Tuesday 25 th October 08:22 Dump the 25 ns spaced 2100 x 1020 bunches 08:30 – 09:30 25 ns tests with different spacing between trains Until 12:00: Access.

Slides:



Advertisements
Similar presentations
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Advertisements

Mo morning set up 228 bunch injection (36 bunch trains), ramp, squeeze, collisions h luminosity (depending on experiments) ATLAS length scale calibration.
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Monday 4 th to Friday 8 th Technical stop  Coordination: Katy Foraz  Machine back to Operations Friday evening on schedule Major cryogenics intervention.
PROFIBUS controller problem (SEU) on cryo valve on DFBMH (600 A circuit RQ6.L7B1/2). Loss of cryo maintain ==> Beam dump. End of fill #1975 after ~2.5.
Wednesday 12 th September Pumping, removal of vacuum equipment from tunnel in the morning TOTEM & ALFA, RP movement tests: OK 11:50 pre-cycle started,
Lot’s of time lost due to cryo problem in IR8. Major impact, therefore review of MD program… Start discussion here, please let us know your input. Will.
31/10/2011LHC 8:30 meeting 1 Overview LHC Operation Week 43 Machine Coordinators: Barbara Holzer & Jan Uythoven.
21/05/2012LHC 8:30 meeting Overview Week 20 Injectors, LHCb polarity, Beam-Beam Coordinators: Bernhard Holzer, Jan Uythoven.
5/11/2012LHC 8:30 meeting Summary of Week 44 Coordination: Mike Lamont & Jan Uythoven.
Monday 29 October 08:48 V/dM scan CMS end of fill #3236. Check of “fast scan”. 10:06 V/dM scan finished, start of RF studies, reducing RF voltage. 11:10.
● 08:30 Loaded by mistake squeeze function to 2 m  Dumped beams ● 10:30-13:00 Test of new algorithm for long. Emittance blow-up to minimize oscillations.
LHC Status Sat Morning 18-June Bernhard Holzer, Gianluigi Arduini et al Tentative Planning: Luminosity 1092 x 1092 Access: installing low pass filter at.
ION COMMISSIONING REVISITED 1 Thanks to: John Jowett, Walter Venturini. Matteo Solfaroli.
LHC 23 June :07: Started injection cleaning with B1. 08:13: Fault on MKI B2. –MKI Beam 2 in P8 had a breakdown at 07:49 during the SoftStart process.
Summary of Week 30 G. Arduini, J. Wenninger Main aims: “Adiabatically” increase peak luminosity by emittance reduction Luminosity production.
Monday h00: End of fill #1640: 3.7 pb h14: RB S12 and S23 tripped before loading rampdown table, active filter. MPE piquet. Fip_Com_Lost.
LHC Status Mo Morning 20-June Bernhard Holzer, Gianluigi Arduini et al 7 runs The Week.
Tuesday 17 th April 04:00 Prepare second fill for v/d Meer scans. 06:22 Stable beams, v/d Meer scans for Alice and LHCb. 13:20 End v/d Meer scans.Dump.
LHC Progress Friday 30 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
LHC Progress Thursday 29 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
Monday :00 Injection for physics fill # :00 Stable beams fill #1816, luminosity ~1.2x1033 cm-2s-1 11:08 Beams dumped. QPS trigger on detector.
LHC status Wednesday 15 th July 2015 Coordination: Wolfgang Hofle, Mike Lamont.
09:25 Operator dump fill #2178, integrated lumi 107/108/18 nb-1. Trip of RQ4.R6 (fire heaters discharged) just after the beam dump but the QPS gave no.
From yesterday LHC status Wednesday 26 th Welcome Verena back on shift 07:08 Access in PM85 for piquet EPC (O.Fournier).  Fuse on RD2.R8 circuit.
