4/25/11 G1100469-v3 1 Facility Modifications and Preparations (FMP) Technical Status Annual NSF Review of Advanced LIGO Project April 25 - 27, 2011 John.

Slides:



Advertisements
Similar presentations
LIGO-G M May 17, 2006 Installation (INS) Requirements and Design Breakout Presentation NSF Review of Advanced LIGO Project Dennis Coyne, Caltech.
Advertisements

G v1 H1 Squeezer Experiment Update L-V Meeting, Caltech, March 18, 2009 ANU, AEI, MIT, CIT and LHO Ping Koy Lam, Nergis Mavalvala, David McClelland,
Product Receiving, Storing, and Issuing
On-Site Services Spectrum BioScience … –Saves you time by Doing routine tasks non-core related –Saves you money… Connects you to researched sources of.
LIGO-G A-M April 5, 2006 Interferometer Sensing and Control (ISC) Cost and Schedule Breakout Presentation NSF Review of Advanced LIGO Project Richard.
G R LIGO Advanced System Test Interferometer LIGO Advanced R&D Review M. Zucker 8 October, 2002.
Q (Basic Laser Quizzes) 1 LIGO-G V3 LIGO (Laser) Safety Document Tree LIGO-M (LIGO Safety Program) LIGO-M (LIGO Laser Safety.
LIGO-G W Status of LIGO Installation and Commissioning Frederick J. Raab, LIGO Hanford Observatory.
LIGO-G D partial ADVANCED LIGO1 Optical Layout Cavity Lengths Input Mode Cleaner (IMC) »IMC FSR = ~9 MHz »Length = ~16.6 m = ~HAM1 to HAM3 separation.
LIGO-G0200XX-00-M LIGO Laboratory1 Pre-Isolation Dennis Coyne LIGO Laboratory NSF LIGO Annual Review, at MIT 23 October 2002.
LIGO-G M LIGO Laboratory1 Adv. LIGO Installation (INS) Plans, Schedule, Costs, Team Plan, Schedule Costs Team.
1 MOSFIRE is a Multi-Object Spectrometer for the Near Infra-Red (wavelengths ~ μm) We are deep in the component fabrication and procurement phase.
Dennis Coyne Excomm Jan 26, 2004
D. Schultz FAC 6/17/08 1 e-Beams Systems Update People Progress the last review LTU and Dump Installation Status Undulator.
LIGO-G D partial ADVANCED LIGO1 Development Plan R&D including Design through Final Design Review »for all long lead or high risk subsystems »LIGO.
20 Nov 2008G v21 Optical & Vacuum Equipment Layouts Dennis Coyne Mike Smith Luke Williams 20 Nov 2008 Adv. LIGO Team Meeting, Caltech, Pasadena,
LIGO-G M LIGO Laboratory1 Adv. LIGO Facilities Modifications (FAC) Plans, Schedule, Costs, Team Plan, Schedule Costs Team.
Rodd Pope, SLAC Undulator System April 20-21, 2006 FAC Meeting 1 Undulator System Assembly Plans Rodd Pope, SLAC In collaboration.
Laser Interferometer Gravitational-wave Observatory1 Characterization of LIGO Input Optics University of Florida Thomas Delker Guido Mueller Malik Rakhmanov.
LIGO-G W LIGO Hanford Observatory Infrastructure Frederick J. Raab, LIGO Hanford Observatory.
David H. Dowell Injector April 29-30, 2004 LCLS Injector Overview D. H. Dowell, SLAC FAC Review April 29-30, 2004 Injector.
LIGO-G M Status of LIGO Barry Barish PAC Meeting Caltech 3-June-04 Upper limits on known pulsar ellipticities.
LIGO-G M April 5, 2006 Interferometer Sensing and Control (ISC) Cost and Schedule Breakout Presentation NSF Review of Advanced LIGO Project Richard.
Hg Delivery System Fabrication Status V.B. Graves P.T. Spampinato Muon Collaboration Friday Meeting May 5, 2006.
LINACs Michael Bevins May 17, GeV Upgrade - Beam Transport Injection, Linac, Extraction, & Correctors Preliminary Design and Safety Review.
LIGO-G M Advanced LIGO Assembly & Installation Plan 14 Oct 2004 Dennis Coyne.
LIGO-G W Status of LIGO Installation and Commissioning Frederick J. Raab, LIGO Hanford Observatory.
LIGO-G v1 The LIGO Vacuum System and plans for LIGO-Australia Stan Whitcomb IndIGO - ACIGA meeting on LIGO-Australia 9 February 2011.
LIGO-G v5 1 Pre-stabilized Laser System (PSL) Technical Status NSF Review of Advanced LIGO Project Benno Willke, AEI Hannover and the AdvLIGO PSL.
LIGO-G M May 31-June 2, 2006 Input Optics (IO) Cost and Schedule Breakout Presentation NSF Review of Advanced LIGO Project David Reitze UF.
