MREFC Process Mark Coles Deputy Director, Large Facility Projects Office of Budget, Finance, and Award Management NSF June 12, 2006.

Slides:



Advertisements
Similar presentations
Metrolinx is an agency of the Government of Ontario Planning, Design and Engineering (PDE) Workplan February 20, 2009.
Advertisements

Planning and Oversight of NSFs Large Facility Projects Mark Coles Deputy Director for Large Facility Projects Office of Budget, Finance and Award Management.
Grand Challenges Hydrologic Sciences: Closing the water balance Social Sciences: People, institutions, and their water decisions Engineering: Integration.
Roadmap for Sourcing Decision Review Board (DRB)
OFFICE OF SCIENCE 1 Large Synoptic Survey Telescope News since the February update Astronomy & Astrophysics Advisory Committee Telecon May 2012 Fred Borcherding/Nigel.
Briefing to the Commission to Review the Effectiveness of the National Energy Laboratories (CRENEL) Joseph McBrearty, Deputy Director for Field Operations.
1 Performance Assessment An NSF Perspective MJ Suiter Budget, Finance and Awards NSF.
The Federal Budget Outlook and NSF Presented by Beth Blue National Science Foundation Office of Budget, Finance, and Award Management Budget Division/Program.
THE NSF BUDGET Overview of Agency Funding Processes Presented by Beth Blue National Science Foundation Office of Budget, Finance, and Award Management.
Mark Coles Deputy Director, Large Facility Projects Office of Budget, Finance, and Award Management National Science Foundation October 1, 2010.
DOE/NSF U.S. CMS Operations Program Review Closeout Report Fermi National Accelerator Laboratory March 10, 2015 Anadi Canepa, TRIUMF Anna Goussiou, University.
Conversation with ACCORD on GSMT 21 January 2005 Michael S. Turner, Assistant Director Directorate for Mathematical & Physics Sciences National Science.
Project Management Process Project Description Team Mission/ Assignment Major Milestones Boundaries Team Identification Measures of Success Roles & Responsibilities.
Office of Science U.S. Department of Energy U.S. Department of Energy’s Office of Science Dr. Raymond L. Orbach Under Secretary for Science U.S. Department.
Large Facility Projects (LFP) – Guidelines & Procedures Manual Jack Lightbody Interim LFP Deputy, BFA October 10, 2002 Status Report to the NSB.
J. Kotcher P5 Meeting, SLAC, February 21-23, Deep Underground Science & Engineering Laboratory (DUSEL) Jon Kotcher also for Richard Fragaszy (ENG)
Overview of the National Science Foundation (NSF) and the Major Research Instrumentation (MRI) Program Office of Integrative Activities National Science.
Setting Priorities for Large Research Facility Projects – The National Academies Recommendations and the NSB/NSF Report Mark Coles Deputy Director, Large.
Pre-Project Planning Lessons from the Construction Industry Institute Construction Industry Institute Michael Davis, P. Eng, PMP Ontario Power Generation.
3 Dec 2003Market Operations Standing Committee1 Market Rule and Change Management Consultation Process John MacKenzie / Darren Finkbeiner / Ella Kokotsis,
October 22, 2003Advisory Committee for Business and Operations 1 Management of Large Facility Projects Within the NSF Mark Coles Deputy Director for Large.
Atlanta Public Schools Project Management Framework Proposed to the Atlanta Board of Education to Complete AdvancED/SACS “Required Actions” January 24,
1 RHD Cost Sharing Review Update 2011 UBCM Convention Presented by RHD Cost Sharing Review Implementation Group September 26, 2011.
Do it pro bono. Competitor/Collaborator Analysis Service Grant The Strategy Management Practice is presented by Wells Fargo. The design of the Competitor/Collaborator.
Do it pro bono. Strategic Scorecard Service Grant The Strategy Management Practice is presented by Wells Fargo. The design of the Strategic Scorecard Service.
The FY 2009 Budget Thomas N. Cooley, NSF Council of Colleges of Arts and Sciences March 13, 2008.
NCSX Management Overview Hutch Neilson, NCSX Project Manager NCSX Conceptual Design Review Princeton, NJ May 23, 2002.
BROOKHAVEN SCIENCE ASSOCIATES National Synchrotron Light Source II Project Management Jim Yeck Deputy Director (Project Management)
IT PMB: Executive Oversight and Decision Authority for Application and Infrastructure Projects at NASA Larry Sweet Chair, IT PMB JSC CIO August 2010.
1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Marty Fallier Director for Conventional Facilities CD-2 Planning May 8, 2007.
