Status Brussels GANTRY Ê Assembly of R3 modules (36 modules) 4 precision of the modules 4 problems with DataBase (not adapted for single sensor modules)

Slides:



Advertisements
Similar presentations
Clean Room Plans Monday, August 23, Hybrids--- Frames--- SensorsModules.
Advertisements

Lyon Gantry Status TEC meeting Dec D. Contardo Module production in Lyon Rigidifier test on R4 Frame tolerance effect on assembly plates Short term.
Status Brussels GANTRY Ê We have observed a significant influence due to temperature 4 we had a lot of problems with our cooling system (ventilation) Ë.
Module Production Brussels Ê Problems with vacuum chambers in plate solved 4 Almost all plates back in Brussels (repaired in Aachen) Ë Problem with rotation.
Innovative Outreach Ideas: How to Serve Communities without Library Buildings.
L2 L3 CMS tracker manager meeting June W. Beaumont Universiteit Antwerpen 6/10/01 l2l3UAjune2001b.sdd Module Long term test activities University.
Tracker Week – UCSB Gantry Status – April 20, 2004 – Dean White 1 Gantry Report University of California Santa Barbara Dean White.
Tracker Week – UCSB Gantry Status – July 20, 2004 – Dean White 1 Gantry Report University of California Santa Barbara UCSB Gantry Team: Andrea Allen Dave.
CMS Tracker Week – Gantry Meeting – 21 st October 2003 – Dean White 1 Status of the UCSB Gantry Dean White University of California Santa Barbara October.
DOE REVIEW 1/20/04 – Dean White 1 Gantry Module Assembly TOB & TEC Dean White University of California, Santa Barbara.
1 Hybrid & Module Testing Status Week of 4/25-4/29.
Tracker Week – UCSB Gantry Status – Febuary 10, 2004 – Dean White 1 Gantry Status University of California Santa Barbara UCSB Gantry Team: Andrea Allen.
Slide 1CMS Database Issues-Derek BargeDOE review, January 20, 2004 CMS Database Issues Derek Barge.
1 UCSB Module Assembly Week of 5/23-5/27. 2 FNAL & UCSB Inventory HybridsSensorsFrames FNALUCSBFNALUCSBFNALUCSB STHPKITSTHPKITSTHPKITSTHPKIT L12pu /
1 UCSB Module Assembly Week of 4/11 – 4/15. 2 UCSB Parts Inventory 4/4/05 Hybrids Sensors Frames STHPKITSTHPKIT L12pu ST193 L12pd ST193.
US Module and Rod Production Overview and Plan For the US CMS Tracker Group.
US Tracker Group Status Sep. 1, 2005 J. Incandela For the US CMS Tracker Group.
Slide 1Rod Production presented by Jim Lamb (UCSB)April 9, 2004 Rod Production Rod Production, April , presented by Jim Lamb (UCSB)
CMS Week – UCSB Gantry Status – June 8, 2004 – Dean White 1 Gantry Report University of California Santa Barbara UCSB Gantry Team: Andrea Allen Dave Staszak.
Status of the Tracker DB System Tk week april 03 D. Contardo Developments Applications.
March 17, 2003 Catania, Meeting ST - CMS CMS Sensor Quality Frank Hartmann – University of Karlsruhe 1 Summary of Sensor Quality Tests List of Problems.
Slide 1-OGP status & module reinforcementDOE review, January 20, 2004 Status of OGP & Module reinforcement Andrea Allen Development Technician DOE Review.
US Module Production June 2, 2005 J. Incandela For the US CMS Tracker Group.
Module mounting Ian Wilmut (RAL). Martin Gibson Martin has been developing the module mounting system at RAL for the last two years – everything we have.
CMS FPIX Reinstallation/Commissioning Lorenzo Uplegger 4/20/091.
Status Brussels GANTRY Ê Overview of the pilot run (second week of October) 4 aims and achievements 4 accuracy on position and angles 4 residual features.
1 TEC pilot run status Goal : test TEC module production rate capabilities - 15 R6 modules assembled on Brussels Gantry and bonded in Aachen I - 15 R7.
Status Brussels GANTRY Ê Recovered from the Gantry PC crash during Pilot Run R6 4 same situation as before the Pilot Run is achieved for R6 Ë Comparison.
