Conducted By: Dr. Madhu Fernando, PMP, DBA, MEng. MGT 30725 PROJECT MANAGEMENT LESSON 5 AND 6: PROJECT PLANNING – TIME AND COST PLANNING AND MANAGEMENT.

Slides:



Advertisements
Similar presentations
Project Cost Management
Advertisements

Budget Management. 57 Budget Management Budget Development Good scheduling skills and abilities Understanding of the project scope Well developed WBS.
Project Cost Management Chapter 7
Project Cost Management Estimation Budget Cost Control
Project Cost Management Sections of this presentation were adapted from A Guide to the Project Management Body of Knowledge 4 th Edition, Project Management.
Chapter 10: Monitoring and Controlling Change
Degree and Graduation Seminar Cost Management
Earned Value Project Management: a powerful tool for software projects
Project Monitoring and Control. Introduction Goal: ensuring that the project is on time and on budget and/or highlight any deviation from the plan Areas.
Project Cost Management
Project Evaluation and Control
The Project Management Body of Knowledge (PMBOK)
Progress and Performance Measurement and Evaluation CHAPTER THIRTEEN Student Version Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved.
Project Evaluation and Control
Cost Management Week 6-7 Learning Objectives
Project Management 6e..
EARNED VALUE MANAGEMENT SYSTEM A Project Performance Tool
PRO 3002 Pam Soderholm Welcome To Class!. In Earned Value Analysis, what does “AC” stand for? Actual Cost of Work Performed QUALITY.
P ROJECT M ANAGEMENT, PMI A PPROACH (PMP) P ROJECT C OST M ANAGEMENT Sayed Ahmed BSc. Eng. in CSc. & Eng. (BUET, Bangladesh) MSc. in CSc. (University of.
This work is licensed under a Creative Commons Attribution 3.0 Unported LicenseCreative Commons Attribution 3.0 Unported License (CC-BY). Project Management.
PowerPoint Presentation by Charlie Cook THE MANAGERIAL PROCESS Clifford F. Gray Eric W. Larson Progress and Performance Measurement and Evaluation Chapter.
Project Management Methodology Project monitoring and control.
Progress and Performance Measurement and Evaluation CHAPTER THIRTEEN Student Version Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved.
Chapter 13: Progress and Performance Measurement and Evaluation
Q N U Earned Value Management They Say I have to Do It, But Why??? By Ursula Kuehn, PMP, EVP UQN and Associates.
BSBPMG402A Apply Time Management Techniques 1 Apply Time Management Techniques Week 6 Project Time Processes – Part 2 C ertificate IV in Project Management.
PPMT CE-408T Engr. Faisal ur Rehman CED N-W.F.P UET P.
POST GRADUATE PROGRAM OF INFORMATION TECHNOLOGY
Project Cost Management
PowerPoint Presentation by Charlie Cook Copyright © 2006 The McGraw-Hill Companies. All rights reserved. THE MANAGERIAL PROCESS Clifford F. Gray Eric W.
Project Cost Management
Conducted By: Dr. Madhu Fernando, PMP, DBA, MEng. MGT PROJECT MANAGEMENT LESSON 7: PROJECT BUDGET: BUDGETING, COST CONTROL AND FORECAST 1.
BSBPMG403A Apply Cost Management Techniques Apply Project Cost Management Techniques Project Cost Processes C ertificate IV in Project Management
Software Project Management (SPM)
9-1 Project Management from Simple to Complex. 9-2 This work is licensed under the Creative Commons Attribution-Noncommercial-Share Alike 3.0 Unported.
EARNED VALUE MANAGEMENT (EVM)
PRO 3020 Pam Soderholm Welcome To Class!. In Earned Value Analysis, what does “AC” stand for? Actual Cost of Work Performed.
BSBPMG504A Manage Project Costs Manage Project Costs Project Cost Processes Diploma of Project Management Qualification Code BSB51507 Unit Code BSBPMG504A.
BSBPMG504A Manage Project Costs 7.1 Estimate Costs Adapted from PMBOK 4 th Edition InitiationPlanning ExecutionClose Monitor Control The process of developing.
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall13-1 Project Evaluation and Control Chapter 13.
Report Performance Monitor & Control Risk Administer Procurement MONITORING & CONTROLLING PROCESS.
Earned Value Analysis Tracking Project Progress. Introduction | Components | Project Scenario | Values | Calculations | Forecasts | Summary l What Is.
1 Earned value analysis Planned value (PV) or Budgeted cost of work scheduled (BCWS) – original estimate of the effort/cost to complete a task (compare.
PMP Study Guide Chapter 11: Controlling Work Results.
SOFTWARE PROJECT MANAGEMENT
Information Technology Project Management, Six th Edition Kathy Schwalbe Copyright Disampaikan Oleh : Wiwid Dolianto S.Kom, MT Universitas Muhammadiyah.
EVM – Do You Really Know What the Numbers Mean? Booz | Allen |Hamilton Seth Huckabee EVP, PMP, PMI-SP.
1 Understanding Earned Value in Under an Hour Breakout Session # A11 Name: Wayne Brantley, MS Ed, PMP, ITIL Senior Director of Professional Education.
0 Earned Value Management. 1  What is it?  Where did it come from?  What’s so special about it?  How do you do it?  What is an EVMS?
IT-301 Project Management I: Unit 4: Cost Management.
Information Technology Project Management, Seventh Edition Note: See the text itself for full citations.
BSBPMG503A Manage Project Time Manage Project Time Project Time Processes Part 2 Diploma of Project Management Qualification Code BSB51507 Unit Code.
Project Time Management Based on PMBOK 5 th Edition Abdelrahman Sheta, PMP,ITIL 1PMP - Project Time Managementfacebook.com/Sheta.Page.
Agenda ‒ Cost Management ‒ Cost Budgeting ‒ Cost Control Learning Goals 1.Cost Control 2.Earned Value Management.
PowerPoint Presentation by Charlie Cook THE MANAGERIAL PROCESS Clifford F. Gray Eric W. Larson Progress and Performance Measurement and Evaluation Chapter.
Developing the schedule – Tracking Gantt charts Critical path method – Longest path, earliest time Schedule trade-offs using CPM – Free slack, total slack.
Earned Value Management EVM. 03/06/2013 Earned Value Management Planned Value (PV): –Budget of the planned work.
Project Cost Management
PROJECT MANAGEMENT AND CONTROL
Project COST Management
Budget Planning.
CHAPTER:7 Project Cost Management
Project Management MGT 30725
Chapter 7: Project Cost Management
Project Cost Management
Project Cost Management
Earned Value Measures Planned Value (PV) Earned Value (EV)
Project Cost Management
Managing Project Work, Scope, Schedules, and Cost
Where We Are Now. Where We Are Now Structure of a Project Monitoring Information System Creating a project monitoring system involves determining:
Presentation transcript:

