Road Map To Development September 2013 December 2013 February 2014 April 2014 July 2014 Data Submission WEQ 008 Assessment CO 283 Report GTL COs Draft COs Development Key Assumptions: -WEQ 008 is approved by December Agreement for funding of the Change Order required is in place by June IDCWG SC support of the COs development by March 2014
December 2014 (Software Testing) April 2015 June 2015 (Start month test) Road Map To Trial Period Month Test Testing Testing Result Report Implement COs Start of Trial Period Key Assumptions: -WEQ 008 is approved by December Agreement for funding of the Change Order required is in place by June IDCWG SC support of the COs development by March 2014
3 Free Template from 3 Timeline Scenarios Activities after Completion of Field Test/Full Staffing Standards ratified after successful field test Standards submitted to FERC Notice of Proposed Rulemaking/Order Incorporated into Code of Federal Regulations with effective date