NEDM Construction Project Cost & Schedule Philosophy Vince Cianciolo, ORNL Physics Division Internal Cost & Schedule Review 02/11/2005.

Slides:



Advertisements
Similar presentations
NGAO Construction Project Cost Estimation: Initial Thoughts Richard Dekany NGAO Team Meeting #12 December 13, 2007.
Advertisements

Cost, Schedule & Funding Closeout Jan Joint DOE/NSF CD2/3a Review 1 DOE/NSF Review of the Dark Energy Survey (DES) Project SC 6/7 Cost, Schedule.
Material Management. Materials should be ordered early –Minimize risk of price inflation, lack of materials –Just in time delivery minimizes space required.
LIGO-G M LIGO Laboratory1 Adv. LIGO Installation (INS) Plans, Schedule, Costs, Team Plan, Schedule Costs Team.
Project Management Session 7
Overview of the Schedule and Budget for the ARCS Instrument Doug Abernathy ARCS Hardware Project Manager ARCS Construction Project Review DOE Germantown.
6-1 Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd Pearson, Larson, Gray, Project Management in Practice, 1e CHAPTER 6 Estimating Project,
WBS 1.7: AFE II Project Cost and Schedule Alan Bross DZero Run IIb AFE II Director’s Review April 13, 2005.
Takeyasu Ito University of Tennessee EDM Collaboration meeting December, 2004 Cost and Schedule Estimate WBS 2.5- Neutron beam polarizer/splitter for SNS.
BSBPMG503A Manage Project Time Manage Project Time Unit Guide Diploma of Project Management Qualification Code BSB51507 Unit Code BSBPMG503A.
N A S A G O D D A R D S P A C E F L I G H T C E N T E R I n t e g r a t e d D e s i g n C a p a b i l i t y / I n s t r u m e n t D e s i g n L a b o r.
Quality Management System
Common PDR Problems ACES Presentation T. Gregory Guzik March 6, 2003.
August 2 and 3, 2010 Project Cost, Schedule, Risk and Contingency Jay Elias.
BROOKHAVEN SCIENCE ASSOCIATES National Synchrotron Light Source II Project Management Jim Yeck Deputy Director (Project Management)
1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Martin Fallier Director, Conventional Facilities Conventional Facilities Value and Risk Management May 8, 2008.
Dec 12-14, 2005TBM Planning and Costing Meeting DCLL R&D Evaluations Summary Compiled by Neil Morley for the TBM Planning and Costing Meeting Dec 12-14,
Report from GG5, Dec. 20, 2005 Report from ILC GG 5: Cost and Engineering (Updates since Snowmass) Wilhelm Bialowons, Peter Garbincius and Tetsuo Shidara.
1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Marty Fallier Director for Conventional Facilities CD-2 Planning May 8, 2007.
Welcome to Session 4 – Project Management Process Overview (continued) Instructor:Phyllis Sweeney Instructor: Phyllis Sweeney Project Management Certificate.
Cost Engineering Solutions Ltd 1 C€$ “DETAILED” ESTIMATING Dave Lewis European Aerospace Cost Engineering Working Group 18th April 2002.
David M. Lee Forward Vertex Detector Cost, Schedule, and Management Plan Participating Institutions Organizational plan Cost Basis R&D Costs.
Assigning Resources A schedule is not complete until all the resources necessary to complete the project have been committed or assigned.
BROOKHAVEN SCIENCE ASSOCIATES National Synchrotron Light Source II Project Management Jim Yeck NLSL II Deputy Director (Project Management)
OFFICE OF SCIENCE 1 3. Cost Estimate Gines, Fisher 2.Are the estimated cost and proposed schedule ranges realistic, consistent with the technical and budgetary.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Baseline Jim Yeck NSLS-II Deputy Project Director NSLS-II PAC Meeting November 20, 2007.
Geog 469 GIS Workshop Project Management.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
HLRF DRAFT Global Design Effort 1 Defining EDR* Work Packages [Engineering Design Report] Ray Larsen SLAC ILC Division for HLRF Team DRAFT April.
I n t e g r i t y - S e r v i c e - E x c e l l e n c e Business & Enterprise Systems The Integrated Master Plan (IMP) and the Integrated Master Schedule.
Felix Sanchez Estimating the Budget and Cost (Part 1) Project Management for ARA Engineers and Scientists Developing a Bottoms Up Estimate.
