Assessment of General Contractor/ Construction Manager Contracting Procedures Preliminary Report Joint Legislative Audit and Review Committee Jill Satran.

Slides:



Advertisements
Similar presentations
CM/CG Contracting Tom Ravn, Mn/DOT Director, Office of Construction and Innovative Contracting.
Advertisements

Organization of Primary Entities
State Ferry Terminals: Procedures to Account for and Request Capital Funds Have Improved, but Additional Actions Are Needed Joint Legislative Audit & Review.
Design/Build Solutions to your construction projects, large and small.
Project Delivery Approaches for Wastewater Utilities in Minnesota June 24, 2008 Metropolitan Council Environment Committee.
Project Delivery Methods. Traditional Owner Design/ Design/Bid/Construction Selection Build Owner’s Vision Owner’s Vision Owner’s Vision Complete Design.
Bodnar/Hopwood AIS 7th Ed1 Chapter 5 u TRANSACTION PROCESSING AND INTERNAL CONTROL PROCESS.
1. A project delivery method describes the process of how a project will be designed and constructed. A project delivery method can be characterized in.
Your Deliver Method... …Pick it Early
Alternative Project Delivery
Review of the Capital Outlay Process and Deferred Maintenance in the Commonwealth Implementation Committee April 18, 2005.
Procurement and Tendering Presentation to [NAME OF CLIENT] [YOUR NAME] [DATE]
JLARC Study of Cost Allocation at Washington State Patrol Preliminary Report Keenan Konopaski, JLARC Staff Presentation to Joint Transportation Committee.
The Outsourcing Process
Alderman Road Residences Phase II Design Build. Extensive master planning preceded this phase 2003 – Dagit Saylor Master Plan Hanbury Evans Update.
Construction What is “construction” defined as or include?  Building?  Altering ?  Repairing?  Demolishing?  Public Improvements?
Basic Health Plan: Part 1 Preliminary Report Joint Legislative Audit and Review Committee Cynthia L. Forland Lisa Jeremiah November 30, 2005.
Large Public Works Projects and the General Contractor/ Construction Manager (GC/CM) Procedure: A New Way to Save Money, Time and Aggravation.
Elements of Internal Controls Preventing Fraud, Waste, and Abuse in Urban and Rural Transit Systems.
K-12 Data Study Proposed Final Report Joint Legislative Audit & Review Committee February 21, 2007 Nina Oman John Bowden.
Policy 7003 Review BCPS Facilities Task Force – Policy Subcommittee Report July 16, 2015.
Public Works Contracting Marsha Reilly Office of Program Research House of Representatives recommended.
This Presentation is a Copyrighted Property of Waller S. Poage, AIA, CSI, MAI, CVS – All Rights are Reserved Session CDT 01 – Fundamentals Lesson CDT 1.3.
9 Closing the Project Teaching Strategies
CEO REPORT Thomas F. Schrader ERCOT Board of Directors December 14, 2004.
Review of Accountability Entities Overseeing WSDOT Preliminary Report Keenan Konopaski, JLARC Analyst June 29, 2005.
Joint Task Force on Local Effort Assistance September 25, 2002 Bill Freund, Consultant To The Task Force.
Procurement and Construction Management and Oversight What Board Members Need to Know Jerry Smiley, AICP 24 July 2013.
Performance Audit of Capital Budget Processes Proposed Final Report February 8, 2005 Joint Legislative Audit and Review Committee Karen Barrett & Isabel.
The State of Pre-K: Realities and Opportunities in Texas Mandi Kimball, Director of Public Policy and Government Affairs.
Voluntary Disclosure Systems  State and City Voluntary Disclosure Procedures Should be Uniform  Procedures, Requirements, and Allowances Should be Codified.
Project Delivery Options in the California Construction Market CSI Fresno Chapter - February 16, 2010 PROJECT DELIVERY OPTIONS in the CALIFORNIA CONSTRUCTION.
K-12 School Spending and Performance Review Preliminary Report Joint Legislative Audit & Review Committee September 14, 2005 Stephanie Hoffman and Lisa.
Higher Education Capital Facilities Studies: Expanding The Comparable Framework Preliminary Report Joint Legislative Audit & Review Committee May 18, 2005.
O F F I C E O F T H E Auditor General of British Columbia 1 OAG Review of the Performance Agreements between MoHS and Health Authorities.
K-12 Pupil Transportation Funding Study Proposed Final Report Fara Daun & Stephanie Hoffman Joint Legislative Audit & Review Committee November 29, 2006.
National Petroleum Council Study Balancing Natural Gas Policy: Fueling the Demands of a Growing Economy September 2003.
Life Cycle Cost Model Update Preliminary Report Joint Legislative Audit & Review Committee January 4, 2007 Stephanie Hoffman and Keenan Konopaski.
January 24, …a delivery method which entails a commitment by the Construction Manager to deliver the project within a Guaranteed Maximum Price (GMP).
Consultants' Competitive Negotiation Act Acquisition of professional architectural, engineering, landscape architectural, or surveying and mapping.
Best Value Public Works Procurement September 7, 2007.
January 31, …a delivery method in which the construction team is known as the design-builder…and is responsible for taking a concept developed by.
CE 366 PROJECT MANAGEMENT AND ECONOMICS Robert G. Batson, Ph.D., P.E. Professor of Construction Engineering The University of Alabama
The Wisconsin Green Tier Program: Developing An Evaluation Tool Analysis by: Darryn Beckstrom, Jessalyn Frost, Erin Rushmer, and Melody Sakazaki.
DGS Recommendations to the Governor’s Task Force on Contracting & Procurement Review Report Overview August 12, 2002.
Can Decentralization Work for Forests and the Poor? Australian Centre for International Agricultural Research (ACIAR) Center for International Forestry.
Alternate Procurement & Funding in Washington State Erin L. Anderson Stoel Rives LLP February 12, 2008.
Preliminary Report Joint Legislative Audit and Review Committee Cynthia L. Forland September 14, 2005 At-Risk Youth Study.
Business Inclusion and Development Program Overview Business Development and Procurement Services Budget, Finance and Audit Committee Monday October 5,
1 American Recovery and Reinvestment Act of 2009: Challenges Facing the Department of Transportation and the Office of Inspector General’s Strategy for.
Evaluation of Budget Process for Information Technology Projects Proposed Final Report February 16, 2006 Joint Legislative Audit & Review Committee Karen.
LACCD Building the Future THOMAS HALL Director Facilities Planning and Development.
Alternate Project Delivery Systems for Governments.
Investing in the Environment1 Investing in the Environment 2001 Performance Audit 3rd Follow-Up Report June 16, 2004 Eric Thomas Joint Legislative Audit.
Capital Facilities Program Update San Rafael City Schools 10 May 2016.
CONSTRUCTION MANAGEMENT AT RISK Prepared by: Nancy Fouad Carey Attorney AGC Alabama Birmingham Section Meeting November 5, 2012.
CPARB GA Issues John Lynch Department of General Administration Engineering & Architectural Services.
PWGSC - KOREA 2nd JCC Meeting Canadian Federal Real Property Construction Contracting Presentation by Bruce Fletcher Director General – CASMS - PWGSC November.
Field Analyst Support Team (FAST) School Finance Division
2016 SAME Small Business Conference - Atlanta
What Small and Emerging Contractors Need to Know Introduction to Project Delivery Methods © Copyright 2017 NASBP.
Lease-Leaseback Project Delivery Method
Contractor Review and Prequalification
Investment Outsourcing
CM at Risk v. Design-Bid-Build
12.2 Conduct Procurements The process of obtaining seller responses, selecting a seller and awarding the contract The team applies selection criteria.
Project Delivery Systems
Engineering Project Tendering.
Performance Playbook for GPO Value
PROJECT DELIVERY METHODS
Presentation transcript:

Assessment of General Contractor/ Construction Manager Contracting Procedures Preliminary Report Joint Legislative Audit and Review Committee Jill Satran and Isabel Muñoz-Colón May 18, 2005

1 Presentation Overview  Background on GC/CM in Washington State  Design-Bid-Build (DBB) vs. GC/CM Contracting Method  Study Overview  Capital Projects Review Board  Conclusions and Recommendations

2 Background on GC/CM in Washington State  Legislature granted GC/CM authority in 1991  The authorization will expire in 2007  Statutory requirements to use GC/CM –Over $10 million AND Complex scheduling, OR Existing facility has to remain open, OR Early GC/CM involvement is critical to project success  Capital Budget instructs JLARC to review GC/CM in major public works projects. Report Pgs. 1-2, 11

Design-Bid-Build GC/CM PREDESIGNDESIGNCONSTRUCTION Contractor Hired (low bid) Architect Hired Guaranteed Maximum Price (GMP) negotiated Contractor Hired Architect Hired 3 Report Pgs. 6-7

4 Study Overview  How does industry research compare GC/CM to Design-Bid-Build (DBB)?  Who is using GC/CM and on what types of projects?  Where are GC/CM projects located?  Who is awarded GC/CM contracts?  Are performance indicators and benchmarks available to compare DBB and GC/CM?  What is Washington State’s experience with GC/CM?