LIGO-G M Management of the LIGO Project Gary Sanders California Institute of Technology Presented to the Committee on Programs and Plans of the.
LIGO-G M 1 Conceptual Design Review: Initial LIGO Seismic Isolation System Upgrade Development, Implementation Plan & Schedule Dennis Coyne April.
Livingston 16 th August 2006 LIGO-G E HAM SAS Passive Seismic Attenuation System Fabrication, Assembly, Installation Ben Abbott, Valerio Boschi,
LIGO- G D Status of LIGO Stan Whitcomb ACIGA Workshop 21 April 2004.
Injector/Re-injection Chicane Michael Bevins May 17, GeV Upgrade - Beam Transport Injection, Linac, Extraction, & Correctors Preliminary Design.
LIGO- G D The LIGO Instruments Stan Whitcomb NSB Meeting LIGO Livingston Observatory 4 February 2004.
E v3 aLIGO SEI Testing and Commissioning Overall Plan
G Z LIGO R&D1 Input Optics Definition, Function The input optics (IO) conditions light from the pre- stabilized laser (PSL) for injection into.
Americas Region: T4CM Status and Plans H. Carter TD SRF Dev. Dept. July 14, 2006.
LIGO-G M Organization and Budget Gary Sanders NSF Operations Review Caltech, February 26, 2001.
D Walters Undulator Systems – BFW April 30, 2008 Production Status of the Quad Spool J Morgan – Engineer Bellows Module Soon-Hong.
1Page # Machine Assembly WBS 700 By: James H. Chrzanowski January 24, 2001.
Vacuum, H-C. Hseuh January 4, 2007 RHIC II Project Internal Cost Review Vacuum Systems H.-C. Hseuh January 4, 2007 Vacuum Systems.
1 Status of Vacuum Process Facilities at SSL 16 October 2009 Sharon R Jelinsky Space Sciences Laboratory, UC Berkeley.
Extraction Michael Bevins May 17, GeV Upgrade - Beam Transport Injection, Linac, Extraction, & Correctors Preliminary Design and Safety Review.
1 FVTX Detector Assembly Stephen Pate New Mexico State University (FVTX Assembly Management WBS 1.7) Stephen Pate, NMSU – FVTX Review – 16-Nov-2009.
ESS WP 12 Project Management & Capabilities Overview Neil Bliss Projects & Mechanical Engineering Group Leader ESS PDR, Lund, 10 th November 2015.
Spectrometer Solenoid Fabrication Status and Schedule RF Cavity / Coupling Coil Module Plan and Progress Steve Virostek Lawrence Berkeley National Lab.
LIGO-G M Advanced LIGO Cost, Schedule and Management Gary H Sanders NSF Review of Advanced LIGO Caltech, June 11, 2003.
LIGO-G M LIGO Status Gary Sanders GWIC Meeting Perth July 2001.
February 17-18, 2010 R&D ERL Gary McIntyre R&D ERL ERL Status & Schedule Gary McIntyre February 17-18, 2010 ERL Status & Schedule.
CMS Upgrade Workshop, FNAL, Oct 28-30, O.Prokofiev Update ME4/2 Chambers and Tooling A construction of new ME4/2 prototype at CERN Factory tooling,
G R Interferometer Sensing & Control P Fritschel 8 Oct 02.
LIGO-G M Overview of the LIGO Continuing Operations (FY FY2006) Proposal Gary Sanders LIGO PAC9 Meeting December 2000.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
LIGO-G M State of the LIGO Laboratory Gary Sanders LIGO/Caltech LSC Meeting, LLO March 16, 2004 State of LIGO.
ALD Technology Transfer – Progress Update LAPPD2 Godparent Review Aileen O’Mahony 5 th April 2013.
Page 1 Coles – Operating the Observatories PAC 9 Dec. 13, 2000 G L Operating the Observatories Mark Coles.
G R 2004 Plan Update LIGO Systems meeting 22 Jan 04 dhs.
Tech Site Jobs. Order Fulfillment Duties Maintain bagged room temperature kit components. Assemble kits for shipment. Inform other groups about kit needs.
PSL APA Update May 3, 2016 UW Physical Sciences Lab.
Data Acquisition, Diagnostics & Controls (DAQ)
LIGO LAB R&D PROGRAM TECHNICAL REVIEW, OCT 02
Auxiliary Optical Systems - AOS
UK RFD Pre-Series cryomodule
Status of LIGO Installation and Commissioning
LIGO Advanced System Test Interferometer
P Fritschel LSC Meeting LLO, 22 March 2005
Improving LIGO’s stability and sensitivity: commissioning examples
Undulator Cost & Schedule Patric Den Hartog, ANL April 24, 2002
Presentation transcript:

