Lawrence Livermore National Laboratory This work performed under the auspices of the U.S. Department of Energy by Lawrence Livermore National Laboratory.

Slides:



Advertisements
Similar presentations
Jose Chan FAC- Undulator System Installation & Assembly 10/30/07 1 Undulator System Installation & Assembly Schedule Jose.
Advertisements

Kathleen Ratcliffe BC2/Linac Installation April 16, BC2 / Linac Installation Coordination Kathleen.
Richard M. Boyce FAC Review – Accelerator Installation October 29-31, Installation – Accelerator Systems Installation Planning.
Hal Tompkins FEE/FEL June 16, FEE/FEL Commissioning Overview By Hal Tompkins Photon Beam Systems Deputy.
FAC, 4/20/06 D. Schultz 1 e-Beams System Update Linac System Preparing for downtime installation. Injector System Installation has started. Undulator System.
1 John Arthur 1 FEH Status CXI Review June 3, 2009 FEH Layout, Status John Arthur – LCLS Expt’l Facilities Div June 3, 2009.
James Welch October 30, FEL Commissioning Plans J. Welch, et. al. FEL Commissioning Plans J. Welch, et. al. Accelerator.
Javier A. Sevilla Interface & Configuration FAC Review April 16, Interface and Configuration Management Outline CF.
Jose Chan and Kathleen Ratcliffe FAC Review- LTU/DUMP installation Status & 6/16/08 1 Linac Installation Status, Schedule.
John N. Galayda LCLS Facility Advisory November 11, LCLS Update November 11, 2008 Construction Status LCLS Instruments.
Kathleen Ratcliffe LTU Installation October 30, LTU Installation Coordination Kathleen Ratcliffe.
John Arthur X-ray November 11, 2008 SLAC National Accelerator Laboratory 1 X-ray Overview LCLS Directorate structure.
Richard M. Bionta XTOD October 12, 2004 UCRL-PRES-XXXXX X Ray Transport, Optics, and Diagnostics, Overview Facility Advisory Committee.
LCLS Transition to Science DOE Status Review of the LUSI MIE Project The Instrument Readiness Review Process John Arthur LCLS Experimental Facilities Division.
Richard M. Boyce FAC April 16, LCLS Installation & Planning Integration process – IMT 2007 Installation Planning BTH.
John Arthur X-ray June 17, X-ray Overview XTOD current status XES current status Schedule to first experiments.
1 Stefan Moeller 1 AMO Instrument Schedule ARR AMO Instrument Schedule Stefan Moeller – XES Manager June 30, 2009.
Donn H. McMahon XTOD Breakout: XTOD FY07 October 12, 2006 UCRL-PRES XTOD FY07 Plan LCLS FAC Review October 12, 2006.
John Arthur Photon Systems April 16, LCLS Photon Systems Status Technical status and accomplishments Response to.
John Arthur Photon October 18, 2005 LCLS Photon Systems Status John Arthur SLAC.
John Arthur Photon October 29, Photon Systems Update FAC recommendations Current status New plan for Photon Systems.
Stewart Shen October 27, LCLS-XTOD Gas Attenuator LCLS FAC Meeting October 27, 2005 Stewart Shen, Keith Kishiyama and Marty Roeben.
John Arthur Photon October 27, Photon Systems Overview John Arthur SLAC.
Richard M. Boyce FAC October 29-31, Installation Planning Integration process – IMT update Installation Planning &
John Arthur X-Ray Optics October 12, 2004 X-Ray Prototype Optics Specifications John Arthur.
John N. Galayda LCLS FAC October Linac Coherent Light Source Overview and Charge Facility Advisory Committee.
D. Schultz FAC 6/17/08 1 e-Beams Systems Update People Progress the last review LTU and Dump Installation Status Undulator.
John Arthur Photon April 20, 2006 Photon Systems Update John Arthur SLAC Photon Systems Manager.
Richard M. Bionta X-Ray Transport, Diagnostic, & Commissioning September 22, 2004 UCRL-PRES Two Problems... LCLS Diagnostics.
Bob Law FAC Oct 24, Sector 20 Project Overview Sector 20 Site Plan Description Organizational Chart Schedule Cost.
Hamid Shoaee LCLS FAC Controls June 17, LCLS Control System Personnel Linac & BC2 Controls progress LTU, Dump Controls.
