1 MICE PM Report Phase One installations to date Problems with target & decay solenoid and rolling platforms Phase One remaining items Progress with Phase.

Slides:



Advertisements
Similar presentations
1 UK Project Alan Grant, STFC. Finance How savings are made Update on stepIV position Milestones Critical Path - stepIV Concerns 2.
Advertisements

Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.
MICE: Hall Infrastructure Chris Nelson CEng CM15 8 th June 2006.
1 MICE CM31 Key schedule drivers for Step IV Schedule table Milestone summary Comment on Step V Step VI Andy Nichols, STFC, 3/11/11.
1 MICE Video Conference Installations to date Future installation work Plans for May shutdown MICO organisation Use of Technical Board.
Step IV Infrastructure update STFC Tim Hayler Eddie Holtom Norbert Collomb Graham Stokes 14 th December 2011 MICO170 meeting 1Tim Hayler.
MICE: Hall Infrastructure Chris Nelson CEng CM16 8 th Oct 2006.
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
1 UKNF/MICE Oversight Committee Open session Integration of the MICE project Background & local history Progress since 2007 Schedule & planning considerations.
1 Project Manager Report Andy Nichols, STFC – RAL MICE Collaboration Meeting, Harbin, 13-17th January 2009.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
1 Status of infrastructure MICE Video Conference, August 17, 2005 Yury Ivanyushenkov Applied Science Division, Engineering and Instrumentation Department.
1 Infrastructure issues Andy Nichols, STFC – RAL MICE Collaboration Meeting, Harbin, 13-17th January 2009.
1 Implications Of Infrastructure Build The Infrastructure Project is bigger than anyone thought, but now it’s understood The cost was underestimated, but.
1 Summary of MICE beamline & hall installations This is a very rough summary of the progress since mid-December Richard Apsimon & Andy Nichols MICO meeting.
Alan Grant OsC 30/4/ UK Project Finance & Schedule.
1 Project Manager Report Andy Nichols, STFC MICE Collaboration Meeting, RAL, June 2009.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Phase Two planning sequence Worries Don’t have time.
1 MICE Video Coference Project Manager Report Contents: Technical organisation of project Target and upstream beamline Muon beamline Infrastructure and.
1 MICE-Video Conference Status of MICE Hall Contents: General status Electrical Mechanical Preparing for Steps II & III Risks and worries Andy Nichols,
1 PM report International & UK programmes Overview Reconstructing the schedule The UK Project Management team Progress with major subsystems Substation.
1 Hall & Beamline Installation Richard Apsimon, Andy Nichols, Willie Spensley MICE Collaboration Meeting, th Feb 2008.
1 Technical Co-ordination, Phase One The shared post of PM/TC has worked quite well Six months ago there was much for us to learn:  Revised the WBS 
1 MICE - INFRASTRUCTURE MICO meeting 7 th February 2008 Tim Hayler.
MICE: overview K. Long, 18 March, Contents ► Introduction ► Beam line ► Infrastructure ► MICE steps ► Phase II (comment) ► Conclusions.
UKNF/MICE PSAG, 3/5/11 Spectrometer solenoids: –Repair plan still ‘in approval’, already two months late –Workshop/mini review at LBNL 10 th /11 th May.
Infrastructure Update As at 11 th March 2009 Remaining four plates now fitted to North shield wall North & South walls and all galleries are considered.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
1 MICE PM Report Completion of Infrastructure Target, solenoids Phase Two planning & schedule Non-MICE costs Staffing & visitors Don’t have time for a.
MICE MICO September ‘07 Chris Nelson. Beamline and Hall Shielded area virtually complete –SW corner –Replacement West wall concrete ordered, corner pieces.
Preparations in the MICE hall Video Conference 25 th June 09 Tim Hayler Andy Lintern Peter Lau Geoff Barber.
1 MICE CM28 PM Report Progress since CM27 Schedule, dates, milestones Electrical substation Visiting RAL Andy Nichols, STFC 4 th October 2010.
1 MICE CMPB Contents: Progress to date Project management things Plans for the May shutdown Steps towards Phase Two Problems and open issues summary Andy.
Magnetic Shielding Issues Roy Preece STFC - RAL. Overview Issues Items in harms way – Step IV Step IV mitigation plan –Racks –Compressors Current / Future.
RSLR mtg 28/3/2014 RLSR mtg Alan Grant. 2 RLSR mtg 28/3/ MICE Finances - Forward Look.
Magnetic Shielding Roy Preece. Issues Cooling channel initially designed without return yolks. Current North and South shielding walls designed to encapsulate.
1 Project Manager Report Andy Nichols, STFC – RAL MICE Collaboration Meeting, RAL, nd October 2008.
Magnetic Mitigation - Contents l Magnetic Mitigation General l West Wall Compressors l Rack Room 2 l Magnetic Shielding Yoke Jason Tarrant – Integration.
1 Project Manager Report Andy Nichols, STFC – RAL MICE Collaboration Meeting, DL, 4 th -7 th June 2008.
1 MICE Hall construction status Richard Apsimon MICE VC meeting 29th Nov 2007.
PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l History l Requirements l Environment l Design l Structural Integrity l Preparation l.
Spectrometer Solenoid Fabrication Status and Schedule Steve Virostek Lawrence Berkeley National Lab MICE RAL October 20, 2008.
MICE FAC Alain Blondel 21 september   MICE The International Muon Ionization Cooling Experiment BRIEF STATUS OF MICE.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
1 MICE PM Report Summary since CM21 Decay solenoid Infrastructure progress Step One Installation Worries MICE Video Conference, 19 th June, 2008.
1 MICE Beamline Installation, status & plans Contents: Upstream & Target, BPM Decay solenoid DSA, D2, Q4,5,6 cKOV support Q7,8,9 Open issues & concerns.
UK Update Package Managers Meeting 001 Roy Preece 13 th January 2014.
PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l Design l Structural Integrity l Preparation l Installation.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
Pre-CM33 schedule planning SuperMICO meeting, June 6th Motivation: For all of us to understand the main drivers behind the top-level MICE schedule So that.
OsC mtg 24/4/2014 OsC mtg Alan Grant. 2 OsC mtg 24/4/ MICE Finances - Forward Look.
1 MICE PM Report Phase One installations to date Some problems with target & Decay Solenoid Phase One remaining items, schedule & milestones Progress with.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
1 MICE PM Report General Update –Phase I nearing completion –MICE Power –Actions for Decay solenoid & target –Follow-ups from last VC –Conclusions MICE.
1 MICE PM Report Infrastructure/integration progress Electrical work AFC, diffuser, etc Help with project control & staffing issues Worries & problems.
1 Project Infrastructure for steps I-III Tim Hayler, STFC – RAL MICE Collaboration Meeting, RAL, nd October 2008.
Malcolm Ellis – Brunel University – 8th April The International Muon Ionization Cooling Experiment.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
1 UK Project Roy Preece – STFC Alan Grant, STFC. Finance Staffing Update on stepIV position Milestones Critical Path – stepIV Magnetic field mitigation.
Tuesday 9 th January Project Status Report Project Achievements Project Schedule Issues Finance Summary Risk Register Photos.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Worries Don’t have time for a detailed status report,
1 Implementation at RAL Iouri Ivaniouchenkov on behalf of Elwyn Baynham, Tom Bradshaw, Tony Jones, Jim Rochford Engineering Department, RAL MICE Collaboration.
What do we want to achieve in this running period? Michael S. Zisman Deputy Spokesmouse Center for Beam Physics Lawrence Berkeley National Laboratory MICO.
1 MICE CM29 Engineering Summary Cooling channel moving platforms – Norbert Floor Beams and plates – Andy L Magnetic modelling – Mike RF Engineering – Andy.
1 MICE CM25 Engineering Session Summary Contents: Infrastructure Diffuser Coupling Coils Radiation Shutter AFC module EMR Andy Nichols, STFC, 4-7 th November.
Step IV Step IV extended through 2016 QP/QD – in progress at FNAL Target dates SSU ECE for Feb now only 20% probability – no-field Feb Remainder for April/March.
MICE CM31 Schedule summary
MICE PM Report Progress with the Infrastructure A few problems
Presentation transcript:

1 MICE PM Report Phase One installations to date Problems with target & decay solenoid and rolling platforms Phase One remaining items Progress with Phase Two Project accommodation Non-MICE expenditure Don’t have time for a detailed status report, have a look at: MICE PSAG, 8 th October, 2008

2 Phase One Installations to date South shield wall: –It’s done! –Ready to install aluminium mezzanine (to support LH2 plant and Air conditioning), with false floor, next priority –North Shield wall support structure is complete –End November date for completion of Phase One heavy civil work still looks believable

3 Installations to date Main Hall PPS specification and plans have been agreed with ISIS and MICE End Jan 09 completion date for PPS Mound excavation and vacuum vents also complete, only needs landscaping now

4 Installations to date Progress with the beamline: –TOF0 now installed in DSA and cabled up but not tested –Noise pick-up problem with Beam profile monitors will be addressed in October shutdown (ISIS needs to be off) –Fixed beamstopper is made –Full sliding beamstopper at end of DSA is all made and has been dry-assembled – will be integrated during October shutdown –TOF1 still has problems with PMs – mid October delivery date looks impossible now. Maurizio Bonesini has promised to give detailed status report during October CM –No changes with KL or cKOV –Every endeavour to finish heavy civil work by end November – this dictates when tracker/readout can be integrated in Hall, effectively the start of step two –Diffuser is almost done at Oxford, but needs lower mass version of can end plate – comes to RAL 20 th November

5 Problems with Target & Decay Solenoid Target: –Weekly meetings organised for recovery of target –Jason Tarrant, new RAL engineer started –Magnetic measurements of actuator coils and parallel FEA study starting –Mechanical work will concentrate on refining shaft/bearing relationship –Goal is to get back to off-line test programme with ISIS to allow target operation 25 th Jan. Decay solenoid: –Nothing really new since last meeting, dates unchanged Rolling platform –Trouble with achieving flatness – sprung very badly in manufacture – not recoverable –Contractor has requested £15K contribution – need to discuss soon –Delivery date now 15 th December – regrettably not an embarrassment!

6 Phase One remaining items North Shield Wall: - about twelve plates fitted so far False floor –Order placed, again with Regal, completion by mid- November. Since last meeting need arisen for concrete reaction block for quench forces on floor – included with false floor order, all design work done. Anchor bolts being fitted now, but need to fill void between cellar infill and floor underside with concrete DSA roof and walkways –Solenoid platform installed, roof panels installed, railings and gate in fabrication, aim to install around DSA while ISIS running, subject to radiation survey.

7 Phase One remaining items Upgrade compressed air supply: –Compressor quotation underway, also circuit drawings –Estimate £12K Roof-extract fan –Somehow escaped from previous estimates – now know diameter – 450mm, fits existing hole in roof - good –Estimate £15K Fencing on R5.2 roof –Firm quote of £8K received, including approved access walkway across mound, still exploring ‘Well-Found Lab’ route for payment, but…..last minute change of height to 1.8m request from ISIS, so need to go round again –Estimate £10K Main Hall door upgrade - must do before December, as Hall-PPS critical, confirmed that BPG will meet the cost of door itself, but not surroundings – WFL? Quote in progress. RF refurbishment –Restoration/Installation costs - £30K, firm quote

8 Phase One Remaining items LH2 Installation: – September installation for prototype system will certainly slip to November/December 2008 – this is now confirmed –Two more safety reviews required: Hazop 2 review, by Serco, prototype control system needs to be finalised first Final safety review (RAL-ISIS-MICE) Both being organised by Jane Vickers & Mike Courthold for October –A concern: the same very overloaded group is responsible for: Decay solenoid Focus coils LH2 implementation

9 Progress with Phase Two Spectrometer Solenoids –Priority for modifications to vent pipework and Rad shield now shifted to magnet #2 – it becomes magnet #1 –MICE has decided to continue with field map at FNAL as per original plan –We get the first magnet early-mid Jan ‘09 –This defines step two start as early April ‘09 Coupling coils –Staffing problems at Harbin with subcontractors – now back on track, but probably six months’ delay –Productive design review at June CM, will follow up in October

10 Progress with Phase Two Focus Coils –Better progress with Tesla – they seem to have got the message regarding review preparation –Final design review scheduled for 3 rd November –Delivery dates still good

11 Project Accommodation We shortly have to vacate the R8 test area For the next four years, MICE will need a pre- integration/lab-space area at RAL We need: Three-phase supply Water Access to transport (3.5*3.5metre door) Crane – 5 tonnes –Need to start this discussion with RAL people; have already raised with Steve Quinton; is this correct approach?

Non-MICE Expenditure For Step Five, MICE needs 2MVA of electrical power Currently there is a marginal 1.2MVA Budget estimates received from Heather Loosemore for substation upgrade: Between £350 & 600K Lead time is two years Need to start worrying now! This and other items need to be WFL funded David Findlay has confirmed that no route to WFL exists through ISIS Meeting fixed with Sean Stuart (RAL Operations) for 16 th October as this seems the next logical step Need to start thinking of fall-back…… 12

Non-MICE expenditure Current list: –Substation upgrade…………..……..£600K –Roof fan…………………………..……£15K –Railings around roof……………..…£10K –Main door replacement work……..£20K Total …... £645K –Also need to fund refurbishment of LH2 control room, installation of racks, doorway and ventilation – estimate in progress, expect £30K –Painting & decorating of whole MICE hall – BPG will pay will confirm with Sean Stuart 13