GLAST Large Area Telescope:

Slides:



Advertisements
Similar presentations
GLAST LAT ProjectNovember 3, 2005 I&T Phase 0 IRR/TRR 1 GLAST Large Area Telescope: Integration and Test Phase 0 IRR/TRR November 3-4, 2005 Introduction.
Advertisements

GLAST LAT Project Managers F2F Integration and Test 1 GLAST Large Area Telescope: Face to Face Managers Meeting LAT Integration & Test April.
GLAST LAT ProjectNovember 18, 2004 I&T Two Tower IRR 1 GLAST Large Area Telescope: Integration and Test One and Two Tower Integration Readiness Review.
GLAST LAT Instrument GLAST Monthly Mission Review August 6, 2007 K. Fouts, SLAC 1 Monthly Mission Review Project Status Overview August 6, 2007 Ken Fouts.
IFCT Plan for Next 3 Months Larry Wai June 26, 2003.
GLAST LAT ProjectNovember 18, 2004 I&T Two Tower IRR - Dept. of IFCT 1 GLAST Large Area Telescope: Integration and Test Two Tower Integration Readiness.
GLAST LAT ProjectLAT I&T Subsystem CDR, March 28, 2003 Document: LAT-PR Section 4 - Page 1 GLAST Large Area Telescope: I & T Peer Review Performance.
GLAST LAT ProjectNovember 04, 2005 Phase 0 TRR 1 GLAST Large Area Telescope: Integration and Test -Electrical Test- Phase 0 TRR Key Requirements Documents.
1 GLAST LAT ProjectMechanical Systems Mechanical Systems Mechanical / Thermal Hardware November 2004 Status Marc Campell, Subsystem Manager.
GLAST LAT Project I&T Meeting – Jan 29,2004 E. Gawehn 1 GLAST Large Area Telescope: MGSE Status Report Eric Gawehn SU-SLAC I&T MGSE Engineer
GLAST LAT ProjectNovember 18, 2004 I&T Two Tower IRR 1 GLAST Large Area Telescope: Integration and Test Two Tower Integration Readiness Review I&T Plan.
GLAST LAT ProjectApril 27, 2006: LAT Pre-Ship Review 1 Presentation 8 of 12 Integration and Test GLAST Large Area Telescope: Pre-Shipment Review Integration.
1 GLAST LAT ProjectMechanical Systems Mechanical Systems Mechanical / Thermal Hardware July 2005 Status Marc Campell, Subsystem Manager.
GLAST LAT ProjectDOE/NASA Review of the GLAST/LAT Project, Feb , 2001 Martin Nordby1 Martin Nordby Stanford Linear Accelerator Center Stanford University.
GLAST LAT ProjectLAT Mgr’s Meeting LAT Planning Meeting Mechanical/Thermal Systems March 17, 2005 Marc Campell.
GLAST LAT Project Technical/Cost/Schedule Review 03/31/ Integration and Test 1 GLAST Large Area Telescope: I & T Input to Monthly Technical/Cost/Schedule.
GLAST LAT Project4 April 2005 LAT System EngineeringLAT Test Planning Meeting GLAST LAT GLAST LAT System Engineering Gamma-ray Large Area Space Telescope.
GLAST I&T January T Borden 1 Tracker EM Mechanical Mock-up T Borden I&T Tracker Mock-up.
GLAST LAT ProjectSLAC Pre - Baseline Review, April 16, 2002 ` 1 GLAST Large Area Telescope: I&T Overview WBS: Elliott D. Bloom Stanford Linear Accelerator.
GLAST LAT Project Technical/Cost/Schedule Review 09/01/ Integration and Test 1 GLAST Large Area Telescope: I & T Input to Monthly Technical/Cost/Schedule.
GLAST LAT ProjectNovember 3, 2005 I&T Phase 0 IRR/TRR 1 GLAST Large Area Telescope: Integration and Test Phase 0 IRR/TRR November 3-4, 2005 Introduction.
GLAST LAT Project Technical/Cost/Schedule Review 03/30/ Integration and Test 1 GLAST Large Area Telescope: I & T Input to Monthly Technical/Cost/Schedule.
GLAST LAT ProjectJune Cost/Schedule Status Meeting 07/23/ Integration and Test 1 GLAST Large Area Telescope: I & T Input to June Cost/Schedule.
GLAST LAT ProjectDOE/NASA Status Review, March 30 & 31, 2004 Integration and Test 1 Integration, Facilities, Configuration, and Test (IFCT) Flow Procedure.
GLAST LAT ProjectSubsystem Managers Meeting May 12, GLAST Large Area Telescope: Lowell A. Klaisner Stanford Linear Accelerator Center Project Manager.
GLAST LAT Project November 18, 2004 I&T Two Tower IRR 1 GLAST Large Area Telescope: I&T Integration Readiness Review Integration, Facility, Configuration.
GLAST LAT ProjectLAT Planning Meeting July 17 th and 18 th Integration and Test 1 GLAST Large Area Telescope: I & T Input to LAT Planning Meeting.
GLAST LAT ProjectNovember 18, 2004 I&T Two Tower IRR 1 GLAST Large Area Telescope: Integration and Test One and Two Tower Integration Readiness Review.
High Bay Operations1 GLAST LAT ProjectMarch 2005 LAT Engineering Meeting 14 March March 2005 LAT High Bay Operations Supporting Test Events LAT.