How Does Industry Research Compare Design-Bid-Build to GC/CM? 5 Traditional Design-Bid-Build Alternative GC/CM Project Complexity Low-moderateHigh Schedule Best suited if reasonable, not a critical factor Best suited if aggressive, fast- tracking possible Compensation Fixed price, low bid contracting Negotiated maximum guaranteed price Risk Primarily ownerSome shared risk Experience Required Moderate High degree of experience required of all participants Team Relationship AdversarialCollaborative Project Cost Lower design and management costs, potential for significant change orders Higher design and management potential for reduced change orders Project Quality Standard quality expectedHigh quality expected Pg. 9

6 Who is using GC/CM? Higher Education State Agencies K-12 Cities Counties Ports Hospital Districts Public Facilities Districts Other Owner Type Project Count $2.7 Billion spent on GC/CM State-level projects $3.8 Billion spent on GC/CM local-level projects Pg. 15

7 …and on what kind of projects? Non-education related projects Education related projects Report Pg. 18

Where Are GC/CM Projects Located? King Snohomish Pierce Report Pg. 168

Who is awarded GC/CM contracts? TBD 6 projects 9 Report Pg. 17

10 Are performance indicators and benchmarks available to compare?  The state does not currently collect consistent reliable state and local-level data to analyze project performance –Cost-per-square-foot –Cost Growth –Time Growth –Quality –Change Orders  To address the lack of data, JLARC: –Compiled an inventory of GC/CM projects –Conducted a survey of those projects –Developed 21 case studies of DBB and GC/CM Report Pgs

What is Washington’s Experience with GC/CM? 11Report Pg. 19 Alternative GC/CM Washington Project Complexity High Partially Present Schedule Best suited if aggressive, fast-tracking possible Present CompensationNegotiated guaranteed maximum pricePresent RiskSome shared riskInconclusive Experience Required High degree of experience required of all participants Partially Present Team Relationship Collaborative Present Project Cost Higher design and management, potential for reduced change orders Inconclusive Project QualityHigher quality design and facilityInconclusive

12 Characteristics Present in Washington  Schedule –GC/CM projects appear to adhere closer to projected schedule than DBB projects.  Negotiated Compensation –Agencies appear to be successfully negotiating their guaranteed contract cost and staying close to their original budget.  Collaborative Team Relationship –GC/CM provides a more collaborative approach in most cases. Report Pgs , 26-27

13 Partially Present in Washington  Project Complexity –Generally agencies are using GC/CM on complex projects. –However, there is some evidence that agencies may be using GC/CM primarily to avoid problems associated with DBB.  Experienced and Involved Owner –Most agencies are investing additional resources in managing GC/CM. –We found a few instances where agencies lacked experience or involvement on the owner’s part. Report Pgs , 25-26

14 Inconclusive – Insufficient Data  Shared Risk –Some owners may believe more risk is being shifted to GC/CM than is occurring.  Project Cost –GC/CM increases preconstruction and, in some cases, management costs. –Impact on change orders, claims and litigation is inconclusive.  Project Quality –It is unclear whether GC/CM contracting methods produce better quality designs or facilities. Report Pgs , 28-30

15 Capital Projects Review Board  Legislature created CPRB in 2005 to develop and recommend: –Criteria to determine effective and feasible use of alternative contracting methods; –Qualification standards for general contractors bidding on alternative public works projects; and –Policies to further enhance the quality, efficiency, and accountability of capital construction projects.  JLARC developed analytical tools that could be used by the Board Report Pgs

16 Conclusions and Recommendation: 1 Conclusion –Some agencies may be using GC/CM to overcome perceived deficiencies in the low-bid process in DBB. Recommendation –The Legislature should further analyze the implications of the low-bid requirement on major capital projects. Report Pg. 35

17 Conclusions and Recommendation: 2 Conclusion –Executive-level oversight is critical to the ongoing development of sound public works contracting policy. Recommendation 2A: The CPRB should be convened quickly to ensure the Board is prepared to provide recommendations to the Legislature before the 2007 termination date of GC/CM. 2B: The CPRB should consider adding to its work plan improving the consistency of GC/CM project documents across projects and jurisdictions. Report Pgs

18 Conclusions and Recommendation: 3 Conclusion –Lack of sound, reliable, and consistent data collection is a major impediment to understanding the impacts of GC/CM. Recommendation 3A: The CPRB should develop standardized statewide performance indicators and benchmarks for all major public works projects. 3B: Project performance data should be collected on state and local projects to form a portfolio of projects. Report Pgs