04:01 Injection kicker timing problems B2  Injection pre-pulse shifted, causing BETS to inhibit beam injection. 144 bunches on TDI.  Run without ROF.A81B2.
Tuesday 24 th July - morning 10:15 Operator dump of fill 2873  Initial luminosity: 5.83e33 cm-2s-1  12 hours stable beams  151 pb-1 delivered  Initial.
06:00 – Ongoing injection problems on beam 2  07:42 – Start of injection investigations  11:11 – Injection problem fixed. Resteering of transfer line.
Lumi scan limits checked (in preparation for next fill VdM scans).  Trims of up to 150 um per beam in IP1 & IP2 both planes both beams were done (IP5.
Thursday 20 th April 01:53 RCBV17.R7B2 tripped as happened few days ago: SIS intercepted. 05:54 Stable beams, 1380b, still RF problems B1, abort gap cleaning.
Production running 1 pb-1Lost to Mon h2062e32EOF studies Tue h17.152e32UFO Q8.L5 Tue h e32OP request Thu h e32OP.
Thursday 27 th October 00:57 fill 2257 dumped during squeeze (RQTF.A67B1) 03:52 stable beams fill #2258 4:33 Dumped, problem of LBDS dilution kicker power.
07:00 Dump fil #2219, 123 pb -1 delivered. Trim TDI parking position to +/- 55 mm in the collimator BP trimmed the temperature kicker limit to 62 degrees.
Monday 19 th March 07:33 Lost (another) beam in the squeeze, beyond 2 m, B2 hits 1/3 resonance. 08:30 Start (another) ramp  Try to correct coupling and.
Tue 23/8 – Wed 24/8 09:00 Start 90 m optics run – Preparation and verification of the collimation functions – Re-generation of functions for Transverse.
Saturday Coordinators weekend: Mike Lamont, Eva Barbara Holzer
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
Machine Coordinators: G. Arduini, J. Wenninger
Friday 15th June 01:11 Injection.
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Monday 11/07: Recovery Plenty of accesses.
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Tue :25 Beams dumped due to RF vacuum interlock
LHC Morning Meeting - G. Arduini
Summary of Week 11: 14 – 21 March
Fri 29/7 – Sat 30/7 09:00 End of fill 1990, PC trip RCBXV3.R1 (likely SEU on QPS). Integrated Luminosity: 41 pb-1. Access for MKI2 main switch replacement.
Wednesday Morning 8: :30 end of fill study - octupole polarity inversion (Elias, Tatiana, Alexey, Georges, …): Goal: study the effect of the.
Thursday 17th May 01:11 Fill #2633 dump in squeeze arc circulator load channel Ad1B 03:16 Fill #2644 Stable beams, lumi 5.2e33 cm-2s-1 04:38 Dumped by.
Summary of Week 16 G. Arduini, J. Wenninger
Lost at 12:05 to power converter (RTQX2.R1) problem
Week 35 – Technical Stop and Restart
04-05/08/2010 End of physics at ~11:00 after 18.5 hours ~120 nb-1.
Yesterday’s morning’s controls issues
Tuesday 22 November 2011.
Sunday
Wednesday 10/5 Cryo recovery until 18:30
Monday 24 October hours of 25ns MD
Tue/Wed 12/ :00 Probe beam back again
Monday 6th 07:39 Dump fill #1854, RQ6.L2 tripped, followed by access
Friday 8/10/10 - Morning Planned to keep fill until the afternoon
Thu 04:00 Fill #2729 Stable Beams. Initial lumi 6.5e33 cm-2 s-1.
Wednesday 16th May 03:05 beam dump, RF fault crowbar problem on module M1B2 06:09 Another crowbar at injection. Access for RF; problem Beam Imminent Warning.
Tuesday 20 September 2011.
Wednesday 23/2 Thanks CRYO!!!.
Fri :52 Stable beams fill #2536
Another Immortal Fill….
Wednesday 26 October 2011.
Saturday 26 November 2011.
HI2011 Commissioning Status
Presentation transcript:

Tuesday 25 th October 08:22 Dump the 25 ns spaced 2100 x 1020 bunches 08:30 – 09:30 25 ns tests with different spacing between trains Until 12:00: Access Problems getting back  BLM sanity check repeated 4 times, HC.BLM.SR6.C - Connectivity: ERROR, not the first and not the last time… 14:00 Injecting pilots 15:15 Injecting high intensity bunches for pile-up tests 16:20 Stable beams & separation tests 19:40 Dump & test squeeze in IP2 without beam  We do the dry run for Alice squeeze at 1 meter beam process. The RQ5.L2B2 tripped during the squeeze, followed by the RQ5.L2B1. 21:20 Waiting for beam from the SPS, RF problem 22:00 RQT13.R5B1 tripped while sitting at injection without beam  Piquet said that in case it trips again it will need an access, but he hopes that it can survive the night. This converter had tripped already once last 17 October and one more time one month before that) 1 LHC 8:30 meeting 26/10/2011

Tuesday night 22:30 injecting probes 23:30 SIS interlock for RQT13.R5B1/B2 due to a LT_Fip_Com_lost, Piquet QPS called 00:00 Loss of PIC when powercycling RQT13.R5B1&B2: again 02:30 Sandrine analysed the last trip of RQT13.R5B1 and she is not sure if in fact the problem is that the circuit quenches at injection. We finnaly agreed on resetting and trying to proceed 05:00 Lots of problems with BPM in IQC and YASP. BPMs missing in yasp again. Called Ralph S. for BPM front-end problems. Complete reboot of crate instead of restarting processes. 06:22 Stable beams, initial lumi around 3.5e33 cm-2s-1 2 LHC 8:30 meeting 26/10/2011

PM of 25 ns MD The injection of the beam was strongly hampered by the pressure rise on MKI8 and in particular by magnet D. Because of that the filling scheme had to be adapted to minimize the pressure rise and therefore the impact on the filling rate. During a soft-start of kicker MKI8 a pressure spike has occurred and it required an extended conditioning  HV magnet break down due to the bad vacuum Finally managed to inject 2100 (B1) against 1020 (B2) bunches with spacing of 925 ns between trains of 72 bunches. Blow-up and losses are still observed along the bunch trains but there is a trend to improvement of the lifetime Heat load data have been collected as well as vacuum data and they indicate an improvement when normalized to current but they must still be analyzed in detail The last hour was dedicated to collect data in steady conditions. From 08:30 to 09:30 we took some measurements with trains of variable spacing to try to quantify SEY and reflectivity at the end of the scrubbing 3 LHC 8:30 meeting 26/10/2011 Gianluigi and vac team

Injection kicker MKI HV break down 4 LHC 8:30 meeting 26/10/2011 Vacuum spike of few 10-7 Happened during soft start after scrubbing period with bad vacuum At voltage which was slightly above nominal

Injection kicker MKI HV break down Electrical breakdown in MKI8-D kicker magnet during SoftStart (54.3kV, 1200ns). This followed an extended period of 25ns beam and vacuum of ~9e-9mbar in the MKI8 tanks as well as high pressure in the nearby beam pipes. ALL electron cloud solenoids were turned off around the MKI8 kickers resulting in the high pressure. Confusing about the ecloud coils during the MD  *** ECLOUD CIRCUIT VIESA.193.5R8.C MUST *NOT* BE TURNED-OFF, EVEN DURING SCRUBBING, AS THESE SOLENOIDS ARE ON THE INTERCONNECTS BETWEEN SOME OF THE MKI8 KICKER MAGNETS ***  *** ECLOUD CIRCUIT VIESA.3.6R8.C CAN BE TURNED-OFF FOR SCRUBBING. THESE SOLENOIDS ARE ON THE MKI SIDES OF Q4 & Q5, but are not extremely close to the MKIs *** The electrical breakdown demonstrates the de-conditioning of the MKIs by high pressure (as per 17 April 2011). This also reinforces the importance of the SIS MKI vacuum interlock (normally set to 2e-9mbar, but relaxed to 2.5e-9mbar for the 25ns MD). We should consider to always run an extended SoftStart (about 30 min instead of 10 min), following a period of time with high pressure in the MKI tanks, to re-condition the kicker magnets 5 LHC 8:30 meeting 26/10/2011 Mike Barnes

RF with 25 ns The 1-T feedback loops were commissioned on all cavities (except for 7B1) with the 25 ns MD beam last night. This system compensates for the transient beam loading caused by the gaps in the beam current. With 1E11 p/bunch at 25 ns spacing, the local beam intensity ( and therefore the resulting transient beam loading) is 30% higher than with 1.5E11 p/bunch at 50 ns spacing. With 25 ns spacing the system showed a very significant (factor five) reduction of the cavity phase modulation (caused by beam current) that was reduced from 4 deg pk-pk to 0.8 deg pk-pk. The demanded klystron peak power did not change significantly. 6 LHC 8:30 meeting 26/10/2011 Philippe & Co.