GLAST LAT ProjectIntegration and Test CDR Peer Review, March 28, 2003 Document: LAT-PR Section 7 - Page 1 GLAST Large Area Telescope: I & T Peer.
GLAST LAT ProjectI&T&C Pre PDR Presentation– Oct. 2, I&T&C Organization Chart I&T&C Manager Elliott Bloom WBS I&T Engineer B. Grist WBS
GLAST LAT ProjectI&T&C Pre PDR, October 2, 2001 E. do Couto e Silva1 I&T&C Organization Chart I&T&C Manager Elliott Bloom WBS I&T Engineer B. Grist.
LAT Design Integration and Analysis1 GLAST LAT Project1 Sep 2005 LAT Monthly Status Review 1 Sep 2005 Design Integration and Analysis LAT Monthly Status.
GLAST LAT ProjectI&T PDR Presentation (IFCT Dept.) – January 9, 2002 Larry Wai Integration and Test Organization Chart I&T Manager Elliott Bloom WBS
GLAST LAT ProjectFace to Face Managers Meeting 04/14/ Integration and Test 1 GLAST Large Area Telescope: I & T Input to Face to Face Managers.
GLAST LAT Project – Cost and Schedule ReviewJanuary 27, 2004 AntiCoincidence Detector 1 GLAST Large Area Telescope: Cost/Schedule Review January 27, 2005.
1 GLAST LAT ProjectMechanical Systems Mechanical Systems Mechanical / Thermal Hardware December 2004 Status Marc Campell, Subsystem Manager.
GLAST LAT ProjectSeptember 15, 2006: Pre-Shipment Review 1 Integration and Test Presentation 11 of 12 GLAST Large Area Telescope: LAT Pre-Shipment Review.
GLAST LAT Project Technical/Cost/Schedule Review 06/30/ Integration and Test 1 GLAST Large Area Telescope: I & T Input to Monthly Technical/Cost/Schedule.
GLAST LAT Project Technical/Cost/Schedule Review 04/26/ Integration and Test 1 GLAST Large Area Telescope: I & T Input to Monthly Technical/Cost/Schedule.
GLAST LAT Project LAT System Engineering 1 GLAST Large Area Telescope: LAT System Engineering Pat Hascall SLAC System Engineering Manager
GLAST LAT Project LAT System Engineering 1 GLAST Large Area Telescope: LAT System Engineering Pat Hascall SLAC System Engineering Manager
1 GLAST LAT ProjectMechanical Systems Mechanical Systems September 2003 GSFC Status Marc Campell, Subsystem Manager.
GLAST LAT Project Integration and Test IFCT Peer Review 1 GLAST Large Area Telescope: I&T Integration Readiness Review Integration, Facility, Configuration.
GLAST LAT ProjectI&T&C Pre PDR Presentation– Oct. 2, 2001 E. Bloom1 Elliott Bloom Integration and Test and Calibration Manager
GLAST LAT ProjectDOE/NASA Baseline-Preliminary Design Review, January 8, 2002 Document: #1 GLAST Large Area Telescope: I&T Overview Elliott D. Bloom Stanford.
LAT Design Integration and Analysis1 GLAST LAT Project24 May 2005 LAT Monthly Status Review 24 May 2005 Design Integration and Analysis LAT Monthly Status.
GLAST LAT ProjectI&T&C Pre PDR Presentation– Oct 2, 2001 Darren Marsh1 I&T&C Organization Chart I&T&C Manager Elliott Bloom WBS I&T Engineer B. Grist.
GLAST LAT ProjectFace to Face, 14 April 2004 LAT System Engineering 1 GLAST Large Area Telescope: EGSE and Interface Verification Pat Hascall SLAC System.
GLAST LAT Project IFC Tour – Sep 5,2003 Larry Wai 1 GLAST Large Area Telescope: Integration and Facility Status Larry Wai SU-SLAC Integration and Facility.
GLAST LAT Project I&T Integration Kickoff Meeting 03/09/04 LAT I&T MGSE Page 1 of 11 GLAST Large Area Telescope: I&T Integration Kickoff Meeting MGSE March.
GLAST LAT ProjectMini-Review, 30 January 2003 LAT-PR-#####-## 1 I & T Responsibility LAT I&T, Verification, and Calibration Flow VibeRandom vibrate/sine.
GLAST LAT ProjectSLAC Internal Review, April 16-18, 2002 LAT-PR Electronics and Flight Software WBS GLAST Large Area Telescope: Electronics,
GLAST LAT ProjectNovember 18, 2004 I&T Two Tower IRR 1 GLAST Large Area Telescope: Integration and Test Two Tower Integration Readiness Review SVAC Elliott.
Bill Raynor Naval Research Lab
GLAST Large Area Telescope:
Mechanical Integration
GLAST Large Area Telescope:
Integration and Test GLAST Large Area Telescope:
GLAST Large Area Telescope:
GLAST Large Area Telescope:
GLAST Large Area Telescope: I&T Integration Kickoff Meeting
Integration and Test Organization Chart
GLAST Large Area Telescope:
GLAST Large Area Telescope:
Integration and Test Organization Chart
GLAST Large Area Telescope
Integration and Test Organization Chart
GLAST Large Area Telescope: I&T Test Readiness Review
Introduction and Overview
Presentation transcript:

