Project Management Chapter 8 (Crashing).

Slides:



Advertisements
Similar presentations
3 Project Management PowerPoint presentation to accompany
Advertisements

Chapter 7 Project Management
Introduction to Management Science
2 – 1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. Project Management 2.
1 Topics to cover in 2 nd part ( to p2). 2 Chapter 8 - Project Management Chapter Topics ( to p3)
Project Scheduling: Networks, Duration estimation, and Critical Path.
Project Scheduling: Networks, Duration Estimation, and Critical Path
Chapter 9 Project Management.
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Day 15.
Operations and Supply Chain Management, 8th Edition
Project Management An interrelated set of activities with definite starting and ending points, which results in a unique outcome for a specific allocation.
■ Project duration can be reduced by assigning more resources to project activities. ■ However, doing this increases project cost. ■ Decision is based.
To Accompany Russell and Taylor, Operations Management, 4th Edition,  2003 Prentice-Hall, Inc. All rights reserved. Project Management OPIM 310-Lecture.
To Accompany Russell and Taylor, Operations Management, 4th Edition,  2003 Prentice-Hall, Inc. All rights reserved. Chapter 6 Project Management To Accompany.
Network Flow Models Chapter 7.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
Copyright © 2012 Pearson Education, Inc. Publishing as Prentice Hall. Section 7.2 Right Triangle Trigonometry.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
7-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Network Flow Models Chapter 7.
7-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Network Flow Models Chapter 7.
Shortest Route, Minimal Spanning Tree and Maximal Flow Models
Project Management Chapter 8.
© J. Christopher Beck Lecture 5: Project Planning 2.
3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall  Complex and temporary task of many related activities. (not ‘business as usual’)  May.
To Accompany Russell and Taylor, Operations Management, 4th Edition,  2003 Prentice-Hall, Inc. All rights reserved. Chapter 17 Project Management Part.
McGraw-Hill/Irwin Copyright © 2007 by The McGraw-Hill Companies, Inc. All rights reserved. 17 Project Management.
9-1 Chapter 9 Project Scheduling Chapter 9 Project Scheduling McGraw-Hill/Irwin Copyright © 2005 by The McGraw-Hill Companies, Inc. All rights reserved.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
To Accompany Russell and Taylor, Operations Management, 4th Edition,  2003 Prentice-Hall, Inc. All rights reserved. Chapter 6 Project Management To Accompany.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
Project Planning and Budgeting Recall the four stages Project Definition and Conceptualization Project Planning and Budgeting Project Execution and Control.
6-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Transportation, Transshipment, and Assignment Problems Chapter 6.
PowerPoint presentation to accompany Heizer/Render – Principles of Operations Management, 5e, and Operations Management, 7e © 2004 by Prentice Hall, Inc.,
4-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Linear Programming: Modeling Examples Chapter 4- Part2.
Lags in Precedence Relationships
7-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Network Flow Models Chapter 7.
Chapter 8 - Project Management1 Lecture 2 Today’s lecture covers the followings: 1.To study “project crashing” concept 2.LP formulation for project management.
The Inverse Trigonometric Functions (Continued)
Project Management Chapter 8.
Project Management Chapter Topics
Project Management: PERT/CPM
Chapter 5: Project Time Management Doddy Prayogo, Ph.D.
P.I.I.M.T American University of Leadership
Learning Objectives When you complete this chapter, you should be able to : Identify or Define: Work breakdown structure Critical path AOA and AON Networks.
Section 9.1 Polar Coordinates
Project scheduling Chapter 10 Copyright ©2016 Pearson Education, Inc.
Building Exponential, Logarithmic, and Logistic Models from Data
Chapter 8 - Project Management
Project Planning and Budgeting
Section 2.4 Circles Copyright © 2012 Pearson Education, Inc. Publishing as Prentice Hall.
Equations Quadratic in Form Absolute Value Equations
Project Scheduling: networks, duration estimation, and critical path
Section 8.3 The Law of Cosines
Section 11.8 Linear Programming
Copyright © 2008 Pearson Prentice Hall Inc.
Copyright © 2008 Pearson Prentice Hall Inc.
Project Scheduling: Lagging, Crashing and Activity Networks
Exponential Equations
Mathematical Models: Building Functions
Copyright © 2008 Pearson Prentice Hall Inc.
Copyright © 2008 Pearson Prentice Hall Inc.
Systems of Linear Equations: Matrices
Quadratic Equations in the Complex Number System
Properties of Rational Functions
Modeling Cross-Cutting Relationships with Allocations
Copyright © 2008 Pearson Prentice Hall Inc.
Copyright © 2008 Pearson Prentice Hall Inc.
The Inverse Trigonometric Functions (Continued)
Managing Risk Chapter 7.
Presentation transcript:

Project Management Chapter 8 (Crashing)

Project Crashing Basic Concept In last lecture, we studied on how to use CPM and PERT to identify critical path for a project problem Now, the question is: Question: Can we cut short its project completion time? If so, how! Chapter 8 - Project Management

Project Crashing Solution! Yes, the project duration can be reduced by assigning more resources to project activities. But, doing this would somehow increase our project cost! How do we strike a balance? Project crashing is a method for shortening project duration by reducing one or more critical activities to a time less than normal activity time.