Steve Lewis XTOD 4-8 April, 2005 UCRL-PRES LCLS Week 4-8 April, 2005 Steve Lewis X-ray Transport, Optics, and Diagnostics:
John Arthur Photon October 12, Photon Systems Update John Arthur SLAC 1.
Hal Tompkins Photon October 30, LCLS Photon Systems Installation and Commissioning Presentation to Facility Advisory.
Geoff Pile LCLS Und. System Fabrication FAC 29 th, 30 th & 31 st October 2007 LCLS Undulator System Fabrication Schedule FAC.
John Arthur Photon Systems April 7, 2005 Photon Systems Overview John Arthur.
C.E. Rago Inj/Lin Design & 4_20_06 1 Injector / Linac Design & Fabrication C.E. Rago FAC Review 04_20_06.
Arturo Alarcon Undulator Controls Module Status 11/12/2008 SLAC National Accelerator Laboratory 1 Undulator Controls Module Status.
Hamid Shoaee Accelerator Readiness Dec. 2, ‘08 SLAC National Accelerator Laboratory Controls Department LCLS Maintenance.
Steve Lewis XTOD Controls FDR 13 March 2008 XTOD Vacuum Controls Final Design Review Steve Lewis/Keith Kishiyama 13 March 2008.
LCLS NEH Operational and User Safety Programs
National Aeronautics and Space Administration 1 Rehab of Electric Propulsion Lab Controls, PH2 Site Visit Registry COMPANYPRIMESUBPHONE NUMBER.
David Schultz Accelerator Readiness Dec. 2, ‘08 SLAC National Accelerator Laboratory 1 Undulator Complex Status LCLS Introduction.
Project Status Update Mark Petree LCLS Self Seeding Status: Management put it on hold. – Preliminary conceptual design completed – Interference.
1 Zoe Van Hoover 1 User Safety: Commissioning and Early Experiments NEH ARR User Safety: LCLS NEH Commissioning and Early Experiments.
Soil Excavation and Concrete Penetration Permitting Process at LLNL Dennis Chew Plant Engineering Department September, 2006 UCRL-PRES This work.
David Saenz Readiness for Oct 12, 2006 # Meeting of the LCLS Facilities Advisory Committee LCLS Conventional Facilities.
John N. Galayda LCLS Accelerator Readiness December 2, LCLS Overview December 2, 2008 Project Construction Status.
1 Enzo Carrone 1 NEH Safety Systems NEH ARR 2009 NEH Safety Systems Enzo Carrone June 30 th, 2009.
James C. Liu 1 and Lawrence S. Walker 2 1. SLAC National Accelerator Laboratory, CA, USA 2. Brookhaven National Laboratory, NY, USA 1. Introduction ANSI.
Linda Bagby - SBN Program Electrical Coordinator ICARUS Electronics Meeting 27 January 2016 SBN Program Operational Readiness Clearance.
Linda Bagby - SBN Program Electrical Coordinator T600 Installation 8 February 2016 SBN Program Operational Readiness Clearance.
THEMIS Mission Assurance
Experimental Facilities Planning
DOE Review May, 2005 Steve Lewis
LTU/Undulator Installation Status
Meeting of the LCLS Facilities Advisory Committee
Stefan Moeller – XES Manager May 14, 2009
John N. Galayda – Director of LCLS Construction March 30, 2009
e-Beams Systems Update
Installation of Photon Beam Transport to FEH
Injector / Linac Installation Current Status
FEE Diagnostics and Commissioning
Shutdown Planning & Installation Schedule
LCLS Week 4-8 April, 2005 Steve Lewis
LTU/Undulator Installation Status
DOE Review 7-9 February, 2006 Steve Lewis
Installation Status & Operational Readiness Process
LCLS Lehman Review February 7-9, 2005
BC2 / Linac Installation Coordination Kathleen Ratcliffe
Presentation transcript:

Lawrence Livermore National Laboratory This work performed under the auspices of the U.S. Department of Energy by Lawrence Livermore National Laboratory under Contract DE-AC52- 07NA FEE and NEH XTOD Controls Installation Readiness Review November 7, 2008 Steve Lewis, Bill Abraham, Ron Shaw, Dave Kasimatis, Jim Greer, Jim Atkins Performance Measures x.x, x.x, and x.x This work performed under the auspices of the U.S. Department of Energy by Lawrence Livermore National Laboratory under Contract DE-AC52- 07NA27344.

