Site Report Poroton Home to Building shell – in record time
In record time to the complete building shell Location: Trier Outside wall: ThermoPlan T10 Inside wall: Planziegel Hlz Incl. special bricks Team: 3 workers (1 master craftsman, 2 assistant ) Constr. period: 5 days for the complete building shell.
The bottom slab is casted
The first delivery
Professional discharging
The second delivery... Everything has to be at it‘s place.
The first layer
After 4 hours, the first layer is ready
Now, the plan-bricks have to be worked up
Brick after brick
Some hours later-The building is growing fast
The result of one day
The next day - The inside walls
Nearly ready
After 30 hours with 3 workers
During the time lag of ceiling delivering – the garage was built
Bricks for the top floor
Again – the first layer is ready
Exact plans allowed the preparation of the bricks for the pitch
Usage of U-Blocks for the ring armature
The ring armature encloses the masonry
Some details
Working with concrete is finished
Inside walls in top floor
Now, the truss can be constructed
Craftsmanship – just great
Insulation at the ring armature....
Finished
The result of 120 hours work
Finally The complete building shell was finished after 5 days. -With 1 craftsman and 2 helpers -Top quality, 100% brick A brickhouse makes you happy