Status of CERN M1R2 production LHCb Muon meeting sept.061Thomas Schneider -Beginning of 2006 two visits to Erbicol because of several reasons: -Material.
CMS Tracker Week, CERN, October Oct 2004CMS Tracker Week - Module ProductionSalvatore Costa - Catania Report from Module Bonding Working.
M. Gilchriese Sector Status Module Loading Task Force Meeting November 18, 2004.
Status Brussels GANTRY Ê Try to assemble modules with good precision 4 different calibration plates (Karlsruhe and Bari) 4 determination of pin positions.
Logistics Lifecycle and Problem Resolution. Definitions Ship Date: Date and time when order is shipped from our WH in Bangalore Delivery Date: Date and.
Brussels Gantry Ê Problem with vacuum chambers in plate 4 leaks in plates with gives communication between positions Ë Problem with rotation motor (U-motor)
TRACI V3 Status & Delivery Plans UPDATE Paolo Petagna LHCb CO2 cooling meeting Apr 15 th, 2015.
CMS Tracker Week, CERN, February Feb 2005CMS TrackerWeek - Module ProductionSalvatore Costa - Catania Report from Module Bonding Working.
Brussels Module Production Ê We have producted 57 R6 modules and 26 R5N modules 4 of which 67 grade A and 9 grade B and 7 outside specifications Ë We have.
03/07/2000Status at TRIUMF1 Module Production Status Production Changes Material Production Status Status of Module Shipping Frame QC Status.
G. Steinbrück 6/21/ Premounting of AOHs for the TEC in Hamburg Georg Steinbrück Hamburg University AOH Meeting, CMS Week 6/21/2005  Status of AOH.
Thermo-mechanical petal status Sergio Díez Cornell 23Jan 2015.
Status Brussels GANTRY Ê New measurements of pin positions 4 using short pins rather than long ones 4 improved the precision Ë Cross-check of precision.
Lyon Gantry Status CERN 15 Sept D. Contardo Calibration Plates and Tools Readiness for production.
Module Assembly Jig Status Cambridge and DESY came to Liverpool Nov. 15 th -16 th for training on module assembly – A complete jig set was sent back with.
Hybrid and Module Status 1. Hybrid Delivery First hybrids over-etched and shrunk due to changes in design and mistakes in manufacturing – Shrinkage for.
Linac2 and Linac3 D. Küchler for the linac team. Planning first preparative meeting for the start-up of Linac2 in June 2013 –this early kick-off useful.
Brussels Gantry Ê Problems with vacuum chambers in plate 4 mostly solved by the workshop in Aachen (thanks) Ë Problem with rotation motor (U-motor) 4 motor.
1) News on the long scale length calibration 2) Results of the two surveys performed on plane 7 Set 1: morning of 12/11/2004 Set 2: morning of 19/11/2004.
T2 Status Report IP5 Installation Future plans. IP5 installation The mechanical structure has shown problems on installation and should be changed slightly.
IRC/SAC status Venelin Kozhuharov for the SAC/IRC working group NA62 Meeting
HE FEE Boards production status 26 th May 2016 Mandakini Patil 1.
→ need to guide UV light into gap; also beware temp effects
Status Brussels GANTRY
Status Brussels GANTRY
FNAL Production Experience
Hamburg Bonding Report
Vienna Module Production
CMS Perugia Modules Production Review
US Testing Update Anthony Affolder (On behalf of the US testing group)
TEC Module Production Overview
Bari production centre resp. M. de Palma
Module Production in Brussels
CMS Perugia Gantry Status Report
L.Fiore Gantry Meeting during the CMS TK week
Module Production in Brussels
US Module Testing Progress Report
TEC module quality overview
US Module Testing Progress Report
Status of Bonding R1N, R1S, R3 of TEC University of Hamburg
Hybrid & Module Testing Status
TEC Ring 2 module prototypes J. Hrubec / Inst. für Hochenergiephysik
Presentation transcript:

