MICE CM18 RAL Alain Blondel 14 June 2007 1 MICE run plan -- steps I and II 1.Establishing the detailed run plan will be one of the mission of the MICE.

Slides:



Advertisements
Similar presentations
1 MICE Beamline: Plans for initial commissioning. Kevin Tilley, 16 th November. - 75days until commissioning Target, detectors, particle production Upstream.
Advertisements

MICE Beam-line and Detectors Status Report 16 th October 2009 Chris Booth The University of Sheffield.
MICE Particle Rate and ISIS Beam Loss Adam Dobbs, Target – ISIS Meeting, 17 th September 2010.
Emittance–momentum matrix1 Demonstrating the emittance-momentum matrix Mark Rayner, MICE Video Conference, 21 January Initial 4D.
Changing the absorbers: how does it fit in the MICE experimental programme? Besides the requirement that the amount of multiple scattering material be.
Linda R. Coney – 24th April 2009 MOM Update Linda R. Coney 21 September, 2009.
Alain Blondel MICE: Constraints on the solenoids 2.Field Homogeneity: or ? this will be dictated by the detector requirements. TPG will be.
MICE FAC Alain Blondel 7 October   MICE The International Muon Ionization Cooling Experiment MICE CM19.
K.Walaron Fermilab, Batavia, Chicago 12/6/ Simulation and performance of beamline K.Walaron T.J. Roberts.
Beam line characterization with the TOFs1 Demonstrating the emittance-momentum matrix Mark Rayner, CM26 California, 24 March Initial.
Linda R. Coney – 24th April 2009 MOM Update Linda R. Coney 14 September, 2009.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 12, 2010.
MICE analysis meeting Alain Blondel 5 August MICE -- what running strategy? disclaimer: of course we will evolve the running strategy as problems.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 26, 2010.
Alain Blondel MICE VC 9 september 2010 Spokesmouse report o VC 22nd April o 12th-13th May posters for IPAC (Vittorio Palladino) o VC 20th May o IPAC May.
May 22, 2008 TJRMICE Beamline Collimation and Correction 1 Tom Roberts Carol Johnstone Muons, Inc.
1June 1 st 2009MICE CM24 - RAL1 MICE Beamline m. apollonio.
MICO 8 th February 2010 Terry Hart (MOM) - Decay Solenoid and Target - MICE Machine Physics runs - Problems and Issues.
MICO 15 th February 2010 Terry Hart (MOM) - Decay Solenoid and Target - MICE Machine Physics runs - User Run Plans.
Mark Rayner, Analysis workshop 4 September ‘08: Use of TOFs for Beam measurement & RF phasing, slide 1 Use of TOFs for Beam measurement & RF phasing Analysis.
CMPB Alain Blondel 14 April STATUS OF MICE.
MICE magnetic measurements Sequence of events and MICE hall movements Alain Blondel – 10-April 2012 revision from 13 December 2012.
MICE Video meeting Alain Blondel 7 December MICE -- what running strategy? reflections on steps I and II.
Emittance measurement: ID muons with time-of-flight Measure x,y and t at TOF0, TOF1 Use momentum-dependent transfer matrices iteratively to determine trace.
Physics Program and Runs: Autumn 2011 & Step IV V. Blackmore MICE Project Board, 08/03/12.
Emittance measurement: ID muons with time-of-flight Measure x,y and t at TOF0, TOF1 Use momentum-dependent transfer matrices to map  path Assume straight.
MICE VC Aug '10J.S. GraulichSlide 1 MOM report o Achievements Since CM27 o Daily Operations o Run Plans o Summary Jean-Sebastien Graulich, Geneva.
(+) session, PAC09 Vancouver – TH6PFP056 Introduction The Muon Ionisation Cooling Experiment (MICE, fig. 1c) at RAL[1]
Results from Step I of MICE D Adey 2013 International Workshop on Neutrino Factories, Super-beams and Beta- beams Working Group 3 – Accelerator Topics.
MICE Beam-line and Detectors Status Report 16 th October 2009 Chris Booth The University of Sheffield.
MICE Step 1: First Emittance Results with Particle Physics Detectors Linda R. Coney EuCARD Meeting – 10 May 2011.
M. apollonio MICE Beamline summary. - Beamline parallel session (June 1 st ): - envisaged goals (Alain) - assess readiness of the line magnet status (Ken)
Alain Blondel – introduction MICE CM Collaboration meeting June 2007 at RAL Complete review of the project Organization of efforts towards.
Beam line commissioning Preparations for Phase1 Kevin Tilley For Paul Drumm & the beam line group.
1 Forces Yury Ivanyushenkov RAL. 2 Goal: find maximal (static and dynamical) possible forces in MICE magnetic system. Method: calculation of axial magnetic.