Facilities Subcommittee Meeting of November 2-3, 2005 Characteristics of the Meeting: 4 of the 5 Subcommittee members attended in person; all 5 members.
Mars 2020 Project Matt Wallace Deputy Project Manager August 3, 2015.
Public-Private Education Facilities and Infrastructure Act 2002 (PPEA) Joe Damico.
BROOKHAVEN SCIENCE ASSOCIATES National Synchrotron Light Source II Project Management Jim Yeck NLSL II Deputy Director (Project Management)
OFFICE OF SCIENCE 1 3. Cost Estimate Gines, Fisher 2.Are the estimated cost and proposed schedule ranges realistic, consistent with the technical and budgetary.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Baseline Jim Yeck NSLS-II Deputy Project Director NSLS-II PAC Meeting November 20, 2007.
1 Investing in America’s Future The National Science Foundation Strategic Plan for FY Advisory Committee for Cyberinfrastructure 10/31/06 Craig.
LIGO-G M Advanced LIGO MREFC (Construction) Proposal Submission Gary Sanders Caltech/LIGO November 2001.
Brinkman Report: Setting Priorities for Large Facility Projects Sponsored by the NSF Key Issues Raised in Report Transparency of process (next slide) Involvement.
Introduction & NSF Overview NSF Tribal College Workshop November 14, 2008.
Subcommittee on Design New Strategies for Cost Estimating Research on Cost Estimating and Management NCHRP Project 8-49 Annual Meeting Orlando, Florida.
LIGO-G M Planning and Implementation Strategy for Advanced LIGO Gary Sanders LSC Meeting Hanford, August 14, 2001.
NSF – HSI Workshop 1 Introduction & NSF Overview NSF Workshop for Sponsored Project Administrators at Hispanic Serving Institutions April 13, Miami,
Advocacy: Influencing Facility Development in Public Parks and Recreation Departments Tennis advocacy should occur year round through informal communications.
Status Report on ILC Project in Japan Seiichi SHIMASAKI Director, Office for Particle and Nuclear Research Promotion June 19, 2015.
DOE Stanford Site Office Office of Science U.S. Department of Energy 1 U.S. Department of Energy’s Office of Science Office of Science Review of the LCLS.
SOLUTION What kind of plan do we need? How will we know if the work is on track to be done? How quickly can we get this done? How long will this work take.
Atlantic Innovation Fund Round VIII February 5, 2008.
Mark McKinnon NSF Mid-Project Review May 11-12, Baseline Project Definition Mark McKinnon Project Manager.
1 Investing in America’s Future The National Science Foundation Strategic Plan for FY OPP Advisory Committee 10/26/06.
1 Global Design Effort: Controls & LLRF Controls & LLRF Working Group: Tuesday Session (29 May 07) John Carwardine Kay Rehlich.
1 Community-Based Care Readiness Assessment and Peer Review Overview Department of Children and Families And Florida Mental Health Institute.
Power Upgrade Project SNS September 21-22, TBM Cost Estimate Cost Estimate Schedule Approach Tom Mann October 27, 2005.
Budget Outlook Glen Crawford P5 Meeting Sep
AB 32 Update December 6, Outline Cap and Trade Program 2013 Update to Scoping Plan Looking ahead to
2016 NSF Large Facilities Workshop Matthew J. Hawkins Head, Large Facilities Office May 24-26, 2016 Washington, DC 1.
NSF and the Federal Budget Michael Sieverts Division Director, Budget Division Office of Budget, Finance, and Award Management U.S. National Science Foundation.
Office of Research and Development Photo image area measures 2” H x 6.93” W and can be masked by a collage strip of one, two or three images. The photo.
GAO’s Cost and Schedule Assessment Guides U.S. Government Accountability Office Applied Research and Methods Cost Engineering Sciences Jason T Lee, Assistant.
Office of Critical Decision-1 Approve Alternative Selection & Cost Range or Brief Presented by:
Introduction and NSF Overview. Vannevar Bush And Science: The Endless Frontier.
EIAScreening6(Gajaseni, 2007)1 II. Scoping. EIAScreening6(Gajaseni, 2007)2 Scoping Definition: is a process of interaction between the interested public,
Research & Innovation Preparatory Phase and Early Phase Support under the WP * of Horizon 2020 Harry Tuinder Research Infrastructure Unit DG Research,
Large Synoptic Survey Telescope
Camera PDR/CD1 Planning 19 September 2008
Project Management W. J. Foyt
TechStambha PMP Certification Training
Management Breakout: MREFC Budget Summary Victor L
David Salazar, Chief Facilities Executive
Preliminary Project Execution Plan
Presentation transcript:

MREFC Process Mark Coles Deputy Director, Large Facility Projects Office of Budget, Finance, and Award Management NSF June 12, 2006

2 Topics MREFC process for preconstruction planning and budgeting, prioritization Timeline for planning Budget status and plans Budget issues surrounding the MREFC account

3 New NSF process for pre-construction planning “Guidelines for Planning and Managing the Major Research Equipment and Facilities Construction (MREFC) Account” –Outlines a formal process for planning and developing large facilities that coordinates development of scope, budget, and NSF plans for oversight –On NSF external web site –Attempt to implement the best features of processes used by other agencies and still preserve NSF’s ability to respond flexibly to community needs and initiatives

4 Motivations for MREFC process Lack of a formal process has resulted in NSB approval of some projects whose scope was not well defined, nor fully budgeted –Resulted in descoping, cancellation, and deferral of construction start Brinkman Report: “Setting Priorities for Large Research Facility Projects Supported by the NSF” –Addressed these issues –Cited need for a well-defined, rigorous pre- construction planning process

5 NSF pre-construction planning process Conceptual Design Preliminary Design Final Design Construction Operations R&RA $ MREFC $ DOE Translation: CD 0CD 1CD 2CD 3CD 4 Approve mission need Approve alternate selection and cost range Approve performance baseline Approve construction start Approve operations start

6 Conceptual Design Stage Readiness StageBoard Approved StageConstruction Concept development – Expend approximately 1/3 of total pre-construction planning budget Develop construction budget based on conceptual design Develop budget requirements for advanced planning Estimate ops $ Preliminary design Expend approx 1/3 of total pre- construction planning budget Construction estimate based on prelim design Update ops $ estimate Final design over ~ 2 years Expend approx 1/3 of total pre- construction planning budget Construction-ready budget & contingency estimates Preliminary Design Develop site-specific preliminary design, environmental impacts Develop enabling technology Bottoms-up cost and contingency estimates, updated risk analysis Develop preliminary operations cost estimate Develop Project Management Control System Update of Project Execution Plan Final Design Development of final construction- ready design and Project Execution Plan Industrialize key technologies Refine bottoms-up cost and contingency estimates Finalize Risk Assessment and Mitigation, and Management Plan Complete recruitment of key staff Conceptual design Formulation of science questions Requirements definition, prioritization, and review Identify critical enabling technologies and high risk items Development of conceptual design Top down parametric cost and contingency estimates Formulate initial risk assessment Initial proposal submission to NSF Initial draft of Project Execution Plan Construction per baseline Project evolution Budget evolution Oversight evolution Merit review, apply 1 st and 2 nd ranking criteria MREFC Panel briefings Forward estimates of Preliminary Design costs and schedules Establishment of interim review schedules and competition milestones Forecast international and interagency participation and constraints Initial consideration of NSF risks and opportunities Conceptual design review NSF Director approves Internal Management Plan Formulate/approve Project Development Plan & budget; include in NSF Facilities Plan Preliminary design review and integrated baseline review Evaluate ops $ projections Evaluate forward design costs and schedules Forecast interagency and international decision milestones NSF approves submission to NSB Apply 3 rd ranking criteria NSB prioritization OMB/Congress budget negotiations based on Prelim design budget Semi-annual reassessment of baseline and projected ops budget for projects not started construction Finalization of interagency and international requirements Final design review, fix baseline Congress appropriates MREFC funds & NSB approves obligation Periodic external review during construction Review of project reporting Site visit and assessment MREFC $ Expenditure of budget and contingency per baseline Refine ops budget MREFC Panel recommends and NSF Director approves advance to Readiness NSF approves submission to NSB Congress appropriates funds Funded by R&RA or EHR $ NSF oversight defined in Internal Management Plan, updated by development phase Proponents development strategy defined in Project Development PlanDescribed by Project Execution Plan

7 Conceptual Design Definition of science objectives and quantitative science requirements Notional proposal that NSF can react to and encourage or discourage Conceptual design report System definitions Site independent design Top-down budget and contingency estimates Forecasts for international partnership Operations budget estimates Conceptual design review by NSF NSB approval to enter “Readiness Stage” (preliminary design)

