NRG Comments/Concerns with HIP Assumptions January 21, 2014 RPG Meeting NRG Comments/Concerns with HIP Assumptions - January 21, 2014.

Slides:



Advertisements
Similar presentations
Houston Region Import Capacity Project Planning for Reliable Power.
Advertisements

October 16, 2009 RPG Meeting ERCOT RPG Project Review Update Jeff Billo.
2004 Congestion Costs. 2 Transmission Congestion Occurs when analysis shows a given outage of a transmission element (contingency) will result in the.
2015 RTP Update January, 2015.
Houston Region Import Capacity Project August 27, 2013 Regional Planning Group Meeting.
System Strength Discussion
Temperature Dependant Discount Factor ROS August 16, 2007.
ERCOT PUBLIC 10/21/ LTSA Update October 21, 2014.
ERCOT PUBLIC 8/19/ LTSA Scenario Results Updates August, 2014.
2011 Long-Term Load Forecast Review ERCOT Calvin Opheim June 17, 2011.
The Status Of The Electric Grid In ERCOT The Electric Reliability Council Of Texas Sam R. Jones, P.E. ERCOT – Retired As a retiree of ERCOT this presentation.
ERCOT PUBLIC 4/22/2014 Updates for 2014 LTSA Scenario and Data Assumptions 4/22/2014.
PLWG Report to ROS July 9, PGRRs needing vote PGRR043 – FIS Scoping Amendment – PGRR043 moves the Subsynchronous Resonance (SSR) Study out of the.
Farmers Rural Electric Cooperative Corporation 2006 Load Forecast Prepared by: East Kentucky Power Cooperative, Inc. Forecasting and Market Analysis Department.
Long Term Study Scenarios and Generation Expansion Update December 7, 2012.
Warren Lasher Director, System Planning October 4, 2014 Our Energy Future.
July 13, 2012 Transmission Needs Analysis Scenario 1 Update: BAU All Technologies.
Long Term Study Task Force Update Transmission Study Practices and Methodologies April 5th,2011 LTS.
Base Case Draft – For Comment Rocky Mountain States Sub-Regional Transmission Study December 9, 2003.
10/03/ Report on Existing and Potential Electric System Constraints and Needs Within the ERCOT Region October 3, 2002.
Lyndonville Electric Department Feasibility Analysis Review December 2,
Jenell Katheiser Doug Murray Long Term Study Scenarios and Generation Expansion Update January 22, 2013.
Grayson Rural Electric Cooperative Corporation 2006 Load Forecast Prepared by: East Kentucky Power Cooperative, Inc. Forecasting and Market Analysis Department.
Texas Wind Energy American Meteorological Society Summer Community Meeting – Norman Oklahoma Henry Durrwachter, P.E. August 12, 2009.
LAREDO PLANT RMR EXIT STRATEGY Presentation to Board of Directors March 16, 2004 Transmission Services Operations.
March 11, 2011 RPG Meeting Lower Rio Grande Valley (LRGV) Import.
Avalon Park Retail Market Analysis Fishkind and Associates, Inc Corporate Blvd. Orlando, FL December 12, 2008.
ERCOT PUBLIC 5/20/ RTP Inputs and Assumptions-Updated April 22, 2014.
John Dumas Director of Wholesale Market Operations Jeff Billo Manager of Mid Term Planning Dan Jones Director with Potomac Economics, the ERCOT IMM Board.
K E M A T & D C O N S U L T I N G Power System Conference, Clemson, South Carolina, March 8-11, 2005 Principles and Issues Relating to the Interconnection.
ERCOT PUBLIC 5/20/ RTP Inputs and Assumptions May 20, 2014.
June 19, 2009 RPG Meeting ERCOT System Development Update Jeff Billo.
Proposed North – South Congestion Mitigation Plan Luminant Energy July 2008.
ERCOT PUBLIC 4/22/ RTP Inputs and Assumptions April 22, 2014.
Economic Planning Criteria Question 2 1/7/2011 Joint CMWG/PLWG Meeting March 4, 2011.
December 7, 2012 Transmission Needs Analysis Scenario 5/7 Update.
PRR 547 – Trading Hubs CMWG Presentation to WMS October 21, 2004.
Wholesale Market Subcommittee Texas Interconnection Long-Term Study Update Warren P. Lasher April 8, 2011.
Electric Reliability Council of Texas (ERCOT) A Success Story… In Progress Ingmar Sterzing United States Association of Energy Economics (USAEE) Pittsburgh.
2008 Annual Five Year Plan Update 2 10/12/2007 Regional Planning: Jay Teixeira, Harry Liu, Brad Schwarz, Jeff Billo, Chris Ngai.
Blue Grass Energy Cooperative Corporation 2006 Load Forecast Prepared by: East Kentucky Power Cooperative, Inc. Forecasting and Market Analysis Department.
Licking Valley Rural Electric Cooperative Corporation 2006 Load Forecast Prepared by : East Kentucky Power Cooperative, Inc. Forecasting and Market Analysis.
JACKSBORO TO WEST DENTON and WEST LEVEE TO NORWOOD 345-kV PROJECTS April 20, 2004 Transmission Services Operations.
May 11, 2012 RPG meeting YTP Scope and Process – RPG Comments.
TAC02/01/2007 DW 1 TAC Briefing on: - Report on Constraints and Needs: Five Year Plan Development - Long Term System Assessment (LTSA) - Entergy Integration.
Environmental Benefits of Renewable Portfolio Standards in an Age of Coal Plant Retirements September 10 th, 2015 Energy Policy Research Conference Denver,
2003 State of the Market Report ERCOT Wholesale Electricity Markets.
TRANSMISSION CONSTRAINTS KENNETH A. DONOHOO, P.E. Manager of System Planning, Technical Operations
Impacts of Environmental Regulations in the ERCOT Region Dana Lazarus Planning Analyst, ERCOT January 26, 2016.
RPG: September 24, Long-Term System Assessment Introduction Jeff Billo, Manager, Transmission Planning September 2013 Regional Planning Group.
3/28/2008 RPG CREZ Meeting CREZ Transmission Optimization (CTO) Study And The Oscar Goes To… Warren Lasher Manager, System Assessment.
September 1, 2011 TAC Lower Rio Grande Valley Regional Planning Group Project Jeff Billo Manager, Mid-Term Planning.
Panhandle Renewable Energy Zone (PREZ) Study
May14, 2010 RPG Meeting Houston Import Study Update Jeff Billo.
2006 Report on the Capacity, Demand, & Resources for the ERCOT Region Technical Advisory Committee June 1, 2006 Kenneth A. Donohoo. P.E. Manager, Transmission.
SERC Reliability Corporation 1 SERC RELIABILITY CORPORATION MID-AMERICA RELIABILITY CONFERENCE June 21, 2006 COLUMBUS, OHIO.
2004 CSCs & Zones. Goals for 2004 Increase ERCOT market efficiency Reduce out-of-merit energy and capacity deployments Reduce uplift of local congestion.
June 11, 2010 RPG Meeting Houston Import Study Update Jeff Billo.
03/06/2008 TAC CREZ Transmission Optimization (CTO) Study Update Dan Woodfin Director, System Planning.
2016 LTSA Update Doug Murray 6/21/2016. Agenda Introduction Scenario Retirement Process Scenario Summary Results Appendix.
Impact of not including proposed generators lacking RARF data in the planning models Planning Guide Section 6.9 Issues February 17, 2016.
Houston Import Project – ERCOT Independent Review
RPG - 10/12/2007 Competitive Renewable Energy Zones (CREZ) Update Bill Bojorquez Vice President, System Planning.
LTSA Scenario Development Workshop
2018 LTSA Workshop August 2017 RPG Meeting Welcome to.
ERCOT 2011 Five-Year Transmission Plan Update
NRG Comments/Concerns with Houston Import Project Assumptions
Warren Lasher Manager, Long-Term Planning and Policy
RE Grid Integration Study with India
New England Electricity Restructuring Roundtable September 18, 2009
Presentation transcript:

NRG Comments/Concerns with HIP Assumptions January 21, 2014 RPG Meeting NRG Comments/Concerns with HIP Assumptions - January 21, 2014

1 The Coastal region load (and Houston particularly) is likely to continue growing in the foreseeable future. Like the Coastal region, there are other regions in the state that are also expected to see continued load growth thanks to Texas’ growing economy (west Texas, D/FW metroplex, regions in the south and central portions of the state such as Corpus Christi, Austin/San Antonio corridor, and the Rio Grand valley.) There is not enough generation to meet the Planning load in A planning assumption of reduced load in one area of the state is electrically equivalent to adding that same amount of generation in that one area. The assumptions used in any planning scenario are the key drivers for the results. Baseline – Planning Assumptions We Should all Agree On

2 Assumptions Used in ERCOT’s HIP Analysis Appear to be Pushing Towards a Particular Result SE Case Peak Planning Peak SE/PlanningPlanning - SE COAST 26, % - EAST 3, % - FAR_WEST 2,775 3,17687% 401 NORTH 1,473 1,74784% 274 NORTH_CE 21,924 29,51274% 7,587 SOUTH_CE 14, % - SOUTHERN 7, % - WEST 1,897 2,23085% 333 Total Load 79,016 87,611 Note: Planning Peak is the higher of SSWG load or the 90/10 load. Table 1: Load Reduction Assumptions Utilized in HIP Analysis

3 The data in the previous slide shows that ERCOT reduced the load by greater than 8,000 MWs in the North Central, North, West and Far West weather zones, while holding the Coastal, East, South Central and South weather zones at the planning case levels. Electrically, this added 7,587 MWs of generation in the North Central load zone (a 26% reduction in load), primarily in the D/FW metroplex. Electrically equivalent to adding X amount of “zero-cost, must run” generation at each load bus where load was reduced. The size of the generation is a percentage of the peak load at the bus. The percentage was determined by how much is needed to have a “solvable” case. Note: In addition to reducing load in the North Central, North, West and Far West weather zones, the HIP analysis included mothballed generation outside the Houston region, but excluded mothballed generation inside the Houston/coastal region. This is equivalent to adding 1,273 MWs in the North and removing 206 MWs of generation from Houston and the South. What do these Assumptions Mean?

4 Load Assumptions Ensure Large Quantities of Transmission are Needed to Serve Houston Reduced load 274 MW Reduced load 7,587 MW - electrically equivalent to adding a 7,587 MW unit, mainly in DFW. Also added an additional 1,273 MWs of mothballed gen. Reduced load 333 MW Reduced load 401 MW =2018 Planning peak load Undoubtedly, these types of assumptions would lead to a conclusion that major transmission infrastructure is needed into Houston from the North.

5 The Assumptions Are Not Supportable For any type of HIP transmission expansion to work there has to be something to import! Is it proper to assume that generation is never added in the coastal region or the south, but approximately 10 GW is added in the North, mostly in DFW? [Load reduction plus mothballed units] Would an assumption of “any” level of generation (or load reduction) in the southern and coastal region significantly change the HIP results? The HIP assumption that load is growing in Houston and nowhere else is not supported by other Planning data. For example, ERCOT’s December 2013 Report on Existing and Potential Electric System Constraints and Needs discusses in detail the large load growth expected to continue in far west Texas and in the Denton/DFW area. North Central load in the HIP (SE) case is lower than the actual peak in A review of other data elements provided by ERCOT’s Planning Group indicates modifications to the assumptions should be made that are better supported by the data.

6 If Load Reduction is Required for Planning, What is the Proper Criteria? At 10/22/13 RPG meeting, ERCOT stated that “Decreasing the loads in North, North Central, West and Far West Weather zones is reasonable because they are geographically & electrically far from the Coast Weather zone, and historical data … indicates the loads in the weather zones do not experience peaks load at the same time as the Coast weather zone. Questions: Should peak loads in other regions be based on “average” coincident peaks? A closer review shows maximum coincident peaks are closely aligned. Isn’t the HIP analysis supposed to be a “peak” case? How can an assumption of a 26% reduction of load in the North Central weather zone be justified based on the above numbers? Table 2: ERCOT Data from October 22, 2013 RPG

7 ERCOT’s SGIA Data Doesn’t Support the Load Reduction Assumptions Source: ERCOT System Planning Monthly Status Report – December, 2013, Renewables Removed. Total by RegionMW% Coastal West North North Central Far West Total Table 3 Table 4: IAs by Region Generation Interconnection Agreements as of December 31, 2013 INRSite NameCountyCODFuelMW For Grid Change from Last Report Zone 14INR0016 Channel Energy Center 138/345kV CT Harris14-JunGas190 Coastal 14INR0015Deer Park Energy CenterHarris14-JulGas190 MW for Grid Coastal 13INR0021 Ferguson Replacement Project Llano14-JulGas570 West 13INR0040Rentech ProjectHarris14-AugGas15 Coastal 10INR0021Panda Sherman PowerGrayson14-AugGas720 North 10INR0020aPanda Temple PowerBell14-AugGas717 North Central 10INR0020bPanda Temple PowerBell15-AugGas717 North Central 13INR0049 Friendswood Energy Generation Harris15-SepGas316 Coastal 13INR0023 Texas Clean Energy Project Ector16-JanCoal240 Far West 13INR0028Antelope StationHale16-JunGas359 North 06INR0006Cobisa-GreenvilleHunt16-DecGas1792 Projected COD North Central 10INR0022 Pondera King Power Project Harris16-DecGas1629 MW for Grid,Proj. COD Coastal

8 Source: ERCOT System Planning Monthly Status Report – December, 2013, Renewables Removed. ERCOT’s Full Interconnect Study Data Doesn’t Support the Load Reduction Assumptions Table Generation Projects Undergoing Full Interconnection Studies Interconnection Database Reference Number CountyFuel Capacity to Grid (MW) Commercial Operation (from resource developer) Zone 14INR0069MilamCoal3014-MarSouth Central 14INR0040HidalgoGas22514-JunSouth 14INR0059KaufmanGas5214-AugNorth Central 14INR0066LamarGas13014-NovNorth 13INR0054BeeGas2514-DecSouth 14INR0039EctorGas45015-MarFar West 14INR0038GalvestonGas39015-AprCoastal 15INR0053WinklerGas12315-MayFar West 15INR0054ReevesGas12315-MayFar West 15INR0055AustinGas14215-MaySouth Central 15INR0027HidalgoGas7915-JunSouth 15INR0028FreestoneGas16015-JunEast 15INR0042HoodGas46015-JunNorth Central

9 Source: ERCOT System Planning Monthly Status Report – December, 2013, Renewables Removed. ERCOT’s Full Interconnect Study Data Doesn’t Support the Load Reduction Assumptions, Cont. Table 6 Table 7: Total FIS’s by Region 1.1 Generation Projects Undergoing Full Interconnection Studies Interconnection Database Reference Number CountyFuel Capacity to Grid (MW) Commercial Operation (from resource developer) Zone 15INR0023WhartonGas70015-JunCoastal 16INR0010MitchellGas79916-FebWest 16INR0009CalhounGas51016-AprCoastal 16INR0006AngelinaGas78516-JunEast 16INR0003BrazoriaGas1116-JunCoastal 16INR0004CameronGas73016-JunSouth 16INR0005CameronGas87116-JunSouth 16INR0007HidalgoGas9516-JunSouth 17INR0004HaleGas20216-JunNorth 15INR0032HaleGas19716-JulNorth 15INR0033HaleGas19716-JulNorth 16INR0013NacogdochesGas21516-JulEast 17INR0002HendersonGas48917-JunNorth Central 17INR0003JacksonGas96517-JunCoastal 17INR0007WhartonGas JulCoastal 11INR0040FreestoneGas64018-MarEast Total by Region MW% C + S + SC + E W + N + NC + FW Coastal West North North Central Far West South South Central East Total ,7503,222

10 If There Isn’t Enough Generation, Aren’t These Load Reductions More Supportable Based on FIS Data (Table 7)? Reduce 6.6% Reduce 9.1% Reduced 7.3% Reduce 6.3% = Reduce 16.4% Reduce 34.2% Reduce 1.6% Reduce 18.5%

11 If FIS Data Isn’t Considered, Then Shouldn’t Load Reductions be Closer Aligned with Actual SGIA Data (Table 4)? Reduce 14.5% Reduce 43.3% Reduced 7.6% Reduce 3.2% = Reduce 9.1% Reduce 31.4% No Change

12 ERCOT’s December 17, 2013 Update on the HIP Project to the RPG included an evaluation of the impact of retirement of older than 50 year old generation “inside Houston area”. 11 units (total 1939 MW) are more than 50 year old by 2018 Sam Bertron G1, G2, G3, G4 and GT2; T.H. Warton GT1; W.A. Parish G1, G2, G3, G4, and GT1 However, if the HIP projects are dependent on imports from the north, why ignore units that will be greater than 50 years old in the North zone? The North zone contains 17 units more than 50 years old by 2018 for a total of 2,857 MW. Handley 3, Mountain Creek 6, Mountain Creek 7, Mountain Creek 8, Powerlane Plant 2, Ray Olinger 1, Spencer 4, Stryker Creek 1, Stryker Creek 2, Atkins G3, Atkins G4, Atkins G5, North Texas 1, North Texas 2, North Texas 3, Valley Unit 1, Valley Unit 2. What is basis for assumption that only >50 year old units in the Houston area will retire and others outside of Houston won’t? Other Questionable Assumptions

13 The load reduction (generation addition) assumptions used to make the HIP analysis “solvable” are questionable, not supported by other available data, and can only lead to one conclusion – build major transmission infrastructure from the North into the Houston area. Approximately 10,000 MWs of new, low cost generation added in the North, primarily in the DFW metroplex. No generation added in the Coastal weather zone or in the South. Older units retire only in the Houston area, nowhere else. Mothballed generation is only available if it’s outside of Houston. Building a major transmission corridor with nothing to import could lead to stranded, costly transmission investments placed on the backs of consumers. NRG believes that more supportable assumptions would significantly alter the HIP results and likely result in a more cost-effective utilization of consumer dollars. Conclusions