GLAST Large Area Telescope: Gamma-ray Large Area Space Telescope GLAST Large Area Telescope: I & T Input to Monthly Technical/Cost/Schedule Review 01/27/05 Elliott Bloom SU-SLAC Subsystem Manager Ken Fouts Subsystem Engineering Manager elliott@slac.stanford.edu, kfouts@slac.stanford.edu 650-926-2469 650-926-2553

Last Month's Accomplishments Management 39 of 66 I&T documents and procedures in review/approval cycle. Supported successful receipt of TKR A. IFCT Completed receipt of CAL FM 102-105. Grid rework and heatpipe bonding complete. Completed check out and validation of test stands and work stations. MGSE PAP’s installed on LAT Integration Stand. Online Support update to CAL test suites. Supported data taking and trigger script development. Released LATTE 4.6.5 Completed pre-release version of LATTE 4.7 SVAC SVAC Pipeline running with new front-end interface. Processing TKR FMA with new code from SAS. Finalized definition of calibration for integrated tower. Particle Test VdG has worked reliably for 18 weeks since the last fix.

IFCT Accomplishments Mech. Systems Addition of purge groove pockets and chamfer of sharp edges complete Elec. Systems TVAC chamber checkout complete and chamber is operational. TKR Subsystem Completed TKR receiving and set-up for receiving and EMI test. Develop EMI taping process with TKR team. I&T Test Validation I&T Test Stand Set-up Procedure completed and released. Version 3 of CAL Module Test Procedure released. Validation process for Trigger Scripts in work Validation process for TKR Scripts in work Validation process for data collection scripts completed TEM/PS Shimming Procedure released. Prepared for dry run of TKR mechanical integration process (configuration of single bay, start installing flex cables on TKR EM)

MGSE Accomplishments PAP platforms have been integrated with the stand. Finalizing preparation and safety approvals for proof test.