4/25/11 G v3 1 Facility Modifications and Preparations (FMP) Technical Status Annual NSF Review of Advanced LIGO Project April , 2011 John Worden LHO

4/25/11 G v3 FMP Functions Prepare for assembly tasks (buildings, laboratories): $3M, WBS.2.1,.3,.5 Create spaces for use as clean assembly areas Procure large, soft-walled, clean rooms for assembly Procure vacuum bake ovens, parts washers. Create clean/bake & conditioned storage space Purchase supplies for wrapping, palletizing, storing assembled components Purchase additional material handling equipment, installation fixtures, optics lab supplies, clean room supplies, etc. Store completed assemblies Provide clean/bake service, support the assembly groups. Design & Build Vacuum System Modifications $5.7M, WBS.4 Convert 2 km at Hanford Observatory to 4 km Move HAM Chambers for Input Optics (IO) and Interferometer Sensing & Control (ISC) use Supply new IO tubes (input and output mode cleaner tubes) Prepare for installation tasks: $2.4M, WBS.1,.2.2,.2.3,.2.4 Stage completed assemblies, procure installation equipment Does not include installation (INS WBS scope) or system/subsystem test/acceptance (PM/systems WBS scope) 2 Budget total for FMP ~$12M DONE Underway with GNB Corp.

4/25/11 G v3 3 FMP Requirements Parts processing and assembly performed in Class 100 clean room work spaces. Processing includes either vacuum bake or air bake (for large plates) to remove Low-Volatile Residue (out- gassing) Clean storage for parts and completed assemblies. Track processing and storage of parts and assemblies. New IO Tubes to meet LIGO vacuum requirements, new mid/end station spools for 2K-4K conversion.

4/25/11 G v3 FMP Status Work spaces completed and commissioned fall of 09. Ongoing effort to support assembly activity – clean and bake, shipping/receiving, packaging, storing, hiring techs. This is a bigger effort than originally thought. Procurement activity for IO Tubes/Vacuum System mods – –GNB – contract awarded in April 2010, first components undergoing vacuum bake April 2011 with shipment of Mid Station Spools by end of April. 4

4/25/11 G v3 aLIGO Corner Station LHO

4/25/11 G v3 aLIGO End Station LHO

4/25/11 G v3 Assembly Space LHO 7

4/25/11 G v3 Clean/Bake LHO 8

4/25/11 G v3 LHO HEPI Pump Carts 9

4/25/11 G v3 Assembly Space LLO 10

4/25/11 G v3 Clean/Bake LLO 11

4/25/11 G v3 LLO: 3 Vacuum Bake Ovens 1 large Air Bake Oven LHO: 3 Vacuum Bake Ovens 1 large Air Bake Oven  Vacuum Bake Oven  Vacuum Prep Warehouse Drying Station  Clean Parts ready for HAM-ISI assembly 12 Clean & Bake

4/25/11 G v3 FMP to do Design & Build Vacuum System Modifications WBS.4 Convert 2 km at Hanford Observatory to 4 km Move HAM Chambers for Input Optics (IO) and Interferometer Sensing & Control (ISC) use Does not include installation (INS WBS scope) Get RFP out on the street in Fall of 2009 Underway: Procure H2 Electronics Building – Slab is in place, modular building delivery ~May 5 ($130K) Procure Install Cleanrooms. – First delivery has arrived at LHO. ($384K) Procure Cartridge Install Test Stands. – First unit complete April 28 ($296K) Procure Cartridge Install Work Platforms. - In design and fab with vendor ($472K) Remaining work: HVAC required for H2 electronics building, H1 electronics, PSL Diode Room Mezzanine for H1 electronics. 13 Fabrication underway.

4/25/11 G v3 Mid Station Spool Washing

4/25/11 G v3 MC Tube Rollups

4/25/11 G v3 Cartridge Install Test Stand

4/25/11 G v3 Work Platforms

4/25/11 G v3 Install Cleanrooms

4/25/11 G v3 Challenges, risks, and mitigations Low technical risk Maintaining Particulate Cleanliness Handling the Simultaneous Assembly Tasks and Space Needs will be Challenging Will need to fit “noisy” construction activities around operating IFO schedules. Safety – assembly and on site transport of heavy components (8000 pounds for assembled BSC system). New laser safety issues – higher power in test labs. Track and store many parts – will need some manpower and an inventory system to control incoming materials as well as completed components. Small quantities of cleaning fluids to be stored and disposed of. Not new for us. 19

4/25/11 G v3 FMP Near term activities Take delivery of new Vacuum components and supervise the install. Install modular building for H2 electronics. Procure HVAC for H2 modular building, H1 and Laser Diode room. 20