Detailed Quantity Estimating Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.

Slides:



Advertisements
Similar presentations
ESTIMATING - A CONTRACTORS PERSPECTIVE. Company History/Background Oman Construction was founded in 1876 First bridge contract in 1881 First Highway Contract.
Advertisements

CERTIFICATE 4 IN BUILDING BCGBC4004A. 18 week course First 10 weeks in classroom Following 8 in computer room 1.30pm pm (with 15 min break) Assessments.
Chapter 15 Closing the Bid. Objectives Upon completion of this chapter, you will be able to: –Describe the estimate summary process –Describe items that.
Estimating & Tendering. Estimating work involves dealing with Measurements and quantities Pricing and rates Subcontract packages Tender preparation.
Taking off and ESTIMATING
Presenter: Victor C. Tyler, P.E. Estimating and Bidding Strategies that Drive Best Practices.
Reinforced Concrete QTO Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.
CON 4003 CVE 4073/5073 The Estimating Process Prof. Ralph V. Locurcio, PE.
Preparing a Post Bid Report Preparing a Post Bid Report NYS OGS Design & Construction Group Cost Control.
Construction Cost Estimating Class #2: Bidding Process Prof. Ralph V. Locurcio, PE.
TAKING IT ALL IN BEFORE YOU TAKE-OFF Presented by Kathy McCauley October 10, 2014.
Chapter 14 Pricing General Expenses. Objectives Upon completion of this chapter, you will be able to: –Define general expenses –Use a checklist to identify.
Earthwork QTO Stage 1 Preconstruction Stage 2: Procurement
Chapter 12 Pricing Masonry Carpentry, and Finishes Work.
Construction Cost Estimating Class #5 - Concrete Prof. Ralph V. Locurcio, PE.
35 Estimating Building Costs Chapter Permission granted to reproduce for educational use only.© Goodheart-Willcox Co., Inc. Objectives Explain the process.
 Given: No information  Find: The Number of basketballs required to fill this classroom.
Assemblies Estimating Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.
Material Management. Materials should be ordered early –Minimize risk of price inflation, lack of materials –Just in time delivery minimizes space required.
Activities CTC-415. Activity Consumes Time Usually consumes resources (cure time for concrete) Definable start and finish Assignable – V. important –
Pre-Construction Phase 1 - Job Site Conditions Work Plan -2.
ESTIMATING By Laith Jacob.
Lecture(3) Instructor : Dr. Abed Al-Majed Nassar
Conceptual Cost Estimating
Construction Engineering 221 Cost Estimating and Bidding.
EM15 – Contractors COST MANAGEMENT
Chapter 1 Introduction to Cost Estimates What is an Estimate? An estimate is an evaluation of a future cost. A building cost estimate is an attempt to.
Chapter 11 Pricing Concrete Work. Objectives Upon completion of this chapter, you will be able to: –Describe the job factors and the labor and management.
Material and Waste. Materials Management Planning of material use, material reuse, material reduction and recycling begins in the first stage of a project.
Construction Engineering Management Project Costing
Chapter 1 Introduction.
Chapter 11 Subcontractor Work. Introduction Subcontractors perform 80% or more of the on-site work in residential construction. Often, the homebuilder.
Front End Work Planning a successful project Presented by Clark Branum Rafco Products.
Chapter 8 Pricing Generally. Objectives Upon completion of this chapter, you will be able to: –Describe the general process of pricing a construction.
Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out Square Foot Estimating.
Construction Contracts and Project Delivery Methods
ARC 807: Professional Practice and Procedure Department of Architecture, Federal University of Technology, Akure, Nigeria ARC 807: Professional Practice.
Construction Cost Estimating Class #2: The Estimating Process Prof. Ralph V. Locurcio, PE.
Advanced Project Management Project Procurement/Contract Management Ghazala Amin.
Chapter 2 Introduction to Construction Procedures
CON 4003 CVE 4073/5073 Construction Cost Estimating Class #2: The Estimating Process Prof. Ralph V. Locurcio, PE.
FOOD ENGINEERING DESIGN AND ECONOMICS
CONSTRUCTION ADMINISTRATION Measurement and Payment Dr. Alaattin Kanoğlu Spring, 2013 Professional Practice Management I.B.U. Architecture Undergraduate.
It’s not just a SWAG* * Scientific Wild Ass Guess Developing the Project Estimate.
Estimating CE-147 Week 2. Estimate Types Concept Detailed Definitive.
Statement Analysis: Comparative Statements FLASHCARDS.
Construction of a Transfer Station
Chapter 13 Estimates for Remodeling Work
Pre-Construction Activities to include: - Provide effective overlap period and oversight of effort - Estimates during - CPM Schedule - Identify lead-time.
What is “Constructability”?
Fundamentals of Project Control Chapter 11 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project.
Estimating and Scheduling CEE 492
Construction Planning and Estimating Construction Technology I Module 2 part 2.
Conaway Conference March 15-16, 2016 “A Bridge from Concept to Construction” A Contractor’s Perspective.
DR. Nabil Dmaidi F ACTORS THAT D ETERMINE V ARIATION IN E STIMATES.
Quantity Surveying.
QUANTITY AND COST ESTIMATION OF RESIDENTIAL BUILDING
Estimating and Scheduling CEE 492
Tender Dossier as seen by Tenderers.
Estimating the Cost for the Concrete Pad
Estimating the Cost for the Concrete Pad
Highways & Infrastructure Best Value Construction Procurement Presentation November, 2017.
An-Najah National University
9/18/2018 Bids CONTRACTING Khamis…..
Estimating the Cost for the Concrete Pad
Estimating the Cost for the Concrete Pad
Estimating the Cost for the Concrete Pad
DBIA Manual of Practice
Basic Principles of Estimating
Muskat Secondary School Project
Presentation transcript:

Detailed Quantity Estimating Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out

Detailed Estimates A careful tabulation of quantity take-off multiplied by unit costs. Can only be prepared when the plans and specs are complete Must include indirect costs Must be accurate, some contracts will state a “ceiling amount”.

Should the Company Submit a Bid? Before a detailed estimate is prepared, some questions must be answered. Questions about: financial, legal, competition, and risk aspects. If the top management decides to bid, a detailed QTO is prepared, a site investigation is made, and the costs are computed.

Organization of the Detailed Estimate Estimating department is not the top management, and others besides the estimator will make reference to the estimate A standard method of estimating should be used. Estimates must be clear and neat, with complete descriptions. Every estimator’s approach within the same company must be the same.

In order to standardize the estimates within a company, different companies will develop different estimating manuals. Estimate forms are the basis for cost control, both better be organized in a similar way. Checklists may assure that some items are not missed

Site Investigation A visit to the site is part of the detailed estimate to avoid surprises and to look for favorable conditions After carefully studying the plans, the estimator will visit the site and gather information about: transportation availability, road conditions, public utilities availability, weather conditions, earthwork items, and other various possible problems such as: noise, dust, traffic, and access to the site. See Figure 7.1. The estimator will take pictures and may recommend to dig test pits. In case of a remote site, the estimator will need information about the local labor conditions, housing, and local suppliers and subcontractors.

The Quantity Take-Off (QTO) An estimate consists essentially of the quantity of each item and the price per unit. QTO includes the in-place quantities as well other material such as shoring, forms, etc. Quantities must –be taken for each item in the same units as the unit of pricing. –be taken in whole multipliers of the modular dimensions of materials and allow for cutting and trimming. The number of 9”X 9” tiles needed for a floor 10 X 20 ft is not simply 10 X 20 X 144 /(9X9) = 356 tiles. It should be 14 X 27 tiles = 378 tiles.

–allow for overlapping of material (reinforcing bars, roofing material, welded wire fabrics, etc.) –include sub-activities. –include additional allowances (5 to 25%) for some items for reasons such as breakage, waste, or theft. Do not include an allowance twice: overlap of rebar is included once.