I&T Milestone Overview for January 2005 FM101 Receiving inspection completed on FM Complete Calorimeter Test Stand Validated Post-ship test completed on FM Calorimeter CPT Software Validated on EM Calorimeter receiving CPT completed on FM TKR-A Installation procedure validated on EM Thermal strap procedure validated on EM Tracker flex cable procedure validated 2/18/05 Tracker CPT software validated TEM/TPS-A Tvac chamber installed in cleanroom Single Tower I&T Validation Metrology bay I&T validated on EM Complete Single Bay trigger tests validated on EM 2/7/05 Single Bay data collection validated on EM Grid Assembly Tilt table proof test Heat pipe bonding completed Thermal control system installation Rescheduled due to design change I&T Need 3/7/05 Integration Stand Delivery of GPR to I&T Earth quaking of base frame In Work (ECD TBD) Match GPR to Proof Test Weight 1

I&T Detailed Schedule

I&T Detailed Schedule

Procedure Status 66 documents total 39 have been submitted for sign-off 36 have been released

Procedure Status (1 of 6) - Management

Procedure Status (2 of 6) - MGSE

Procedure Status (3 of 6) – IFCT Electrical

Procedure Status (4 of 6) – IFCT Mechanical

Procedure Status (5 of 6) - Particle

Procedure Status (6 of 6) - SVAC

Cost and Schedule Status Cumulative Schedule Variance (end of December) Work Scheduled: 6144 k$; Work Performed: 5661 k$ Schedule Variance: -483 k$ (-8%) -141 k$ in MGSE Receive LAT Gnd Tst Heat Exchanger, Receive LAT Misc Equip and Fixtures, Receive LAT Vibration Test Fixture, Receive Misc LAT Transport Containers, Receive LAT Low Humidity Tent, Proof Test-LAT 4x4 Stand, Receive Rad & X-LAT Plate Lift Fixtures, Receive Ship Cont for LAT Vibe Test Equip, Prep and Proof Test 1 X 4, 1x1 Grid Lift Fixture -343 k$ in IFCT department Receive/Inspect Grid, Receive/Inspect TKR Tower A,B,1,2,3,4,5,6,7,8,9,10,11, Receive/Inspect CAL Module A,B,1,2,3,4,5,6,7,8, 9,10,11,12,13,14, Receive/Inspect Tower Electronics A,B,1,2,3,4,5,6,7,8,9,10,11,12,13,14,15,16, Integrate Flight TKR/CAL Towers A,B,1,2,3,4,5,6,7,8, Functional Test Tower A,B,1,2,3,4,5,6,7,8,9,10, Receive/Inspect Flight ACD, Receive/Inspect LAT-wide electronics, Receive/Inspect Cross-LAT Thermal Plate, Survey and Alignment Support of Inspection, Tower Integration Training, Fabricate Custom Connector Mate Tool, Power Supplies & Bus Protection Units, Comprehensive Test procedure development. Cumulative Cost Variance (end of December) Work Performed: 5661 k$; Actual Cost: 5958 k$ Cost Variance: -297 k$ (-5%) The actual variance should be -166k$ (-3%) due to an error in SLAC accounting of accruals.

Zero Schedule Variance Actions Complete MGSE tasks that are in flow for two tower and LAT build. Zero baseline variance requires matching I&T schedule to hardware deliveries. Current rebaseline will correct variances. Utilize TIMs with TKR and ELX to take advantage of lessons learned by subsystems prior to delivery.

Issues & concerns ISSUES Availability of flight assembly hardware. Shortages identified by I&T and being worked with Subsystems. CONCERNS MGSE Delivery Schedule MGSE Proof test (ECD 2/5/05) I&T Procedure Development Tracker Integration Procedure for Grid Installation. (3/14/05 Need date). TKR and Mechanical MOU’s require input from Subsytems.