MICE input beam weighting Dr Chris Rogers Analysis PC 05/09/2007.
Plans (& ideas) for beamline commissioning The beamline Magnet field tests Source characterisation Optics (& model) commissioning K. Tilley CM18, 14/06/07.
MICE FAC Alain Blondel 21 september   MICE The International Muon Ionization Cooling Experiment BRIEF STATUS OF MICE.
MICE at STFC-RAL The International Muon Ionization Cooling Experiment -- Design, engineer and build a section of cooling channel capable of giving the.
Alain Blondel MICE VC 12 March 2009 Brief MICE news 1. Decay solenoid: operations will restart in early July. Criteria for acceptance have been specified.
Paul drumm, mutac jan Precursor: - Resources since cm16. Beamline Review Response. Optics related work: the major threads: -Current (ε,p) status.
11 Nov 2008PC Analysis PC Schedule 2008 Tuesdays fortnightly 9 September  23 September  2 October  CM22  11 November  25 November 9 December.
1 G9a -FROST. 2 Experiments FROST New generation of CLAS photoproduction experiments with FROzen Spin Polarized Target (FROST) E02-112: γp→KY (K + Λ,
MICE RF Workshop Alain Blondel MICE = critical R&D for neutrino factory and muon collider 1 neutrino factory: accelerate muons and store to produce.
MICE Run Plan Sept/Oct 2009 m. apollonio – IC MACHINE PHYSICS USERs RUN NO SHIFT A B C D E.
MICE VC116 Alain Blondel 18 December MICE NEWS See more details in Macolm’s MICE news!
Low emittance tuning in ATF Damping Ring - Experience and plan Sendai GDE Meeting Kiyoshi Kubo.
March 18, 2008 TJRMICE Beamline Status1 MICE Beamline Status (March 18, 2008) Tom Roberts Muons, Inc. Illinois Institute of Technology.
Linda R. Coney – 5 November 2009 Online Reconstruction Linda R. Coney 5 November 2009.
MICE CMPB Alain Blondel 1 Highlights on MICE.
Running plan Step I.1 Basic radiation levels. I.1.1 ISIS running with beam elements on, target off, beam stop shut. Establish permanent MICE monitoring.
- MICE - The Muon Ionization Cooling Experiment Jean-Sebastien Graulich, Univ. Genève o Introduction: Aims And Concept o Design o Infrastructure: Hall,
MICE CM20 Alain Blondel 10 February The International Muon Ionization Cooling Experiment MICE CM20 Spokesmouse remarks.
MEIC Detector and IR Integration Vasiliy Morozov, Charles Hyde, Pawel Nadel-Turonski MEIC Detector and IR Design Mini-Workshop, October 31, 2011.
1June 2 nd 2009MICE CM24 - RAL1 m. apollonio Beamline+( ,P) matrix.
1 Updated Run Plans. K.Tilley, MICO, 07/02/08 - pre-commissioning - Target, - beamline functionality - detectors, particle production - decay solenoid.
17 Sept 2007 Analysis PC 18 Sept Analysis PC Schedule 2007 Tuesdays alternate weeks, 15:30 – 17:00 GMT, with ad hoc exceptions Tue 3 April Tue 17.
M. apollonio 7/7/2010CM27 - RAL11 Beam-Line Analysis …
MICE, Uni-Geneva and the transnational access to MICE (MICE-TNA)
Monte Carlo simulation of the particle identification (PID) system of the Muon Ionization Cooling Experiment (MICE) Mice is mainly an accelerator physics.
1June 1 st 2009MICE CM24 - RAL1 Beamline Optics m. apollonio.
(one of the) Request from MPB
MICE. Outline Experimental methods and goals Beam line Diagnostics – In HEP parlance – the detectors Magnet system 2MICE Optics Review January 14, 2016.
1 1 Optics related work: the major threads: -Current (ε,p) status - G4BL/TTL Simulation comparisons - Beam steering/correction -Collimation d/stream &
Beam-Line Analysis m. apollonio 7/7/2010 CM27 - RAL 1.
MICE Beamline Status m. apollonio 17 December 2009 MICE VC
MICE Operations Scenario Run 1
Beam Optics Set-Up at SLAC End Station A
CNGS Proton beam line: news since NBI2002 OUTLINE 1. Overview
K. Tilley, ISIS, Rutherford Appleton Laboratory, UK Introduction
Presentation transcript:

MICE CM18 RAL Alain Blondel 14 June MICE run plan -- steps I and II 1.Establishing the detailed run plan will be one of the mission of the MICE installation commissionning and operations group (MICO). 2. ’the running strategy will evolve as problems arise;’ 3. This has been modified to take into account solenoid issue Refer to presentations at analysis/CM meetings (AB CRogers 5 August 2005, CM13 October 2005, CM16, analysis december 2006)+ discussions with KTilley and Dieter Renker from PSI.

