Post Break Week 3. Metal Miners This weeks presentation is much improved over last weeks, however, critical design problems remain including – Floating.

Slides:



Advertisements
Similar presentations
Surface Sr. Design Week 7. What You Should Have Distances to Mill and Leach as a Function of Depth Cycle Time Calculations for Proposed Truck Fleets.
Advertisements

Running MSOPIT for Assignment #6 These Slides are Base on MS3D version 4.6 which was current in Sept. of 2009 Note – These slides contain concepts also.
Sequencing Mining Operations with MineSight® ©2007 Dr. B. C. Paul {Note – The Name MineSight® and the Program described are property of Mintec Inc – Tucson,
Contour Lines.
How to Set Up a Processing Plan in MSOPIT’s Economics Panel.
Coal The goal of coal mining is to economically remove coal from the ground. Coal is valued for its energy content, and since the 1880s is widely used.
Senior Design – Week Projects. A General Comment Team leaders need to get me team member assignments.
Handling Solution in a Heap Leach ©2009 Dr. B. C. Paul.
Week 9. COAL Things Missed Last Week Show a map of your #6 coal and areas where you will have to cut roof rock because of your CM selection Show a year.
MineSight VALP Optimizing Cut-Off Grades © 2012 Dr. B. C. Paul Note – MineSight and VALP are both trademarked names belonging to Mintec Inc. These slides.
Roads in MineSight.
Matching An Excavator to Our Trucks ©2009 Dr. B. C. Paul Note – These Slides contain tables and information found in the Caterpillar Performance Handbook.
Surface Mining Ore Deposit Grades ©2011 Dr. B. C. Paul Note- The information contained in these slides is considered common knowledge to those schooled.
Week 5 Senior Design Work on Coal Preparation You have determined that you will use a heavy media plant – Plus ½ inch will go to heavy media baths.
SCHEDULE. ROAD-SIDE DITCH REVISITED Revisiting the road-side ditch problem: By how much is the contributing area of each stream cell increased in shifting.
An Introduction to MS Reserve
The Quasi - Open Pit Methods Mnge 315 ©Dr. B. C. Paul spring 2003.
More Insurance How much insurance We started talking about insurance. Question now is “how much?” Recall that John’s expected utility involves his wealth.
Monroe L. Weber-Shirk S chool of Civil and Environmental Engineering AguaRed.
Picking the Right Investments Choosing the Right Discount Rate P.V. Viswanath Based on Damodaran’s Corporate Finance.
How to Get a Metal Price for a Concentrate
Principles of Paving rev Principles of Paving.
... are the markets in the economy that help to match one person’s saving with another person’s investment. ... move the economy’s scarce resources.
Types of Market Structure
Copyright © 2003 McGraw Hill Ryerson Limited 4-1 prepared by: Carol Edwards BA, MBA, CFA Instructor, Finance British Columbia Institute of Technology Fundamentals.
Current Integrated Use of Biomass from Forest Treatment Plummer Forest Products.
Amrit Prakash Jonko 08MN23.  A method of mining whereby high value ore is mined in such a manner as to make the low-grade ore left in the mine incapable.
Lecture 11 Optimizing Cut-Off Grade Strategy
Week 11. DIAMOND One More Thing to Build Prepare a One-Line Diagram for the electrical energy needs of your mining operation For energy needs met with.
Adding Roads and Benches To A Pit Design ©2007 Dr. B. C. Paul {Note – The Name MineSight® and the Program described are property of Mintec Inc – Tucson,
Week 2 of Sr Design Diamond People Begin Building your Geologic Model – Right now your data limits you to assuming that each pipe is a single grade.
Wes Marshall, P.E. University of Connecticut March 2007
Entering My Haul Road Profile ©2009 Dr. B. C. Paul Note- This presentation draws on previous notes developed as early as 2000 and contains numerous screen.
Calculating Stripping Ratios for Area Strip Mines Mnge 315
Sequencing Mining Operations with MineSight®
Post Break Week 2. Comments for Consideration of Coal Miners One issue you have created is extreme variability in your coal tonnage – This will impact.
Week 4. SME Weirdness There will be no class from the week of Feb. 16 to 20 th Your report on this work load will be presented on Tuesday Feb. 24 th This.
Ind – Acquire the foundational knowledge of channel management
Senior Design Spring 2011 ©2011 Dr. B. C. Paul Acknowledgement is given to Companies whose design software is referenced by trademark name in this presentation.
Week 3 Sr. Design. Important Things we Know You will be doing heavy haulage by Barge on the Yukon River for $5 per tonne to Nennana – There will be no.
Obtaining Information From the Geologic Block Model
Developing Haulage Profiles (Part of Getting the Truck Cycle Time) ©Dr. B. C. Paul 2000 revised 2008 Note – The instructor prepared the basic steps and.
Surface Mining Ore Body Geometry ©2011 Dr. B. C. Paul Note- Concepts given here are considered to be common knowledge to those involved in early stage.
Interpreting VALP Results © 2012 Dr. B. C. Paul Note – MineSight and VALP are both trademarked names belonging to Mintec Inc. These slides suggest ways.
Building Economics. In this Example we Start With Western Mine Cost Service Models.
Compositing Assays To The Chosen Bench Height ©2007 Dr. B.C. Paul {Note – The Name MineSight® and the Program described are property of Mintec Inc – Tucson,
Week 8. COAL Timing Will Be Big Show a map of your #6 coal and areas where you will have to cut roof rock because of your CM selection Show a year by.
Computer Aided Mine Design Part III Cut-Off/Equipment Interactions ©Dr. B. C. Paul 2000 ©Dr. B. C. Paul Summer 2003.
Just After Spring Break Sr. Design. Coal Group For Each of Your Coal Seams Define the Boundary of the areas you believe are minable –Provide a plan view.
Mine Properties. DIAMONDS Kimberlite Pipes Located in Wyoming.
Week 9 ©2012 Dr B C Paul. Coal Trouble in the Board Room –Plans to ignore large amounts of met coal and drop mining your low sulfur coal and cut down.
Computer Aided Mine Design Part II – Pit Sequences ©Dr. B. C. Paul 2000 ©Dr. B. C. Paul summer 2003.
Open Pit Planning and Design The Standard Approach for Open Pit ©2007 Dr. B. C. Paul.
Ab Rate Monitoring Steven Petlick CAS Underwriting Cycle Seminar October 5, 2009.
FPC Assignment 1. Go to Your Project and Fire-Up MSOPIT.
Molybdenum Ores and Minerals (Another Porphyry Deposit Metal)
Do Now ISOLINES 1.) Isolines NEVER touch or cross each other.
Senior Design 2009 Projects Overview. General Format Week Day 1 – Outline Work to Be Accomplished During the Week Week Day 2 – Work Day / Special Lecture.
Week 10 ©2012 Dr B C Paul. Copper Your initial road moves have been questioned. –You have drawings showing the end of each stage –Between two of your.
Starting Up MineSight for Your Coal Mine Project.
Does the graph show a proportional relationship? Yes or No. HINT Next Slide Next Slide Remember that in order for a graph to be proportional, it’s points.
Unit #4 Carlson Software. Carlson is an Autocad Overlay Designed to build specialized commands into a widely used drawing package Largely 2D or a highly.
Copyright © 2014 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.
Slopes in MSOPT Calculations ©2012 Dr B. C. Paul Note – These Slides are based on and include screen shots from the program MineSight by Mintec. Credit.
True Open Pits ©Summer 2003 Dr. B. C. Paul. Telling a True Open Pit Strip mines advance across the deposit backfilling pits with new overburden as they.
Section 2.  Exploring rock for mineralization is the first step in finding an ore deposit.  Rock samples are taken from exploration areas and analyzed.
The 2007 Class Project ©2007 Dr. B. C. Paul. The 2007 Project A copper/moly porphyry deposit located near Eureka Utah –Ie (hard rock deposit) Deposit.
THE MARKET FOR LOANABLE FUNDS. FINANCIAL MARKETS... are the markets in the economy that help to match one person’s saving with another person’s investment....
Riprap Installation Construction Inspection for Field Office Activities Will use Riprap Gradation and Riprap Subgrade Problems from Class Problem Section.
MineSight VALP Optimizing Production and Cut-Off Grades
Presentation transcript:

Post Break Week 3

Metal Miners This weeks presentation is much improved over last weeks, however, critical design problems remain including – Floating roads – Excessively long conveyor paths – And roads that are suppose to move at the same time they carry haul trucks moving the material from cutting the road The design also has problems with uneven feed rates to the mill over the mine life

Correcting the Problems You now have pits that are basically in the right place and have the right slope – Try and smooth out the mill feed What is the average mill feed if the mine is going to go for 40 years? Rather than call your pits year 3, 6, 9, 12, 15, 20, 25, 30, 35, and 40 – if your mill fed is at the average rate your pits might actually be at time 4, 7.2, 10.1 etc – Identify the correct point in time that you are actually looking at (no don’t try to redesign to get exactly 3, 6, 9, 12 etc).

Look at Your Pits Particularly at first the rough surface topography makes for a lot of discontinuous benches and roads. – If you tried to exit the pit at one of the low elevation points where would you run the road? For some of the higher benches maybe what you need is a road down to the exit point Can you find exit points in your pit that would be relatively undisturbed by later mining (such as the north area of the pit that is inactive after about 20 years) Until you start pushing to the west? In later years a lot of your pit development is downward. – When you push down try to leave your shallower pit undisturbed including the roads Instead of cutting later pits into the original topography, cut and merge them into the previously mined topography and make your roads join up – This will help avoid the problem of demolishing roads that you are trying to use – It will also tend to stabilize the points at which traffic exits the mine.

Conveyor Routes Conveyor costs are heavily impacted by the length of the conveyor. Making a conveyor that could go up at 20% follow a road that goes up at 10% makes little economic sense. – Add in a separate conveyor route that puts the in pit crusher in a practical place and gets out of the pit without unnecessary length

Show Your Upgraded Work Pick distinct colors for your roads. – Conveyor routes should be one color – Active in pit roads should be one color – Inactive in pit roads should be one color – On the Surface roads to the dump, mill, and leach should be different colors How do you color a road? – Remember – especially for surface roads you create a road center line and then attach cut or fill templates along the line.

Trick You used these templates along the polyline for cuts or Fills that you put into geometry objects Then you merged those surfaces with the topo surface to Create a topo surface with the cut or fill. What if a create a geometry object for just the flat road Surface and gave the geometry object the color I chose For the road. What if I took that same original polyline for the road Center that I attached the cut and fill templates to and Now attached this template to it? Oh Ho! – Now I have a distinctly colored flat road surface Geometry object – don’t I.

Use 2D Cross Sections to Show Your Design Pits follow Your Guide Pits Make a set of north south or east west vertical grid sets Attach the grid set to the viewer Go into 2 Dimensions so I see a slice through the landscape With only the guide pit and the design pit for year 3, 6 or what ever turned on I can look at multiple cross sections to show they follow each other.

Reserve Checking Rather than use MSOPIT to check reserves use MSreserve Under MineSight Help is a menu item for Msreserve help that will teach you how to Use the routines to calculate your reserves

Your Objective is to Show Your Design Pits Contain Basically the Same Resources as Your Theoretical Pits Breakdown your reserves by ore type (oxide, sulfide, mixed) Report your grade in units of dollars per ton – This will require that you have run MSOPIT and saved dollar per ton block values back into the block model – Report your high and low grades and a reasonable breakdown of grades inbetween (a distribution of ore grades not just an average) This will be useful information when you prepare to run VALP

Get the Borrow Pit for Road Cut and Fill Right Changes to the pit will potentially change surface roads (you have to color the surface roads anyway) Examine the entire area that will be disturbed by the ultimate pit – Are there any areas you can get enough borrow waste? If yes design a borrow pit in those areas If no design the initial borrow point and include your stock-piles in the disturbed terrain views.