Trade-off concept Here, we adopt the “Trade-off” concept We attempt to “crash” some “critical” events by allocating more resources to them, so that the time of one or more critical activities is reduced to a time that is less than the normal activity time. How to do that: Question: What criteria should it be based on when deciding to crashing critical times?

Example – crashing (1) Max weeks can be crashed The critical path is 1-2-3, the completion time =11 How? Path: 1-2-3 = 5+6=11 weeks Path: 1-3 = 5 weeks Now, how many days can we “crash” it? Normal weeks 2 6(3) 5 (1) 3 1 5(0)

Example – crashing (1) 6(3) 5 (1) 5(0) 2 6(3) 5 (1) 3 1 5(0) The maximum time that can be crashed for: Path 1-2-3 = 1 + 3 = 4 Path 1-3 = 0 Should we use up all these 4 weeks?

Example – crashing (1) 6(3) 5 (1) 5(0) 3(0) 4(0) 2 6(3) 5 (1) 3 1 5(0) If we used all 4 days, then path 1-2-3 has (5-1) + (6-3) = 7 completion weeks Now, we need to check if the completion time for path 1-3 has lesser than 7 weeks (why?) Now, path 1-3 has (5-0) = 5 weeks Since path 1-3 still shorter than 7 weeks, we used up all 4 crashed weeks Question: What if path 1-3 has, say 8 weeks completion time?

Example – crashing (1) Such as 6(3) 5 (1) 8(0) 2 6(3) 5 (1) 3 1 8(0) Now, we cannot use all 4 days (Why?) Because path 1-2-3 will not be critical path anymore as path 1-3 would now has longest hour to finish Rule: When a path is a critical path, it will not stay as a critical path So, we can only reduce the path 1-2-3 completion time to the same time as path 1-3. (HOW?)

Example – crashing (1) Solution: 6(3) 5 (1) 8(0) 2 6(3) 5 (1) 3 1 8(0) We can only reduce total time for path 1-2-3 = path 1-3, that is 8 weeks If the cost for path 1-2 and path 2-3 is the same then We can random pick them to crash so that its completion Time is 8 weeks

Example – crashing (1) Solution: 4(0) 4(1) 6(3) 5 (1) 8(0) 3(0) OR 2 6(3) 5 (1) 3 1 8(0) 3(0) OR 5 (1) 6(3) 2 1 3 8(0) Now, paths 1-2-3 and 1-3 are both critical paths

AOA Network for House Building Project The Project Network AOA Network for House Building Project Figure 8.6 Expanded Network for Building a House Showing Concurrent Activities Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

Project Crashing and Time-Cost Trade-Off Example Problem (1 of 5) Figure 8.19 The Project Network for Building a House

Project Crashing and Time-Cost Trade-Off Example Problem (3 of 5) Table 8.4

Project Crashing and Time-Cost Trade-Off Example Problem (2 of 5) Crash cost & crash time have a linear relationship: Figure 8.20 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

Project Crashing and Time-Cost Trade-Off General Relationship of Time and Cost (2 of 2) Figure 8.23 The Time-Cost Trade-Off Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

Project Crashing and Time-Cost Trade-Off Example Problem (4 of 5) Figure 8.21 Network with Normal Activity Times and Weekly Crashing Costs

Project Crashing and Time-Cost Trade-Off Example Problem (5 of 5) As activities are crashed, the critical path may change and several paths may become critical. Figure 8.22 Revised Network with Activity 1 Crashed

Project Crashing and Time-Cost Trade-Off Project Crashing with QM for Windows Exhibit 8.16

Formulating as a Linear Programming Model AOA Network for House Building Project Figure 8.6 Expanded Network for Building a House Showing Concurrent Activities Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

Formulating as a Linear Programming Model Example Problem Formulation and Data (1 of 2) Figure 8.24 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

Example Problem Formulation and Data (2 of 2) The CPM/PERT Network Example Problem Formulation and Data (2 of 2) Minimize Z = x1 + x2 + x3 + x4 + x5 + x6 + x7 subject to: x2 - x1  12 x3 - x2  8 x4 - x2  4 x4 - x3  0 x5 - x4  4 x6 - x4  12 x6 - x5  4 x7 - x6  4 xi, xj  0 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

Formulating as a Linear Programming Model The CPM/PERT Network Formulating as a Linear Programming Model The objective is to minimize the project duration (critical path time). General linear programming model with AOA convention: Minimize Z = xi subject to: xj - xi  tij for all activities i  j xi, xj  0 Where: xi = earliest event time of node i xj = earliest event time of node j tij = time of activity i  j i Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

Project Crashing with Linear Programming Example Problem – Model Formulation Minimize Z = $400y12 + 500y23 + 3000y24 + 200y45 + 7000y46 + 200y56 + 7000y67 subject to: y12  5 y12 + x2 - x1  12 x7  30 y23  3 y23 + x3 - x2  8 xi, yij ≥ 0 y24  1 y24 + x4 - x2  4 y34  0 y34 + x4 - x3  0 y45  3 y45 + x5 - x4  4 y46  3 y46 + x6 - x4  12 y56  3 y56 + x6 - x5  4 y67  1 x67 + x7 - x6  4 xi = earliest event time of node i xj = earliest event time of node j yij = amount of time by which activity i  j is crashed Objective is to minimize the cost of crashing Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall