis 2: Patient Room Re-Design for Shared Wet Wall Northeast Hospital Expansion 123 Medical Lane, USA Mechanical Breadth: Piping Re-Sizing Sanitary and Vent Piping Schematic Table (2): Sanitary Drainage Sizing Table 916.1: Vent Size and Developed Length *Tables referenced from the 2009 International Plumbing Code Number of Drainage Fixture Units (dfu) Fixture TypeDfu Value Lavatory1 Shower (Flow Rate < 5.7 gpm)2 Water Closet, public (1.6 gpf)4 I.Introduction Project Background Analysis Overview II.Analysis 1: Implementing an Integrated Project Delivery Current Delivery Method Case Studies of Similar Projects Using IPD Suggested Methods for Implementation III.Analysis 2: Patient Room Re-Design for Shared Wet Wall Existing/Proposed Patient Room Layout Mechanical Breadth: Piping Re-Sizing Cost and Schedule Impact IV.Analysis 3: SIPS Utilization for Patient Floors Original Crew Sizes & Proposed Work Zones Workflow Balancing Cost and Schedule Impact V.Conclusions & Recommendations VI.Acknowledgements

AE Senior Thesis Project Joshua Miller | Construction Management Option Analysis 2: Patient Room Re-Design for Shared Wet Wall Northeast Hospital Expansion 123 Medical Lane, USA Mechanical Breadth: Piping Re-Sizing CW and HW Supply Piping Schematic Load Value, Water Supply Fixture Units (wsfu) Fixture Type Wsfu Values ColdHot Lavatory (Public, Faucet)1.5 Shower (Public, Mixing Valve)3.0 Water Closet (Public, Flush Valve)10.0- *Tables referenced from the 2009 International Plumbing Code 8 ft/sec Velocity Portion of BranchWsfuGpm Converting from wsfu to Gallon per minute (gpm) 5/8” 1/2” I.Introduction Project Background Analysis Overview II.Analysis 1: Implementing an Integrated Project Delivery Current Delivery Method Case Studies of Similar Projects Using IPD Suggested Methods for Implementation III.Analysis 2: Patient Room Re-Design for Shared Wet Wall Existing/Proposed Patient Room Layout Mechanical Breadth: Piping Re-Sizing Cost and Schedule Impact IV.Analysis 3: SIPS Utilization for Patient Floors Original Crew Sizes & Proposed Work Zones Workflow Balancing Cost and Schedule Impact V.Conclusions & Recommendations VI.Acknowledgements

AE Senior Thesis Project Joshua Miller | Construction Management Option Analysis 2: Patient Room Re-Design for Shared Wet Wall Northeast Hospital Expansion 123 Medical Lane, USA Cost and Schedule Impact SystemExisting DesignProposed DesignDifference% Change CW & HW Supply$1, $1,580.26($71.71)105% Sanitary$10, $5,437.89$5, % Vent$1, $930.69$ % Insulation$1, $794.88$ % Total$14, $7,948.84$6, % SystemExisting DesignProposed DesignDifference% Change CW & HW Supply$2, $1,367.62$ % Sanitary$5, $2,440.21$3, % Vent$1, $965.83$ % Insulation$ $477.37$ % Total$9, $4,773.66$4, % Material Cost Comparison Per Patient Room Pair Labor Costs Comparison Per Patient Room Pair SystemExisting DesignProposed DesignDifference% Change CW & HW Supply % Sanitary % Vent % Insulation % Total % Labor Hour Comparison Per Patient Room Pair DesignSchedule Acceleration Material CostsLabor CostsTotal Cost Existing-$670,079.25$435,192.30$1,105, Proposed93 days$357,697.80$214,814.70$572, Total Schedule & Cost Reduction Summary I.Introduction Project Background Analysis Overview II.Analysis 1: Implementing an Integrated Project Delivery Current Delivery Method Case Studies of Similar Projects Using IPD Suggested Methods for Implementation III.Analysis 2: Patient Room Re-Design for Shared Wet Wall Existing/Proposed Patient Room Layout Mechanical Breadth: Piping Re-Sizing Cost and Schedule Impact IV.Analysis 3: SIPS Utilization for Patient Floors Original Crew Sizes & Proposed Work Zones Workflow Balancing Cost and Schedule Impact V.Conclusions & Recommendations VI.Acknowledgements Savings $532,759