Conducted By: Dr. Madhu Fernando, PMP, DBA, MEng. MGT PROJECT MANAGEMENT LESSON 5 AND 6: PROJECT PLANNING – TIME AND COST PLANNING AND MANAGEMENT 1

PROJECT TIME MANAGEMENT Project Time Management Process Plan Schedule Management Define Activities Sequence Activities Estimate Activity Resources Estimate Activity Duration Develop Schedule Control Schedule 2

PLAN SCHEDULE MANAGEMENT Process of establishing the policies, procedures, and documentation for planning, developing, executing, managing, and controlling the project schedule. 3

DEFINE ACTIVITIES The Process of identifying and documenting the specific actions to be performed to produce the project deliverables. 4

SEQUENCE ACTIVITIES The Process of identifying and documenting the relationships among the project activities. 5

ESTIMATE ACTIVITY RESOURCES The Process of estimating the type and quantities of the material, human resources, or equipment, or supplies required to perform each activity. 6

ESTIMATE ACTIVITY DURATION The Process of estimating number of work periods required to complete individual activities with estimated resources. 7

PROJECT ESTIMATING TECHNIQUES Estimating methodDescription Analogous estimatingGenerally used at the start of the project when not much is known. Compares the current project with past similar projects. A quick and relatively easy method of estimating, although not terribly accurate. Parametric estimatingUsed for estimates that are quantitatively based, such as dollars per square foot or number of installations per day. A relatively simple method, but not every activity or cost can be estimated quantitatively. Three-point estimatingAccounts for uncertainty associated with estimating by determining an optimistic (best case, represented by O), most likely (represented by M), and pessimistic (worst case, represented by P) scenario. The most likely estimate is weighted most heavily. The equation is (O + 4M + P) / 6 Bottom-up estimatingUsed when there is significant detail about the activity. A detailed assessment of the resources, capabilities, and amounts are used to determine an accurate duration or cost estimate. This is the most accurate method but also the most time- consuming and expensive form of estimating.

DEVELOP SCHEDULE The Process of analyzing activity sequences, durations, resource requirements and schedule constraints to create a project schedule. 9

CRITICAL PATH METHOD AND PERT TECHNIQUES Practice : CPM Calculation PERT Calculation Individual Exercises

CONTROL SCHEDULE The Process of monitoring the status of project activities to update project progress and manage changes to the schedule baseline to achieve the plan. 11

PROJECT COST MANAGEMENT Project Cost Management involves developing the cost baseline, project budget and control changes. 1.Estimate Cost 2.Determine Budget 3.Control cost

ESTIMATE COST – TOOLS AND TECHNIQUES Expert judgment Analogous estimating Parametric estimating Bottom-up estimating Three point estimating

COST PLANNING – DETERMINE BUDGET Cost budgeting also uses similar tools and establish the project budget by aggregating cost of the activities to a total budget. The approved budget will provide the cost baseline for the project.

CONTROL COST  Approved project budget provides the baseline for the project cost.  Any changes to the cost baseline must be monitored and approved only with an approved change request Tools and Techniques: Earned value management Forecasting To-complete Performance index (TCPI) Performance reviews Variance analysis Project management software

CONTROL COST WITH EARNED VALUE TECHNIQUE Earned Value Management Formulas for performance measurement BAC = Budget at Completion PV = Planned Value AC = Actual Cost EV = Earned Value CV = Cost Variance CV = EV- AC SV = Schedule Variance SV = EV – PV CPI = EV/AC SPI = EV/ PV EAC = AC + ETC ETC = BAC-EV