Expo Line Transit Project Exposition Light Rail Transit Project Expo Board Presentation Monthly Project Status Update April 2, 2009.

Slides:



Advertisements
Similar presentations
Planning and Development Committee West Corridor Update May 10, 2007.
Advertisements

California High-Speed Train Project Los Angeles Union Station Alternatives Analysis January 7, 2010 Board Presentation.
Phase 1 Project Status: Design Continued development of alternative station design concepts for stations in the vicinity of USC and Expo Park Received.
Chicago Transit AuthorityJune, 2007 Chicago Transit Authority Regional South Metro Transportation Summit June 16, 2007 Matteson, Illinois.
LIGHT RAIL PERMITTING ADVISORY COMMITTEE COMMITTEE MEETING Dec. 17, 2014|3:00PM -5:00PM | ROOM 1E-113.
1 TOWN OF NEWMARKET FLOODING ON SEPT. 13, 2006 Committee of the Whole February 5, 2007.
US Army Corps of Engineers BUILDING STRONG ® FOLSOM DAM MODIFICATIONS APPROACH CHANNEL EIS/EIR Major Robert Dion and Cameron Sessions Project Managers.
Jan. 16, 208 CoW1 - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Committee of the Whole January.
City/University Projects Fund Calendar Year 2012 Budget Request.
Building Innovative Facilities for a Multimodal Future 2014 BICYCLE MASTER PLAN UPDATE FINAL PUBLIC REVIEW Baltimore City Department of Transportation.
Division of Local Assistance Office of Special & Discretionary Programs December 2, 2010.
Texas Department of Transportation Corpus Christi District Harbor Bridge Project U.S. 181 (Harbor Bridge)/SH 286 (Crosstown Expressway) Agency Scoping.
Anaheim Regional Transportation Intermodal Center Project Update.
Presentation Outline Summary of efforts-to-date Broward County LRTP Amendment Process Next steps.
1 November Accomplishments: Design and Construction Began sanitary sewer, gas, waterline and electrical relocations between 18th and 23rd Streets Continued.
Department of Transportation Final Recommendation of SR-710 Pasadena Working Group Regarding Proposed Alternatives for SR-710 North Project Council Meeting.
Anacostia Streetcar Phase 2 Environmental Assessment & Section 106 Evaluation: Community Workshop January 12, 2011.
Phase 1 Project Status: Design Received 60% design submittal for 5 Work Packages: C1, Utility Improvements, Harcourt to Venice C2, Corridor Improvements,
Project Update & The Success of the Integrated Project Management Office Metro Goldline East Extension Los Angeles January 19, 2007 ASCE Construction Institute.
Ottawa’s Light Rail Transit Project OLRT Tunnel Geotechnical Update Technical Briefing December 21, 2010 John Jensen Director Rail Implementation Office.
Capital Improvement Program. During the Annual Strategic Action Plan (SAP) evaluation, long-term needs and priorities are identified by City Council Capital.
Regional Transportation Investments: Alaskan Way Viaduct / Seawall Port of Seattle Commission Meeting March 28, 2006 Item No. xx Supp. Meeting.
Mid-City Exposition Light Rail Transit Project Closed Session Presentation March 2, 2006 Exposition Metro Line Construction Authority.
NCSX Management Overview Hutch Neilson, NCSX Project Manager NCSX Conceptual Design Review Princeton, NJ May 23, 2002.
1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Construction Status Michael P. Bromfield Construction Engineer NSLS II Conventional Facilities Advisory Committee.
CCJPA Sacramento to Roseville 3 rd Track Project Sacramento Stakeholder Advisory Committee (SAC) Meeting #1 HDR Office Tuesday, May 20, :00 - 9:00.
Project Status: Design Initiated development of alternative station design concepts for stations in the vicinity of USC and Expo Park Received 85% design.
Department of Transportation Consideration of Potential City of Pasadena Position Related to SR710 Extension Alternatives Being Considered By Metro City.
Metro Gold Line Eastside Extension Four Quadrant Gate Feasibility Study Summary.
Fendering Update The following activities are anticipated over the next quarter: Review of alternate designs for fendering Meet key stakeholders and regulatory.
December Accomplishments: Design and Construction Continued trenching for and laying of storm drain pipe in Flower Street from I -110 to 23rd Street Started.
Planning & Community Development Department 1336 and 1347 East Colorado Blvd. Pre Development Plan Review City Council Meeting January 28, 2013.
LIGHT RAIL PERMITTING ADVISORY COMMITTEE COMMITTEE MEETING Jan. 21-3:00PM | ROOM 1E-113.
1 August Accomplishments Conducted the 4 th Urban Design Committee meeting, which consisted of a tour of the Metro Orange Line. Conducted one-on-one briefings.
Expo Line Transit Project Exposition Light Rail Transit Project Expo Board Presentation Monthly Project Status Update January 14, 2008.
May’s Accomplishments Mobilized Authority and Design Build Contractor staff to Authority offices at 707 Wilshire Three Open House meetings were held in.
Regional Transportation Investments: Alaskan Way Viaduct / Seawall Port of Seattle Commission Policy and Staff Briefing March 14, 2006 Item No. xx Supp.
July Accomplishments: Authority and Design Build Contractor staff conducted the 3rd Urban Design committee meeting. Committee members viewed proposed station.
Texas Department of Transportation Corpus Christi District Harbor Bridge Project U.S. 181 (Harbor Bridge)/SH 286 (Crosstown Expressway) Citizens Advisory.
February’s Accomplishments Met extensively with FTA staff and received the Record of Decision from FTA Finalized Negotiations with the top ranked Design.
OLDE TOWN ARVADA TOD Update to RTD Board September 3, 2013
Bond Oversight Committee Meeting Fourth Quarter 2015 January 26, 2016.
Exposition Light Rail Phase 2 - Recommendation for Alternative Siting of Maintenance Facility within the City of Santa Monica.
Metro Gold Line Foothill Extension March 5, 2016 Opening.
Major Project Scoping Committee.  Two previous studies to develop improvements for the I-35W Corridor ◦ Project Limits were from 42 nd to I-94 ◦ Project.
Indian Hill Boulevard Grade Separation Proposal, January 25, 2016.
Planning Commission Study Session: Preferred Plan July 23, 2015.
Indian Hill Grade Separation City Council Meeting February 23, 2016.
North Metro Competitive Procurement RTD Board FasTracks Monitoring Committee October 8, 2013.
City and County of San Francisco Scoping Meeting Environmental Impact Report (EIR) PURPOSE To solicit participation in determining the scope.
California State Lands Commission February 20, 2015.
Waterdown Road Corridor Class Environmental Assessment (Phase 3 & 4) Community Services Committee May 9, 2012.
December 17,  MnDOT signed a highway easment in 1960 with US Steel  The TH 53 is over a ore deposit with shallow strippings, high iron and low.
Planning & Community Development Department Olivewood Village Project (530, 535 E. Union St., 95, 99, 119 N. Madison Ave. and 585 E. Colorado Blvd.) Predevelopment.
CITY COUNCIL OCTOBER 18, 2011 Central Park Gazebo Replacement.
I-225 Rail Line Chuck Culig, Project Manager Tuesday, April 2, 2013 RTD Board of Directors Update.
Richland Creek Water Supply Program Update Paulding County, Georgia Board of Commissioners Work Session March 08, 2016.
Expo Line Transit Project Exposition Light Rail Transit Project Expo Board Presentation Monthly Project Status Update October 2, 2008.
2015 Annual Program Evaluation (APE) Status Update July 14, 2015.
The Plaza at Santa Monica Project PUBLIC SCOPING MEETING
Northwest Area Mobility Study FasTracks Monitoring Committee
City Council Meeting November 7, 2016
Robinson Park Recreation Center Renovation
Willow Meadows Civic Club Meeting September 13, 2011
Eagle P3 Project Update RTD Board of Directors Sept. 2, 2014.
Phase 1 Project Status: Design
Endorsement of the Recommended Design Concept (Preferred Alternative) for Transforming I-66 Outside the Beltway Board Transportation Committee October.
2014 Annual Program Evaluation (APE) Status Update
Los Angeles County Metropolitan Transportation Authority
Contract Award for the Colorado Street Bridge Suicide Mitigation Enhancements Project City Council May 20, 2019 Item # 7.
Presentation transcript:

Expo Line Transit Project Exposition Light Rail Transit Project Expo Board Presentation Monthly Project Status Update April 2, 2009

Expo Line Transit Project PHASE 1

Expo Line Transit Project Design  Baseline Design is approximately 96% complete  Venice/Robertson design is 92% complete Construction  Construction is approximately 35% complete Construction Packages  Negotiated 15 of the 20 construction packages totaling $362 million Project Budget  Currently within the construction and overall project budget  There are still outstanding issues that could pose a significant risk to the budget Phase 1 Project Status

Expo Line Transit Project Phase 1 Project Status Project Schedule  Contractor’s latest schedule update shows a 32-week project delay Delay in completing the cable design for LADWP overhead power lines at the La Cienega structure is driving most of the delay Delay in starting the Flower/Adams overcrossing due to need to complete 100% drawing comments required for Caltrans permits/approval Delays in the wire pulling associated with LADWP overhead power lines at the La Brea structure Authority has requested a recovery schedule from the contractor  Areas of potential further delay Incorporation of the Pedestrian Overcrossing at Farmdale Ave Culver City aerial station Storage and Inspection Facility Blue Line Tie-In

Expo Line Transit Project Current Construction Activities  Continued placing concrete for the trench invert slab and began rebar installation for the trench wall (Seg A)  Continued retrofit of Caltrans Flower Street Bridge over the I-110 Freeway (Seg A)  Completed installation of reinforcing steel and began placing concrete for Western Avenue Station (Seg B)  Continued installing structural backfill for Abutment No. 1 at La Brea Overcrossing Structure (Seg C)  Continued setting wall form panels for Abutment No. 6 at La Cienega Overcrossing Structure (Seg C)  Began falsework for the La Brea Overcrossing Structure (Seg C) Phase 1 Project Status