MICE CM18 RAL Alain Blondel 14 June  - STEP I: April 2007 STEP II: October 2007 STEP III: 2008 STEP IV: 2008 STEP V 2008? STEP VI 2009? PHASE I PHASE II MICE steps as of october 2005

MICE CM18 RAL Alain Blondel 14 June  We should revisit our MICE Schedule: as of june 2007 (unchanged since march 2006) 1 October 2007 Or january 2008 STEP I April 2008 STEP III: July 2008 STEP II STEP IV: Delivery of 1st FC May 2009 STEP V: summer 2009 STEP VI end 2009 PHASE I PHASE II R&D beam line commissionning starts august 2007(?) UK PHASE I

MICE CM18 RAL Alain Blondel 14 June Establish beam match andwhether we have all knobsnecessary to drawemittance vs. transmissioncurve. Measure emittance -- STEPI: If step I starts feb 1st 2008 and solenoid arrives mid March we have 1.5 month to get beam and detectors running properly. We estimated that 20 days of beam were needed. This leaves very little time for installation and commissioning of detectors.. Operation will be interrupted when SS1 arrives until tracker and TOF/KL are installed Is TOFII needed for step I, II? (in principle trigger on TOF0+TOF1 should suffice). My answer would be NO (no need for downstream trigger either) It will definitely be needed for step III.  STEP I STEP II STEP II -- OK

MICE CM18 RAL Alain Blondel 14 June

6 MICE control room MICE in February 2008 develop beam with P(B1)=P(B2), align, check rates And target dip, first tries at P(B1)≠P(B2) Detectors will be installed and running when we start the beam

MICE CM18 RAL Alain Blondel 14 June MICE control room MICE in May 2008 measurement of emittance and diffuser operation. Develop beam PID, Fill the matrix.

MICE CM18 RAL Alain Blondel 14 June MICE control room MICE in October-december 2007 Version I Very conservative. Will work. Danger: delays in installing detectors, DAQ, CR, controls etc… RA12 Target or no target? Beam passage is plugged

MICE CM18 RAL Alain Blondel 14 June MICE control room MICE sometimes in (october to december) 2007 version II Advantage is obvious. Duration may be limited to a month (november?) Question: can this be achieved (or: what needs to be done to achieve this) without compromizing the Christmas shutdown effort? Target Is the present target good enough? In negative mode, a beam of e- and pi- How long and which conditions does it take to move B2 in and out?

MICE CM18 RAL Alain Blondel 14 June ! the most important point: the beam line elements (quads, dipoles) should be well aligned both in position and angles. The magnet current to field should be measured (or have been measured) and polarity verified. Mistakes there take a long time to understand and fix in the tuning process while the preventive actions are straightforward. The phase advance in the decay solenoid is a free knob and would allow a mini(or maxi)-mization of the outgoing pion beam to facilitate collimation A collimator downstream of B2 seems absolutely needed to protect the TOF0/Cherenkov and MICE itself from spray induced by the primary momentum particles Running-in would better be done with a setting where P (B1) = P (B2) Excerpts of a meeting with Dieter Renker (PSI)

MICE CM18 RAL Alain Blondel 14 June concerning the possibility to have a diagnostic device at the focus behind B1 -- it looks like a good idea except that the beam dispersion is very large and only the on- momentum particles will be focused properly. Excerpts of a meeting with Dieter Renker (PSI) --The beam will look like a butterfly or an horizontal hourglass with the focus nominally at the center, but vertical beam size rapidly increasing as one goes on the side horizontally in both directions. If the x-y beam profile monitor is too wide we will integrate over off momentum particle and the sensitivity to the focus may not be great. Also it will be very difficult to locate the horizontal position of the focus. These things should be checked by simulation before we place too much hope in these scifi counters. --According to the turtle file there is vacuum between the target and the exit of B2. This would cause a problem when trying to place a detector just after B1 (NB discussing with Paul afterwards there will be a small vacuum break there between B1 and decay solenoid in any case but it may require modification to fit a detector)

MICE CM18 RAL Alain Blondel 14 June beam aligned? question 1: how well should the and be =0 for beam to be considered aligned? answer (Chris Rogers) : assume we want to reweight the beam with factor per particle of no more than 10% leads to alignment of better than  x  x ~ 1 mm and similarly in the other dimensions. Reweighting factors increase very rapidly with mismatch. this will require about ~1000 muons (a few seconds) for one dimension For 5 dimensions will need up to 250 points (3 5 ) depending on correlation of parameters (30 if x and y are not correlated) -- easy. – if one has the knobs to do the tune! Correctors will be absolutely needed for x, x’ y, y’. 4 knobs at least How do we correct dispersion?