8 Preliminary Design - aka “Readiness Stage” Project baseline defined - detailed design and planning activities that form the basis for a request to Congress for construction funds All significant cost drivers and major risk factors understood Site specific design NEPA/NHPA impacts and mitigations budgeted Partnership intentions firmly stated How NSF will manage the project is described in an Internal Management Plan, approved by NSF Director Preliminary Design and Final Design activities defined by proponents in Project Development Plan – budget, schedule, deliverables Projects failing to progress against objectives of PDP fall out of Readiness Stage Projects emerge following successful Preliminary Design Review by NSF

9 Final Design – aka Board Approved Stage – aka “the Queue” MREFC panel proposes a prioritization to NSF Director Director consults with OMB, and brings a project forward for NSB consideration only if construction appropriation is likely within period budget estimates are valid Director recommends project to NSB with prioritization NSB reviews NSF external review results, PEP and IMP NSB annually reprioritizes approved projects in NSF budget request to Congress Project proceeds with final pre-construction planning activities during period prior to Congressional appropriation and construction start

10 Construction Stage Construction proceeds according to PEP Periodic external review by NSF Construction scope includes commissioning activities Considerable latitude in defining scope of construction activity during pre-construction, but must adhere to that definition during construction period

11 Example timeline Fall 2006 PDR Winter NSF assessment March or May 2007 NSB approval Summer submission of FY09 budget Fall OMB negotiations Feb 2008 submission to Congress Spring 2008 appropriations hearings Oct ’08 (or later) FY09 appropriation NSF approval to obligate MREFC funds Construction begins in FY or 09 Calendar year

12 Readiness Stage – Preliminary Design Entrance and exit from Readiness Stage controlled by MREFC Panel –NSF Deputy Director (chair) + AD’s and Office Heads –Ensures uniformly high standards are applied –Reviews competition for NSF resources and recommends to NSF Director a relative prioritization for projects entering and exiting NSF Director –reviews/approves MREFC Panel recommendations –Approves Internal Management Plan (how NSF will provide oversight, how NSF will fund this activity) –Recommends projects to NSB for construction funding, with priority NSB –Annually reprioritizes the queue of projects awaiting construction funding

13 Projects in construction Atacama Large Millimeter ArrayMPS EarthScopeGEO IceCubeOPP-MPS Scientific Ocean Drilling VesselGEO South Pole Station ModificationOPP

14 Projects approved by NSB for construction but not appropriated by Congress NEON (BIO)- FY07 start request ARRV (GEO)- FY07 ““ OOI (GEO)- FY07 ““ Advanced LIGO (MPS)- FY08 ““ The “Queue”

15 Projects in Readiness Stage Advanced Technology Solar Telescope (MPS) –possible FY09 start –PDR planned for October 2006

16

17 New start profiles are NSF’s best understanding at this point, but could change

18 Possible scenario for ATST – pre-PDR estimates

19 Considerations in starting a new project Some attempt for balance across NSF in range of disciplines supported by MREFC –Competition from Computer Science, Engineering, Earth Science, as well as Physics and Astronomy for future projects. Example projects that may progress to Readiness Stage: GENICISE CLEANERENG EarthScope InSARGEO GEOSGEO Petascale Cyber Infrastructure for GeoscienceGEO ERL Phase II/XFELMPS DUSELMPS EVLA Phase IIMPS LSSTMPS Square Kilometer ArrayMPS Thirty Meter TelescopeMPS

20 Other considerations Desire to close out queue in FY07 budget request – no long-term queue residents –Likelihood of near-term funding will be a consideration in proposing future projects for construction funding “Appetite control” –Enforced by high standards and a rigorous process of pre-construction planning –Competition with base program activities

21 Pre-construction funding Why not an agency-wide account for advanced preconstruction planning and development? –Pre and post construction annual outlays are about equal. NSF capability to support pre-construction and post- construction are linked. Preconstruction planning ranges from 5-25% of total construction cost. Annual operating costs + science utilization are 10-25% of total construction cost. –Avoid “politicizing” the facility selection process Preserve objectivity of selection and prioritization process, based on expert assessment and peer review. Preserve “off-ramps” for projects in advanced planning that should not be built. Size of base program is the limiting factor in new facility construction

22 Backup materials

23