2 Option:UCRL# Option:Directorate/Department Additional Information FEE - NEH Controls installation sequence Racks active to subsystems shown are highlighted. Triple Bay ( Alcove ) BL Instr. racks Triple Bay ( Alcove )

3 Option:UCRL# Option:Directorate/Department Additional Information Subsystems  Fixed Mask, X-Ray Slit  K-Measurement Monochromator  Gas Detector/Solid-Gas Attenuator  Total Energy  Direct Imager  Off-Set Mirrors and Pop-up’s  NEH Hutches 1,2 Vacuum FEE INSTALLATION PHASE 1 FEE-NEH INSTALLATION PHASE 2

4 Option:UCRL# Option:Directorate/Department Additional Information FEE - Installation Phase 1

5 Option:UCRL# Option:Directorate/Department Additional Information FEE – NEH Installation Phase 2

6 Option:UCRL# Option:Directorate/Department Additional Information Subsystems  Fixed Mask, X-Ray Slit A  K-Measurement Monochromator B  Gas Detector/Solid-Gas Attenuator A  Total Energy A  Direct Imager A  Off-Set Mirrors and Pop-up’s C  NEH Hutches 1,2 vacuum C FEE PHASE 1 FEE – NEH PHASE 2 CONTROLS READINESS

7 Option:UCRL# Option:Directorate/Department Additional Information Readiness Table ACTIVITY LEVEL A LEVEL B LEVEL C Electrical / Electronic Design √√ √ partial doc’s Procurement √√√ partial Assemblies Installed in Racks √√ ○ Cable requirements to Plant (Ponce) √ cable ph 5 √ cable Ph 6 AC Power Requirements to CF (Lori - Khalid) including FEE PPS. Installation plans in BIO (Bldg. Insp. Office) for review. √ power ph 1 √ power ph 2 Safety Integration (NRTL, AHJ, Elect., Radiation, Seismic,… ) √ ○○ CONTROLS READINESS Integration at LLNL by rack Ship Date √ ○ ○

8 Option:UCRL# Option:Directorate/Department Additional Information Instrument Racks under test in lab (on stands, w/doors removed). Ship first week of Jan 09 (FEE Phase 1)

9 Option:UCRL# Option:Directorate/Department Additional Information Triple bay Vacuum rack under test in lab. Ship first week of Jan 09 (FEE Phase 1)

10 Option:UCRL# Option:Directorate/Department Additional Information Triple bay Vacuum rack-rear view showing I/O (w/panels removed). (FEE Phase 1)

11 Option:UCRL# Option:Directorate/Department Additional Information OMS Instrumentation and Beam line Vacuum Racks Loading now. Ship mid-Feb 09 (FEE Phase 2)

12 Option:UCRL# Option:Directorate/Department Additional Information Facility Integration  Cable Plant Phase 5 FEE install……………complete (Ponce)  Cable Plant Phase 6 OMS prep …CAPTAR encoding (Misaki)  FEE ac power for Phase 1&2 loads……in BIO review (Khalid)  MPS requirements…… Mike Przybylski  Controls documentation available electronically. Hardcopy workbook on table for viewing.

13 Option:UCRL# Option:Directorate/Department Additional Information Safety  Controls hardware is NRTL certified or AHJ inspected by LLNL prior to ship date.  Integrated Work Safety (IWS’) documents from LLNL are applicable to LCLS ISM ‘work basis’ for work to be performed during FEE controls installation.  Safety oversight occurs when Conv. Facilities submits vendor (MTH Engineers, Inc) electrical plans to the Bldg. Inspection Office for approval. Reviewers include Electrical, Radiation, Seismic, Environmental, Waste, and others.