AE Senior Thesis Project Joshua Miller | Construction Management Option Northeast Hospital Expansion 123 Medical Lane, USA Analysis 3: SIPS Utilization for Patient Floors I.Introduction Project Background Analysis Overview II.Analysis 1: Implementing an Integrated Project Delivery Current Delivery Method Case Studies of Similar Projects Using IPD Suggested Methods for Implementation III.Analysis 2: Patient Room Re-Design for Shared Wet Wall Existing/Proposed Patient Room Layout Mechanical Breadth: Piping Re-Sizing Cost and Schedule Impact IV.Analysis 3: SIPS Utilization for Patient Floors Original Crew Sizes & Proposed Work Zones Workflow Balancing Cost and Schedule Impact V.Conclusions & Recommendations VI.Acknowledgements

AE Senior Thesis Project Joshua Miller | Construction Management Option Analysis 3: SIPS Utilization for Patient Floors Northeast Hospital Expansion 123 Medical Lane, USA Original Crew Sizes & Proposed Work Zones I.Introduction Project Background Analysis Overview II.Analysis 1: Implementing an Integrated Project Delivery Current Delivery Method Case Studies of Similar Projects Using IPD Suggested Methods for Implementation III.Analysis 2: Patient Room Re-Design for Shared Wet Wall Existing/Proposed Patient Room Layout Mechanical Breadth: Piping Re-Sizing Cost and Schedule Impact IV.Analysis 3: SIPS Utilization for Patient Floors Original Crew Sizes & Proposed Work Zones Workflow Balancing Cost and Schedule Impact V.Conclusions & Recommendations VI.Acknowledgements

AE Senior Thesis Project Joshua Miller | Construction Management Option Analysis 3: SIPS Utilization for Patient Floors Northeast Hospital Expansion 123 Medical Lane, USA Workflow Balancing Each Activity has 1 week to complete 1 zone Crews to complete 900 SF per day I.Introduction Project Background Analysis Overview II.Analysis 1: Implementing an Integrated Project Delivery Current Delivery Method Case Studies of Similar Projects Using IPD Suggested Methods for Implementation III.Analysis 2: Patient Room Re-Design for Shared Wet Wall Existing/Proposed Patient Room Layout Mechanical Breadth: Piping Re-Sizing Cost and Schedule Impact IV.Analysis 3: SIPS Utilization for Patient Floors Original Crew Sizes & Proposed Work Zones Workflow Balancing Cost and Schedule Impact V.Conclusions & Recommendations VI.Acknowledgements

AE Senior Thesis Project Joshua Miller | Construction Management Option Analysis 3: SIPS Utilization for Patient Floors Northeast Hospital Expansion 123 Medical Lane, USA Workflow Balancing (Proposed SF/Day) (Original SF/Day) X (Original Crew Size) = (Proposed Crew Size) (Proposed Crew Size) X (Hourly Cost/Worker) X 8 Hrs = (Total Cost/Day) (Total Cost/Day) X 5 Zones/Floor = (Total Cost/Floor) X 5 Days/Zone (Total Cost/Floor) X 3 Patient Floors = (Total Project Cost/Activity) Σ(Total Project Cost/Activity) = Total Project Cost I.Introduction Project Background Analysis Overview II.Analysis 1: Implementing an Integrated Project Delivery Current Delivery Method Case Studies of Similar Projects Using IPD Suggested Methods for Implementation III.Analysis 2: Patient Room Re-Design for Shared Wet Wall Existing/Proposed Patient Room Layout Mechanical Breadth: Piping Re-Sizing Cost and Schedule Impact IV.Analysis 3: SIPS Utilization for Patient Floors Original Crew Sizes & Proposed Work Zones Workflow Balancing Cost and Schedule Impact V.Conclusions & Recommendations VI.Acknowledgements

AE Senior Thesis Project Joshua Miller | Construction Management Option Analysis 3: SIPS Utilization for Patient Floors Northeast Hospital Expansion 123 Medical Lane, USA Workflow Balancing (Proposed SF/Day) (Original SF/Day) X (Original Crew Size) = (Proposed Crew Size) (Proposed Crew Size) X (Hourly Cost/Worker) X 8 Hrs = (Total Cost/Day) (Total Cost/Day) X 5 Zones/Floor = (Total Cost/Floor) X 5 Days/Zone (Total Cost/Floor) X 3 Patient Floors = (Total Project Cost/Activity) Σ(Total Project Cost/Activity) = Total Project Cost I.Introduction Project Background Analysis Overview II.Analysis 1: Implementing an Integrated Project Delivery Current Delivery Method Case Studies of Similar Projects Using IPD Suggested Methods for Implementation III.Analysis 2: Patient Room Re-Design for Shared Wet Wall Existing/Proposed Patient Room Layout Mechanical Breadth: Piping Re-Sizing Cost and Schedule Impact IV.Analysis 3: SIPS Utilization for Patient Floors Original Crew Sizes & Proposed Work Zones Workflow Balancing Cost and Schedule Impact V.Conclusions & Recommendations VI.Acknowledgements