Access Request from ALICE for 1 hour Finally took about 2 hours  ALICE  Problem on the UJ14/16 PADs delayed the intervention of ZDC people. List of accesses: - QPS for power-cyle on QRD/F controller in cell 11L4; - QPS restart of PC in UA83; - ButMons removal in UX65; - check of buffer zone by RP in PZ33; - RF, BI and EPC at point 4; - ALICE (twice); - ZDC experts. RF  This mor ning we went in UX45 to solve the problem with 7B1 (cables disconnected!!!!). Its 1-T fdbk is now operational. We then spent an hour checking the behaviour in physics settings (Q=60k, 1.5 MV/cavity). The system is operational on all cavities and will be used for all beams from now on. 7 LHC 8:30 meeting 26/10/2011

High pile-up physics run (not an MD) 8 LHC 8:30 meeting 26/10/ x 11 bunches average bunch intensities fooled by tails...

Pile-up run Injected 11 high intensity bunches ( e11ppb, ~2um at the SPS) to give IP1/5 10 high pile-up colliding pairs (+1 colliding pair for IP8 and IP2) Minimized the time at injection by a semi-dedicated SPS supercycle (LHC4+CNGS only) Observed emittance blow up at the LHC: ~3-3.5um in collisions from wire scanners Achieved a peak pile-up of about 35 Observed once again the impact of number of HO collisions of loss pattern (lower losses for lower number of HO collisions) Separation scans to reduce the pile-up in steps for both CMS and ATLAS (~20% reduction per step) At the end, turned off ADT with head-on colliding beams to observe possible coherent modes Additionally, acquired orbit data which will be looked at offline. 9 LHC 8:30 meeting 26/10/2011 Georges, Giulia, Michaela, Werner, Xavier

SPS extraction kicker MKE4 waveform scan Performed on SPS with TT40 TED in  Data from BTV Understand problems with steering of B2 and injection oscillation pattern Clearly, steering with 12b in the first few hundred ns is not optimal  Resulting in beam not well centred when using 144 bunches = full kicker length 10 LHC 8:30 meeting 26/10/2011 Watch that scale! Brennan, Verena

Physics fill #2254 Filling, MKI2 vacuum up to 8E-9 CMS vacuum up to about 10-7 again Lumi around 3.5e33 cm-2s-1 11 LHC 8:30 meeting 26/10/2011 OK when going into collisions

The Plan Physics Thursday PM: run with enhanced satellites  And likely some smaller intensities for the normal bunches Friday: test of IP2 squeezed optics and aperture measurements, in preparation of the ion run.  Scheduled for 24 hours. Sunday 18:00: start of MD period 12 LHC 8:30 meeting 26/10/2011

8h30 meeting26-Oct-2011CERNMassimiliano Ferro-Luzzi 13 Magnets and luminometers during MD  proposals and wishes

8h30 meeting26-Oct-2011CERNMassimiliano Ferro-Luzzi 14Magnets  ALICE: no special intentions/requirements from expt. Can keep the magnets ON or OFF. –what is needed for the ion setup/MD this and next week ?  ATLAS: The ATLAS magnets will stay ON during the MD. ATLAS will then ramp down the toroid on Mon 7nov in the morning and ramp up again on Friday 11nov. The solenoid will stay ON.  CMS: expt would like to ramp down the solenoid on Tue 1nov, for a filter regeneration. This will be completed sometime during the TS week and CMS will ramp up the solenoid when ready. –must wait for end of 25ns ? possible shift of MD ?  LHCb: prefer to put OFF and only turn ON if needed for an MD. –Indeed, needed for 25ns 20deg crossing in IP8 (Tue 1Nov ?).

8h30 meeting26-Oct-2011CERNMassimiliano Ferro-Luzzi 15Luminometers Subject: luminometer requirements during LHC MD Dear Massi, Here follows the list of MDs which require luminosity measurements: - Sunday 23-7: tune working points; - Tuesday 13-21: LR beam-beam with 25 ns beams; - Wednesday 9-19: ATS and tight collimators. Can you please circulate it to the experiments? Thank you very much, Ralph, Frank and Giulia