TOF Project Construction Project Plan
Cost Estimate Marion White (Argonne) SCU 3-Lab Review Meeting December 16, 2014.
SC Project Review of NCSX, April 8-10, 2008 Ron Strykowsky - page 1 Office of Science NCSX Project Review of NCSX April 8-10, 2008 Cost and Schedule Ron.
W.J. Foyt LUSI DOE Review July 23, 2007 Project Management 1 Project Management W. J. Foyt Project Scope Timeline Cost Estimate.
Jeff Sestokas Estimating the Budget and Cost (Part 2) Project Management for ARA Engineers and Scientists Developing an Estimate from the Top Down.
1 BROOKHAVEN SCIENCE ASSOCIATES National Synchrotron Light Source II CD-1 Cost Estimate Development Diane Hatton Associate Director for Administration.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
Chapter 14 Pricing and Estimating. Pricing and Estimating Many managers regard pricing as an art ! Many managers regard pricing as an art ! Information.
1 US Cost & Schedule Summary W. R. Edwards US Project Manager CD-2/3a Review January 8, 2008 BNL.
TOF Preliminary Design and Safety Review Project Management Controls R. L. Brown.
Project management Topic 2 Planning.
EDM Collaboration Meeting, October 5-7, 2006 WBS He Services (He3S) “Homework” Steve Williamson.
LIGO-G M LIGO Laboratory1 Adv. LIGO Installation (INS) Plans, Schedule, Costs, Team Plan, Schedule Costs Team.
Brenna Flaugher Sept. 24 th Lehman Review1 Run IIB Silicon Upgrade: Cost and Schedule Lehman Review Sept. 24, 2002 Brenna Flaugher Run IIB Silicon Project.
Mark Reichanadter LCLS October 9-11, 2007 LCLS BCR Overview and EIR LOIs Project Progress / Status Revised Project Baseline.
AGS RSVP Weekly Meeting P. Pile 24 Mar 2005 AGS RSVP Weekly Meeting 24 Mar 2005 Useful Links: RSVP Project : C-AD.
Office of Nuclear Physics Collaboration Meeting 5/19/08 #1 nEDM Reworked Schedule Kim Selvage Project Controls Analyst.
Takeyasu Ito University of Tennessee/Oak Ridge National Laboratory EDM Cost and Schedule Review February, 2005 Beam Splitter / State Selector, Polarizing.
Power Upgrade Project SNS September 21-22, TBM Cost Estimate Cost Estimate Schedule Approach Tom Mann October 27, 2005.
Strykowsky 1Project Review November 2, 2005 NCSX Project Review November 2, 2005 Cost and Schedule Ron Strykowsky.
September 10, FY 2003 Plans Bob Simmons. September 10, Introduction Overview of Project and Engineering Plans Project Plans Engineering Plans.
David M. Lee Forward Vertex Detector Cost, Schedule, and Management Plan Participating Institutions Organizational plan Cost Basis R&D Costs.
EDM Fast Start Presentation WBS 11 – Assembly and Commissioning Vince Cianciolo, Paul Huffman May 23, 2006.
NCSX Strykowsky 1Cost and Schedule Rebaseline April 25, 2005 NCSX Project Re-baseline Review April 25, 2005 Cost and Schedule Ron Strykowsky.
Strykowsky 1Office of Science Review August 15, 2007 Office of Science Project Review NCSX August 15-17, 2007 Cost and Schedule Ron Strykowsky.
Oct 17, 2001SALT PFIS Preliminary Design Review Management, Schedule, & Budget 1 Southern African Large Telescope Prime Focus Imaging Spectrograph Management,
Cost and Schedule Breakout Session Paul Weinman Pacific Northwest National Laboratory.
Attempting to Cost Estimate the nEDM Upper Cryostat Larry Bartoszek, PE Bartoszek Engineering 12/2/04.
LARP Review, June 10, 2013Cost and Schedule Overview – M. Kaducak 1 Cost and Schedule Overview Marc Kaducak LARP Review June 10, 2013.
Software project management 3rd Umer khalid Lecturer University of Lahore Sargodha campus.
Project management. Software project management ■It is the discipline of planning, organizing and managing resources to bring about the successful completion.
Cost and Schedule Paul Weinman Pacific Northwest National Laboratory.
Page Headline Project Management Cost & Schedule Review Rob Michnoff.
Preparations for a Lehman Review
External Independent Review (EIR)
PLANNING & SCHEDULING (First Part)
Project Management Considerations
Conventional Facilities
Presentation transcript:

nEDM Construction Project Cost & Schedule Philosophy Vince Cianciolo, ORNL Physics Division Internal Cost & Schedule Review 02/11/2005