Status Brussels GANTRY Ê Assembly of R3 modules (36 modules) 4 precision of the modules 4 problems with DataBase (not adapted for single sensor modules) Ë Towards R5 module assembly 4 still 3 R5N and 3 R5S modules are needed for the TEC Test Beam 4 mask of the sensors is not correct… (update website) Ì Plans for the near future Í Outlook O.Bouhali, J.D’Hondt, C.Vander Velde, L.Van Lancker, J.Wickens TEC meeting CMS – April 2004

Assembly of R3 modules Ê We received about 38 hybrids in total ( + 36 more end of last week) ï only 2 of them failed the electronic ARC tests (58 tested yet) Ë In total 36 R3 modules were assembled ï with 2 persons working in parallel this job can be done in about 2 hours ï including after curing, virtual assembly, mounting on transportation frames, assembly, …(everything) Ì Via dry assemblies, corrections were estimated (shifts and rotations) ï (slightly) different for all plate positions ï this incorporates precision problems with the sensor pick-up tool ï now we have 1 pick-up tool for all sensor types (R3, R5, R6) !! DataBase problem for single sensor modules !! Ê DataBase and Gantry software always expect 2 sensors ï hence the assembled modules are always ‘NOT VALID’ ï we correct the DB flags by hand before introducing them ï … people are working on it

Assembly of R3 modules : precision X Y

X Y

X Y

Ê The specifications on the angle of the sensor on the frame are very severe (10mdeg) Ë The angle between the hybrid and the sensor is important for the bounding, hence it could be that modules outside the limits could be bounded and are therefore valid Those from the beginning of the production period, residuals much better now

Transport of R3 modules Ê The first 8 modules are already shipped to Karlsruhe and Hamburg (DHL) ï 2D bar code labels were not glued on these frames (I have some with me) ï transportation did arrive in good shape (no damage) ï Hamburg claimed some damage yesterday on the back of the sensors (to be checked) Ë The remaining 28 modules will be shipped now ï 50% to Hamburg ï 50% to Karlsruhe (we will wait a bit until we have the R5 modules)

Towards R5 module assembly Ê For the TEC Test Beam we need 3 R5N and 3 R5S modules ï we will assemble them this week 4 For R5N the software is about to be ready and modules will be glued tomorrow. We have seen that the mask of the sensors is not matching with the reality… This will be checked and updated very soon (in communication with Aachen). 4 For R5S the software is in development and modules will be glued this week to be able to ship them in time on probably monday Ë A good precision of these modules cannot be guaranteed, but this is not very important for the TEC Test Beam… corrections to be applied in the future to minimize the residuals (via dry assemblies a la R3) Ì Some problems with the pin holes for the R5 plates, the pins do not enter the holes completely (Aachen is investigating their plates … Oliver Pooth). DB was down today : hence no modules produced today !!! …also some residual problem appeared…

Conclusion and outlook for the future Ê Precision of R3 modules is good Ë In total 36 modules are assembled (+ 2 bad hybrids) Ì Production is continuing (another 36 hybrids did arrived) assembled already 4 yesterday Í Some problems with DataBase to be solved… Ê R5N : 3 modules will be glued tomorrow (‘old’ hybrids) Ë R5S : in development (to be finalized and glued this week) Ì … no guarantee for precision but enough for the TEC Test Beam

Outlook Ê R3 (1 plate of 4 modules) : 20 modules/week (~700 total) Ë R5N (1 plate of 3 modules) : 15 modules/week (~800 total) Ì R5S (1 plate of 3 modules) : 15 modules/week (~800 total) Í R6 (1 plate of 3 modules) : 15 modules/week (~1100 total) Plan was to produce 4 plates per day (for R5N, R5S, R6 one reserve plate, hence we can alternate ring types during production) For R5 and R6 we have to wait for sensors (ST?) and hybrids. R3 production is continuing (700 modules or 35 working weeks) main concern for R3 is the delivery of the hybrids (end of next week we are out of hyrbids)