Coal Miners – Market and Water Numbers and Constraints Senior management believes spot market prices will take a tumble (like they did in the early 1990’s) – Expected spot prices will fall by 20% from the expected $46/ton to $37/ton – In response you need to have at least 70% of the mines steam coal tonnage on contract

Spot Markets The spot market will take as low as 9,500 BTU/lb and up to 18% ash and 5% sulfur but with the following penalties – Transportation Buyers assume ownership of coal at docks on the Ohio and Mississippi rivers (Mnt Vernon Indiana is probably your closest) Any costs to get the coal to the docks comes out of your sales price – BTU penalty coal sales price is a linear function of BTU content from 12,000 BTU per lb Coal that is 10% short of 12,000 BTU/lb (10,800 BTU/lb) will be short 10% on price ($33.30/ton) Similarly coal over 12,000 BTU per lb will get a premium – Sulfur Penalty 10 cents per ton for every 0.1 lbs/MMBTU over 0.2 lbs/MMBTU – Ash Penalty $1/ton for percentage over 9%, also a $1/ton bonus for percentage under 9%

Golden Goat Sales People Have Hustled for Contracts Industrial Boilers around Terra Haute – Will buy 1,500,000 tons/year of coal on 10 year contract renewable for 3 or 5 year terms – Will pay $67/ton (but you cover the transportation cost) – Specs Less than 1.5% sulfur Less than 0.2% chlorine 75% of coal over 1/4 th inch Ash less than 10%

More Contracts Hutsonville Power Plant – Will buy 1,200,000 tons per year – 20 year contract with 5 year renewal terms there-after – Will pay $44/ton – but you cover shipping to power plant – Specs Ash < 7% Sulfur < 4.5% BTU >= 10,700 BTU/lb

More Contracts Newton Power Plant – Will Buy 2,000,000 tons/year 5 year contract renewable in 5 year terms – Pay $46/ton but you pay shipping to power plant – Specs Ash <8% Sulfur <2.5% BTU >= 10,100 BTU/lb Bonus of $2/ton if chlorine under 0.4%

Another Contract TVA will buy up to 7,000,000 tons per year 7 year contract renewable in 3 year terms there- after Will pay $45/ton for coal at the Ohio River docks (you pay shipping to get it to docks) Specs – Ash <13% – BTU >= 10,500 BTU/lb – Chlorine < 0.2%

Another Contract St. Petersburgh power station in Indiana will buy 2,500,000 tons/year on a renewable 5 year contract They will pay $47/ton for coal delivered to the power plant (ie you pay shipping) Specs – Ash <6% – Sulfur <4% – BTU/lb >= 11,700

Another Contract Shipping Coal to Foreign Markets – will buy 2,500,000 tons of coal 5 year renewable contract Price $47/ton for coal at the docks on the Ohio or Mississippi River (you pay shipping to get it there) Specs – Sulfur < 2.3% – BTU > 11,500

Water Flows General coal mine faces in #7 and #5 and #2 coal seams – 5 gpm per hundred feet of entry – Plus water used on equipment General coal mine faces in #6 coal seam – Dry except for water used on equipment – Areas within 50 ft of fault line 2 gpm per foot of entry in the affected area Special areas in #5 – Areas with sandstone channel roof 100 gpm per foot per entry way into affected area Potential for water pockets that flow at 60,000 gpm for limited time – Areas within 100 ft of fault line An additional 20 gpm per foot of entry into affected areas Special areas in #2 – Areas with sandstone channel roof 10 gpm per foot per entry way into affected area – Areas within 100 ft of fault line An additional 10 gpm per foot of entry into affected areas

Comment Hopefully these water inflows will enable you to specify you water handling equipment Contracts and parameters should give coal preparation plants concrete margins to shoot for – Since your coal seams show significant variations in sulfur particularly you cannot just work with average sulfur content of seams without regard to where you are mining in a given year – On washability data you can assume washability is proportional to local sulfur or ash concentration Ie- if a 1.5 cut will reject 40% of the sulfur from 3.5% sulfur it will also reject 40% of sulfur from 0.9% sulfur areas.