EDM Cost & Schedule Review 02/11/2005 V. Cianciolo, ORNL Physics 2 Outline WBS high level summary Development of cost estimate –Estimate developed for the baseline design discussed by Jan Boissevain –Each project element defined by: Sample WBS dictionary entry Risk-based contingency analysis Sample cost sheet Development of schedule estimate Details on major items to be given by responsible collaborators in following talks

EDM Cost & Schedule Review 02/11/2005 V. Cianciolo, ORNL Physics 3 WBS Overview Over 120 elements in WBS structure Elements organized in 14 major divisions:

EDM Cost & Schedule Review 02/11/2005 V. Cianciolo, ORNL Physics 4 WBS Overview, cont. These were further broken down into major sub-tasks: $FY05

EDM Cost & Schedule Review 02/11/2005 V. Cianciolo, ORNL Physics 5 WBS Overview, cont. $FY05

EDM Cost & Schedule Review 02/11/2005 V. Cianciolo, ORNL Physics 6 WBS Application Generally the cost and schedule estimates were developed one level deeper: –Design item Cost/effort/time required to produce shop drawings. –Procure item Cost/effort/time required to purchase item, including, e.g., development of procurement spec, delivery time. –Install item Cost/effort/time required to integrate them into next larger item, including stand-alone testing and in-field modifications. Each element defined in a WBS dictionary entry –Description –Basis for estimate Cost estimates for each element documented in individual cost sheets –Material, labor, overheads included Required physicist effort estimated, but costs not assigned to project –Risk-based contingency calculation

EDM Cost & Schedule Review 02/11/2005 V. Cianciolo, ORNL Physics 7 Sample WBS Dictionary Entry

EDM Cost & Schedule Review 02/11/2005 V. Cianciolo, ORNL Physics 8 Typical Rate Assumptions LaboratoryUniversity Material13%0% Labor100%50% Engineer$79 Technician (High)$54 Technician (Low)$40 Overhead Rates Hourly Labor Rates

EDM Cost & Schedule Review 02/11/2005 V. Cianciolo, ORNL Physics 9 Sample WBS Cost Sheet

EDM Cost & Schedule Review 02/11/2005 V. Cianciolo, ORNL Physics 10 Contingency Calculation Technical, cost, and schedule risk weights TechnicalCostScheduleRisk weight Material cost OR labor rateSame for all1 Design OR manufacturingMaterial cost AND labor rate2 Design AND manufacturing4 Technical, cost, and schedule risk factors TechnicalCostScheduleRisk factor Existing design and off-the-shelf hardwareOff-the-shelf or catalog item1% Minor modifications to an existing designVendor quote from established drawingsNo schedule impact on any other item2% Extensive modifications to an existing designVendor quote with some design sketches3% New design, nothing exoticIn-house estimate based on previous similar experienceDelays completion of non-critical path subsystem item 4% New design, different from established designs or existing technology In-house estimate for item with minimal experience but related to existing capabilities 6% New design, requires some R&D but does not advance the state-of-the-art In-house estimate for item with minimal experience and minimal in-house capability Delays completion of critical path subsystem item 8% New design, development of new technology which advances state-of-the-art Top-down estimate from analogous programs10% New design, way beyond the current state-of-the-artEngineering judgment15% Each item in the WBS is assigned three risk factors (F) and three risk weights (W). –State of design –Basis of cost estimate –Schedule criticality C = F i W i, where repeated indices imply summation. C = 2x15% + 1x10%+ 1x4% =44%

EDM Cost & Schedule Review 02/11/2005 V. Cianciolo, ORNL Physics 11 Development of Project Schedule Durations estimated for each WBS element –Past experience –Vendor estimates Schedule contingency assigned –For most items the float estimate is given by the duration estimate and the cost contingency estimate. Elements entered into MSProject and linkage analysis performed. Gives a project schedule, including schedule contingency, unconstrained by (unknown) BA profile. Items well off the critical path are then delayed to backload the profile while still completing the project as soon as possible. –Gives proposed BA profile. –Allows escalation calculation (2.5% per year assumed).