Roads And Bridges Development Corporation of Kerala LTD

Slides:



Advertisements
Similar presentations
ODOT Structure Project Manager Training
Advertisements

Session 12 STEPS 3 AND 4. Stage 2 Detail Design Submission should include an updated cost estimate and the following: (Not every item listed will apply.
SEMINAR ON SEGMENTAL CONSTRUCTION OF BRIDGE
Connection Details for Prefabricated Bridge Elements and Systems
July Training Outline Part 1 Cost-per –SF and Detailed Estimate Pay Item Detailed Estimate Segments Bridge Level Data Segment Level Data Supports.
Grade Separation (GS-16) Project. Project Location - Bensenville N.
Indianapolis Airport Interchange Bridges Presented to: TRB Bridge Aesthetics Subcommittee January 11, 2005.
Current Status of Japanese Road Bridges and Future Perspective
Findings from On-site Inspection (Rt 202/US Rt 23 BRIDGE)
MDOT ACTT Workshop Structures I-94 From I-96 to East of Connor Participants Steve Stroh, URS Corp Vijay Chandra, Parson Brinckerhoff Raj Ailaney, FHWA.
Bridge Engineering (6) Superstructure – Concrete Bridges
Structural System Overview
TEQIP-II Institutions
Art Nowak February 2013 STRUCTURE DESIGN MANUAL 1.
Bridge over BNSF Railroad 7 km East of Windham - East Bridge Replacement Project Using Accelerated Bridge Construction.
SHRP2 Project R04 Bridge Designs for ABC
Chapter 34 Bridge Construction.
DEPARTMENT OF PUBLIC WORKS BUREAU OF ENGINEERING & CONSTRUCTION STRUCTURAL DESIGN SECTION REPLACEMENT OF BRIDGE NO. B-0427 ON DAIRY ROAD OVER OWL BRANCH.
Bridge Engineering (7) Superstructure – Reinforced Concrete Bridges
3 June Rapid Replacement of the Hood Canal Bridge Approach Spans Joseph Merth, P.E. Bridge Design Engineer 3 June 2008.
Reconstruction of the Eads Bridge Highway Deck
Road to Prosperity. UP GRADATION OF AIRPORT SEAPORT ROAD TO FOUR LANE -PHASE I – PROGRESS REPORT AS ON Upgrdadation of airport seaport.
Damage Illustrations. Potential Bridge Damage Bridge Component / DamagePossible Cause Approach Slab or Pavement  Raised, lowered, cracked, or buckled.
Bridge Maintenance and Repair.
Schematic Design of an Accelerated Bridge Construction Project Michael P. Culmo, P.E. Vice President of Transportation and Structures CME Associates, Inc.,
ODOT Policy for Deck/Slab Closure Pours Sean Meddles, P.E. Assistant Administrator ODOT Office of Structural Engineering.
Bridge Structure Types and Components. BRIDGE STRUCTURE TYPES AND COMPONENTS TECHNICAL STANDARDS BRANCH INTRODUCTION TO BRIDGES TRANSPORTATION Slide 2.
RM Product Update October 2009 Alexander Mabrich, PE, Msc Senior Engineering Consultant.
Public Information Meeting Rehabilitation of Bridge No Flat Rock Hill Road over I-95 Old Lyme, Connecticut Rehabilitation of Bridge No Flat.
Introduction to a pit installation
Bridge Engineering (5) Substructure – Abutments and Piers
Road to Prosperity. UP GRADATION OF AIRPORT SEAPORT ROAD TO FOUR LANE -PHASE I – PROGRESS REPORT AS ON Upgrdadation of airport seaport.
St Johnsbury BF 7000(20) Bridge 6 on VT Route 2B over the Lamoille Valley Rail Trail Presenter: John Byatt, PE Consultant Project Manager.
Dedicated Freight Corridor By CHAHATEY RAM CBE/ER.
St. Croix River Crossing S.P Contractor Informational Meeting May 15, 2013 Contact: Paul Kivisto, P.E. St. Croix Crossing Bridge Construction.
PROJECT REPORT DESIGN CONCEPTS OF BOW STRING GIRDER (40 M SPAN) OF ROAD OVERBRIDGE AND DESIGN OF SUB STRUCTURE FOR THE SAME.
Presented by: Department of Transportation - Toll Bridge Program New Benicia-Martinez Bridge Project.
Concrete Barrier placed at unauthorized median at Ch
ROB at Koratty in lieu of LC No.54 Progress as on
BANDRA-WORLI SEA LINK BY : PRAJAPATI NIHAR V..
There are 2 Types of Bridge Inspectors – Class B and Class A.
1. 2 ONGOING PROJECT -1-ROB AT PARAPPANANGADI-PROGRESS GRAPH
BIM Bridge Inspection and Maintenance Technical Standards Branch Class B Bridge Inspection Course Bridge Maintenance BRIDGE MAINTENANCE.
VT 100 over the Mad River Bridge Replacement July 13, 2015.
Miscellaneous Bridge Components
FOUNDATIONS.
Condition of Prestressing of the Ft. Lauderdale- Hollywood Airport Deconstructed Segmental Bridges Luis M. Vargas Beiswenger Hoch and Associates.
Construction Methodology for Suramadu Main Bridge.
TOTAL BRIDGE REPLACEMENT OF M-13 OVER CHEBOYGANING CREEK
Inspection Form Types Each form has a unique
Offsite manufactured Bridges
Required Drawings and Info for Formwork or Scaffold Design
There are 2 Types of Bridge Inspectors – Class B and Class A.
Engineering Terms Bridge Unit.
Oregon DOT Integral Abutment Design Criteria
Project Purpose and Objective
Danube Bridge Vidin – Calafat
Micro Pile to Concrete Connection
INTEGRAL BRIDGES Guided by: Dipu.V.S Lecturer Civil Engg Dept
New Bridge Construction
ROB at Pulianam Progress as on
Project members ROB at Mulamkunnathukavu Progress as on
By T.G.N.C.VAMSI KRISHNA. 171FB M.tech – Civil.
Course Contents Culverts Bridges Buildings 20 November 2018.
WE-WC Almaty – Khorgos Road Section Materials prepared in %
THE UPGRADE OF 33.7 KM OF NATIONAL ROUTE N2, BETWEEN MTUNZINI TOLL PLAZA (SECTION 28, KM 42.7) AND EMPANGENI T-JUNCTION (SECTION 29, KM 13.0) CONTRACT.
Western Europe – Western China motor road “Almaty-Khorgos”
Narrows Bridge - Perth Concrete Repair Works
Protective surface finishes
Micro Pile to Concrete Connection
Presentation transcript:

Roads And Bridges Development Corporation of Kerala LTD Road to Prosperity Project Review Meeting – 1st July 2015

ONGOING PROJECTS FLYOVER AT PALARIVATTOM ROB AT ALOOR-MALA ROB AT ANGADIPURAM 4. RIVER BRIDGES AT MAHILALAYAM-CHOWARA Seaport Airport Road Phase II Section B 5. ROB AT KUMARANALLOOR 6. ROB AT KUNHIPPALLY 7. ROB AT EROOR 8. ROB AT DIVINE NAGAR

FLYOVER AT PALARIVATTOM

PROGRESS STATUS All substructure works completed Girder casting (68/122) completed 20 girders launched; 6 on Edappally side and 14 on Vyttila side. Service road on Edappally and Vyttila sides completed up to DBM. Casting of precast drain started.

WORKS DURING JUNE 2015 TARGETED ACHIEVED Pier – 1 no (P18) Pier cap – 1 no (P18) Girder casting – 15 nos Girder Launching – 18 nos Precast Drain – 200 m Deck Slab – 2 nos Pier – 1 no (P18) Pier cap – 1 no (P18) Girder casting – 18 nos Girder Launching – 18 nos Precast Drain – 62 m Deck Slab – Zero

PROGRESS GRAPH

Launched Girders in AP1-P1 span Casting of precast drain PROGRESS PHOTOS Girder Concreting Girder Launching Launched Girders in AP1-P1 span Casting of precast drain

ROB AT ALOOR-MALA

PROGRESS STATUS All superstructure works and approach road completed except wearing coat of one adjacent span. The balance works include painting, road marking, construction of staircases and toll booth. Railway span is being executed by RAILWAYS. The parapet wall to be constructed.

PROGRESS GRAPH

CC Wearing coat in adj.span Reinforcement for adj.span PROGRESS PHOTOS CC Wearing coat in adj.span Expansion joint Painting Reinforcement for adj.span

ROB AT ANGADIPURAM

PROGRESS STATUS Piling completed. Pile cap (13/18), Pier (11/18), Pier cap (9/18) and Girders (3/54) are completed. 45% of retaining wall and 40m drain completed on Angadipuram side.