Expo Line Transit Project Slab Placement and Wall Rebar Installation at Trench Structure Construction Progress

Expo Line Transit Project Flower Street Overcrossing Above I-110 Freeway After Completion of Girder Demolition Construction Progress

Expo Line Transit Project Construction Progress Concrete Placement for Western Avenue Station— East Platform Footings

Expo Line Transit Project Conduit Installation at Exposition Portal of Trench Structure Construction Progress

Expo Line Transit Project Erection of Falsework for La Brea Overcrossing Structure Construction Progress

Expo Line Transit Project Project Issue Summary  Harvard Pedestrian Tunnel Contractor is assembling CIDH cages for structural reinforcement over the pedestrian tunnel Staff is developing an initial list of potential pedestrian safety improvements that could possibly be implemented at Foshay Learning Center  Staff is coordinating the possible improvements with CD 8, LADOT, CPUC, Metro and LAUSD  Staff will prepare and submit a report to the CPUC’s Consumer Protection and Safety Division no later than May 20, 2009 Phase 1 Project Status

Expo Line Transit Project Project Issue Summary (Cont.)  Farmdale Pedestrian Overcrossing Staff has completed the Draft CEQA and NEPA Document  Staff met with CPUC Environmental Staff to discuss project status  The Draft CEQA/NEPA Document will be submitted to FTA and CPUC this week for review  Begin Preliminary Engineering on the Farmdale Pedestrian Overcrossing and closure of Farmdale Avenue  Began assembling the amended application for submittal to CPUC  Storage and Inspection Facility CEQA/NEPA environmental clearance received Completion of design scheduled for Fall 2009 Construction completion anticipated for Fall 2010 Phase 1 Project Status

Expo Line Transit Project Project Issue Summary (Cont.)  Proposed Joint Development at Venice/Robertson Station Culver City is contemplating a joint development project adjacent to the Venice/Robertson station  Culver City has committed to reimburse design costs associated with modifications to the LRT bridge foundations to accommodate a subterranean parking structure  A reimbursement agreement is needed to cover the differential in construction costs should Culver City’s design be implemented  A decision by Culver City is needed this month in order to begin the steel fabrication required for the City improvements Phase 1 Project Status

Expo Line Transit Project Phase 1 Project Status Government/Community Relations  Held Expo Park/USC Station groundbreaking media event on March 6, 2009 (Seg A)  Provided project status updates to the following organizations: Figueroa Corridor Business Improvement District (Seg A) Baldwin Villas Senior Center (Seg B)  Attended regularly scheduled meetings, including: Ted Alexander Elementary School PTA Meeting (Seg B) West Adams Neighborhood Council Meeting (Seg B) South Robertson Neighborhoods Council Meeting (Seg C)  Hosted an informational booth at 7th & Fig Farmers Market  Attended monthly update meeting with USC and Expo Park to discuss coordination of events and construction activities  Attended bi-monthly coordination meetings with LA Trade Tech staff to discuss construction activities, impacts and mitigation measures

Expo Line Transit Project PHASE 2

Expo Line Transit Project DEIR Release and Public Comment  Public comment period began on January 28, 2009 and closed on March 27, 2009 after a 14 day extension requested by the community  Conducted 3 public hearings on February 18, 23, and 25 Over 525 stakeholders attended the public hearings Over 174 provided verbal comments  Over 3,000 public communications were submitted  Key areas of concern for stakeholders include: Grade crossing configurations Location of maintenance facility Inclusion of bikeway within the project Phase 2 Project Status

Expo Line Transit Project Government/Community Relations  Participated in the following coordination meetings City of Santa Monica regarding maintenance facility location LADOT and City of Santa Monica regarding bikeway  Conducted several briefings with agencies, organizations, businesses, schools and environmental groups Santa Monica City Council Southern California Edison (SCE) Culver City Chamber of Commerce Century City Chamber of Commerce Santa Monica Chamber of Commerce Santa Monica/Malibu Unified School District Culver City Downtown Business Association Santa Monica Convention and Visitors Bureau Southern California Air Quality Management District (SCAQMD) Phase 2 Project Status St. Anne’s Catholic Church St. John’s Health Center Casden Development Bergamont Station Water Garden Heal the Bay Yahoo!

Expo Line Transit Project Phase 2 Milestones ActivityForecast Completion Date Status Scoping Meetings & ReportMay - 07Complete Screening of AlternativesOct - 07Complete Administrative Draft to FTANov - 08No longer applicable Conversion to CEQA DocumentDec - 08/Jan - 09Complete Public Comment Period/Hearings on DEIRJan/March - 09Complete Board Discussion of Preferred AlternativeApril - 09 Board Adoption of Final EIROct - 09 Design-Build Contract AwardJan Phase 2 Project Status