MICE CM18 RAL Alain Blondel 14 June We will also need data to do the initial alignment/calibration/characterization of the detectors. Without and with mag field, vs momentum etc… I think the detector experts should think about it and define their needs. -- muon beam with small momentum spread? would be very useful in step I – need will be obsolete when we have SS1 -- beam enhanced in electrons or pions in order to tune up the PID detectors -- We will also need to establish the beam momentum scale … (wrt TOF?) Ancillary data and measurements

MICE CM18 RAL Alain Blondel 14 June STEPI 1. running in of the beam line. This assumes that all magnet polarities and fields have been tested by powering during the shut down 2. it is suggested to run-in with negative polarity and P(B1)=P(B2) only electrons and negative pions/mus to simplify pile-up in TOF0) 3. it is assumed that tracker TOF0 and TOF1 are complete, x y x’ y’ are availale 4. Beam momentum spread? target running in ?6? shifts verify leaks, dip, radiation etc…. first beam from target to bend 1 to decay solenoid ?6? shifts through DK solenoid and to Bend 2 need a fluo screen with videocam or a transportable and operational TOF0 or… no quads powered at first go.

MICE CM18 RAL Alain Blondel 14 June measurements at TOF0 6 shifts will allow first meast of through rate (negatives first) as fn of B1, B2 max should be B1=B2 TOF0, TOF1 negatives and B1=B2 to keep electrons and low dipping target 3 shifts will allow verification of TOF time calibration and verification of beam alignment on TOFs. positions of TOFs set up cherenkov scan beam dipoles for alignment and quadrupoles for misalignment 20 shifts findout if quad is misaligned by checking change of av. position vs change of current note qads misalignments for future realignment obtain aligned beam with B1=B2 after 41 shifts = 14 days.

MICE CM18 RAL Alain Blondel 14 June vary B1 and B2 at the same time to verify momentum relation (1 shift) calibrate using TOF0- TOF1 on pions w.r.t. electrons begin to explore B2.ne.B1 6 shifts electrons should become rare and muon peak appear. redo alignment with B2=0.6 B1 2 shifts obtain an aligned muon beam first measurement of beam size in TOF1 vary optics 10 shifts to verify that the beam sizes are approximately correct total estimated beam time requested for stepI: 60 shifts = 20 days.

MICE CM18 RAL Alain Blondel 14 June Step II: Detector commissioning Goals: Commission detector systems: Tracker and solenoid Alignment, calibration Magnet off Pencil beam what is the requirement here? Demonstrate beams for MICE: Alignment of beam (Lack of) dispersion Range of transverse emittances Range of momenta Demonstrate match into MICE spectrometer Range of transverse emittances Range of momenta 2 weeks total 1 week I dont understand the need for the pencil beam … we measure momentum particle by particle twice (TOF+tracker) already here it will be critical to have the knobs to tune this how do we correct for dispersion? quads and diffuser B1 B2 another three weeks total STEPII 7 weeks = 50 days

MICE CM18 RAL Alain Blondel 14 June This is very preliminary and should be looked at by others. It looks as if the running in of MICE stepI and II will require about 70 days of beam time Need to have run periods separated by periods for Thinking Fix things Analyse results This thus can be estimated to last ~6 months not including installation time 20 january to mid-june (arrival of SS2) = 4 months. I believe that ~2 months would be missing if we start to install detectors after the Xmas shut down.

MICE CM18 RAL Alain Blondel 14 June beam matched? we will want to generate matched beam:  x 2 =  x’ 2 =   with no dispersion.  but perhaps a particular relation between amplitude and energy  question 2:  what precision is needed on this match to satisfy cooling measurements?  question 3:  can the beam gnerate the energy-amplitude relation  or should the analysis do it?  beam intensity?  Obtaining the ‘right’ number of muons per spill  at 140 MeV/c or 240 MeV/c  will require different tuning of the target dip depth -- or collimation.  Which is more desirable?    many knobs to scan for a given diffuser setting. what precision needed  how many muons will be needed to do this? Once the baseline setting is matched and understood, will want to repeat the exercize for various momenta and various diffuser to check that we can really generate all beams we need/want from 1 to 10 mm emittance.

MICE CM18 RAL Alain Blondel 14 June Bob Palmer: in MICE, the diffuser does not generate this kind of correlations, and we may want to scan momentum to ensure good population of phase space in the corners. p- p0 p+