WORKS DURING JUNE 2015 TARGETED Pier cap – 1 (P14) Girder – 1 (P3-P4) Deck Slab – 1 (P3-P4) Retaining wall (Angadipuram side) – 100% Service road (Perinthalmanna side) – 100% Drain – 100m Building Dismantling – 100% ACHIEVED Pier cap – 1 (P14) Girder – 1 (P3-P4) Deck Slab – Zero Retaining wall (Angadipuram side) – 45% Service road (Perinthalmanna side) – 0% Drain – 40m Building Dismantling – 95%

PROGRESS GRAPH

Drain work on Angadipuram side PROGRESS PHOTOS Drain work on Angadipuram side Building dismantling Road repairing Girder P3 – P4

RIVER BRIDGES AT MAHILALAYAM-CHOWARA Seaport Airport Road Phase II Section B

PROGRESS STATUS OF MAIN BRIDGE All works up to Pier cap completed Girders (40/48) casted and 36 girders launched Deck slabs (6/12) casted.

PROGRESS STATUS OF MINOR BRIDGE Pile (13/17), Pile cap (4/5), Pier (4/5), Pier cap(4/5) and Girders (10/16) are completed.

WORKS DURING JUNE 2015 TARGETED ACHIEVED Main Bridge Girder – 4 nos (2 nos each in P1-P2& P2-P3) Girder Launching – 8 nos (4 nos each in P2-P3 & P3-P4) Deck Slab – 1 (P6-P7) Minor Bridge Girder – 2 nos(P2’-P3’) Main Bridge Girder – 3 nos (1 no in P1-P2& 2 nos in P2-P3) Girder Launching – 4 nos (4 nos in P3-P4) Deck Slab – 1 (P6-P7) Minor Bridge Girder – 1 no(P2’-P3’)

PROGRESS GRAPH

PROGRESS PHOTOS

ROB AT KUMARANALLOOR

PROGRESS STATUS The ROB was inaugurated and opened to traffic on May 24,2015. Construction of staircases and toll booth to be completed.

ROB AT KUMARANELLUR

ROB AT KUNHIPPALLY

PROGRESS STATUS All works up to pier cap completed Out of 16 spans, girder and slab casting completed in 14 spans Expansion joint and kerb works completed in 12 spans Handrail work completed in 8 spans Retaining wall on Monthal side completed Retaining wall on NH side to be started. Here work can be completed only after getting possession of land owned by Late Dr. Irfan Habeeb.

WORKS DURING JUNE 2015 TARGETED ACHIEVED Girder – 1 (Adjacent span on Monthal side) Expansion joint – 3 nos Handrail – 5 spans Painting (P5-P6) – 30% Drain (Monthal side) –Complete Retaining Wall (Monthal side) – Complete Dirt Wall – 2 nos (A1,A2) Girder – Zero (Adjacent span on Monthal side) Expansion joint – 3 nos Handrail – 5 spans Painting (P5-P6) – 20% Drain (Monthal side) – 98% Retaining Wall (Monthal side) – Complete Dirt Wall – 1 no (A2)

PROGRESS GRAPH

Diversion Road-Monthal side PROGRESS PHOTOS Diversion Road-Monthal side Staging Work Dirt Wall – A2 Painting in Progress

ROB AT EROOR

PROGRESS STATUS Piling completed. Pile cap (7/10), Pier (4/10) and Pier cap (4/10) are completed. Slab casting started and (1/10) is completed Construction of service roads to be started

WORKS DURING JUNE 2015 TARGETED Pile – 7 nos (2 nos in P8 & P7, 3 nos in A2) Pile cap – P5,P6,P7 Pier – P5,P6,P7 Drainage – 50 m Span – 2 (P2-P3 & P1-P2) ACHIEVED Pile – 7 nos (2 nos in P8 & P7, 3 nos in A2) Pile cap – P5,P6 Pier – Zero Drainage – 50 m Span – 1 (P2-P3)

PROGRESS GRAPH

PROGRESS PHOTOS Pile Casting Staging for P1-P2 span Placing of Voids in span P2-P3 View from P2 – P3 span

ROB AT DIVINE NAGAR

ADJACENT SPANS OF DIVINE NAGAR ROB Casting of Slab in adjacent span RP1-P6A completed Handrail and Kerb works started in RP1-P6A span. Setting out completed for constructing staircase at Divine Side Works in adjacent span RP2-P7 to be started

PROGRESS GRAPH

ADJACENT SPAN RP1-P6A Kadukutty Side