AE Senior Thesis Project Joshua Miller | Construction Management Option Analysis 3: SIPS Utilization for Patient Floors Northeast Hospital Expansion 123 Medical Lane, USA Cost and Schedule Impact Schedule TypeOriginalSIPS Labor Cost $2,992, $2,979, Start Date3/5/14 End Date7/22/153/18/15 Duration (days) Labor Savings: $12, Schedule Acceleration:126 days (18 weeks) I.Introduction Project Background Analysis Overview II.Analysis 1: Implementing an Integrated Project Delivery Current Delivery Method Case Studies of Similar Projects Using IPD Suggested Methods for Implementation III.Analysis 2: Patient Room Re-Design for Shared Wet Wall Existing/Proposed Patient Room Layout Mechanical Breadth: Piping Re-Sizing Cost and Schedule Impact IV.Analysis 3: SIPS Utilization for Patient Floors Original Crew Sizes & Proposed Work Zones Workflow Balancing Cost and Schedule Impact V.Conclusions & Recommendations VI.Acknowledgements

AE Senior Thesis Project Joshua Miller | Construction Management Option Conclusions & Recommendations Northeast Hospital Expansion 123 Medical Lane, USA Analysis 1: Implementing an Integrated Project Delivery Analysis 2: Patient Room Re-Design for Shared Wet Wall Analysis 3: SIPS Utilization for Patient Floor s Project Multi- Party contract Liability Waivers Risk/ Reward Pool Integrated Team Structure Early Involvement of Key Players Co- location Network Sharing Proposed Northeast Hospital Expansion   Design Schedule Acceleration Material Costs Labor CostsTotal Cost Existing-$670,079.25$435,192.30$1,105, Proposed93 days$357,697.80$214,814.70$572, Schedule TypeOriginalSIPS Labor Cost $2,992, $2,979, Start Date3/5/14 End Date7/22/153/18/15 Duration (days) Savings $12, days (18 weeks) Savings $532, ✔ ✔✔ I.Introduction Project Background Analysis Overview II.Analysis 1: Implementing an Integrated Project Delivery Current Delivery Method Case Studies of Similar Projects Using IPD Suggested Methods for Implementation III.Analysis 2: Patient Room Re-Design for Shared Wet Wall Existing/Proposed Patient Room Layout Mechanical Breadth: Piping Re-Sizing Cost and Schedule Impact IV.Analysis 3: SIPS Utilization for Patient Floors Original Crew Sizes & Proposed Work Zones Workflow Balancing Cost and Schedule Impact V.Conclusions & Recommendations VI.Acknowledgements General Conditions: $13,027,770 Total 973 total original work days $13, per day

AE Senior Thesis Project Joshua Miller | Construction Management Option Acknowledgements Northeast Hospital Expansion 123 Medical Lane, USA Special Thanks To: John Ovelman – Whiting-Turner Chris Brooks – Southland Industries Raj Vora – Southland Industries John Carbonneau – Southland Industries Adam Davis – Penn State Office of Physical Plant Mark Bittner – CBRE Healthcare Jake Hughes – CBRE Healthcare PACE Industry Members My Friends, Family, and A-7 Academic: Penn State Architectural Engineering Faculty Dr. Craig Dubler – Faculty Advisor Industry Acknowledgements: Whiting-Turner Southland Industries CBRE Healthcare I.Introduction Project Background Analysis Overview II.Analysis 1: Implementing an Integrated Project Delivery Current Delivery Method Case Studies of Similar Projects Using IPD Suggested Methods for Implementation III.Analysis 2: Patient Room Re-Design for Shared Wet Wall Existing/Proposed Patient Room Layout Mechanical Breadth: Piping Re-Sizing Cost and Schedule Impact IV.Analysis 3: SIPS Utilization for Patient Floors Original Crew Sizes & Proposed Work Zones Workflow Balancing Cost and Schedule Impact V.Conclusions & Recommendations VI.Acknowledgements

Northeast Hospital Expansion Thank you Courtesy of Smith Group JJR Questions?