OVER CURRENT RELAY The relay has two settings. These are the time setting and the plug setting. The time setting decides the operating time of the relay.

Slides:



Advertisements
Similar presentations
Announcements Be reading Chapters 9 and 10 HW 8 is due now.
Advertisements

MOLDED CASE CIRCUIT BREAKER BASICS
ENERGY CONVERSION ONE (Course 25741)
RT3b – André Smit, Siemens USA
PROTECTION scheme for bus bar / feeder
Tap Conductor Rules.
Power System Analysis/ Power System 1 EEE 4113/ EEE 3131
Dynamic Programming Lets begin by looking at the Fibonacci sequence.
Material used:  Tin  Lead  Zinc  Silver  Antimony  Copper  Aluminum.
Find all subgroups of the Klein 4- Group. How many are there?
TESTING AND COMMISIONING
Combined Selective Systems :-
Specification of CTs: CTs are defined in terms of rated burden, accuracy class and accuracy limit. Saturated values of rated burden are: 2.5, 5, 7.5, 10,
Unit Transformer Unit transformer are step up transformer which is connected to generating house & step up voltage from 15kV voltage to 132 voltage level.
Differential protection : (protective relaying by Blackburn)
Getting Started with Hypothesis Testing The Single Sample.
Transformer.
Substations. Substations Chapter 4 Substations Major types of equipment found in most transmission and distribution substations with their purpose,
Bonding, Grounding and the NEC  Presented by The National Association of Certified Home Inspectors
2001 South First Street Champaign, Illinois (217) Davis Power Consultants Strategic Location of Renewable Generation Based on Grid Reliability.
Chapter 7 SYSTEM PROTECTION
Copyright © Cengage Learning. All rights reserved. 6 Normal Probability Distributions.
Electrical Installation 2
Grounding, bonding, and ground fault currents
Connections of a CT and a PT to supply, load and relay.
Electrical Distribution Training
TESTING AND COMMISIONING
By J DAVID MANOHAR (08A31A0232). NECESSITY OF SUPERCONDUSTOR  Damage from short circuit is constant threat in power systems  All the power systems components.
 Safety  Protective devices - devices designed to automatically limit or shut off the flow of electricity in the event of a ground-fault, over-load or.
Need for protection Power system must be kept in operation continuously without major breakdowns This can be achieved in two ways: 1.Implement a system.
Equations, Inequalities, and Mathematical Models 1.2 Linear Equations
Half Wave rectifier Full wave rectifier Mathematical Examples
Protection of Microgrids Using Differential Relays
Lecture 22 Unbalanced Faults and Power System Protection Professor Tom Overbye Department of Electrical and Computer Engineering ECE 476 POWER SYSTEM ANALYSIS.
Queensland University of Technology CRICOS No J Protection of distributed generation connected networks with coordination of overcurrent relays.
Transformer Protection Over-current protection in the form of fuses may be the only protection provided to a small 100 kVA, 11 kV/440 V distribution transformer.
Lecture 22 Unbalanced Faults and Power System Protection Professor Tom Overbye Department of Electrical and Computer Engineering ECE 476 POWER SYSTEM ANALYSIS.
Announcements Read Chapters 10 and 11
Introduction to switchgears
A PRESENTATION OF PRACTICAL TRAINING ON “400KV GSS “ \
Statistical Inference Statistical inference is concerned with the use of sample data to make inferences about unknown population parameters. For example,
Functions (Mappings). Definitions A function (or mapping)  from a set A to a set B is a rule that assigns to each element a of A exactly one element.
A SEMINAR ON 400 KV GSS(RRVPNL) BIKANER.
CHAPTER 11 Mean and Standard Deviation. BOX AND WHISKER PLOTS  Worksheet on Interpreting and making a box and whisker plot in the calculator.
SARDAR VALLABHBHAI PATEL INSTITUTE OF TECHNOLOGY PREPARED BY: 1)BALDIWALA ALIABBAS ( ) 2)PARTH GUPTA ( ) 3)ANIL KHATIK ( )
Protection of Power Systems
1 :. Introduction These are special type of transformers used for the measurement of voltage, current, power and energy. As the name suggests, these transformers.
DC Machine & Transformer
 The figure below shows a protection system for a transmission line, consisting of a CT, PT, a relay and its associated circuit breaker.
Power System Protective Relaying-Part Two
Protection of Power Systems
Part Three – Relay Input Sources
 Energised by two quantities(voltage and current)  Φ1 and Φ2 set by voltage and current  Eddy currents induced in the disc due to two fluxes  Interaction.
TRANSFORMERS.
Announcements Please read Chapters 9, 10 and 11 HW 8 quiz today
Protection of Power Systems
Objectives Describe the introduction of a zener diode briefly
Protection of Power Systems
ECE 476 POWER SYSTEM ANALYSIS
Analysis of FADC single-crystal data
Removal of Fraser RAS from RAS Databse
ELECTRICAL INSTALLATION AND MAINTENANCE (EIM) 5 INSTALL ELECTRICAL PROTECTIVE DEVICES FOR DISTRIBUTION, POWER, LIGHTING, AUXILIARY, LIGHTNING PROTECTION.
Chapter 7 System Protection
Calculations: Transformers and Service Conductor Calculations
Numerical Analysis Lecture 16.
Removal of Fraser RAS from RAS Databse
POWER SYSTEM COMMISSIONING AND MAINTENANCE PRACTICE
Transformer Calculations: Word Problems
POWER SYSTEM COMMISSIONING AND MAINTENANCE PRACTICE
Presentation transcript:

OVER CURRENT RELAY The relay has two settings. These are the time setting and the plug setting. The time setting decides the operating time of the relay while the plug setting decides the current required for the relay to pick up.

The plug-setting multiplier, PSM, is defined as follows: where I relay is the current through the relay operating coil and PS is the plug-setting of the relay = pickup current. The value of PSM tells us about the severity of the current as seen by the relay A PSM less than 1 means that normal load current is flowing. At PSM > 1, the relay is supposed to pick up. Higher values of PSM indicate how serious the fault is. For example, let us consider a 1.0 A relay (i.e. a relay with current coil designed to carry 1.0 A on a continuous basis) whose plug has been set at 0.5 A, i.e. at 50%. Assume that, for a certain fault, the relay current is 5.0 A. The relay, therefore, is said to be operating at a PSM of (5.0/0.5) = 10.

Inverse Time Over-current Relay Inverse time characteristic fits in very well, with the requirement that the more severe a fault is, the faster it should be cleared to avoid damage to the apparatus

Inverse definite minimum time (IDMT) over-current relay This is possibly the most widely used characteristic. The characteristic is inverse in the initial part, which tends to a definite minimum operating time as the current becomes very high. The operating time is Very inverse time over-current relay The inverseness of this characteristic is higher than that of the IDMT characteristic. The operating time is Extremely inverse time over-current relay The inverseness of this characteristic is higher than that of the very inverse characteristic. The operating time is

Application of IDMT Relays for Protection of a Distribution Feeder The purpose of relay R B is to provide primary protection to line BC. The purpose of relay R A is to provide primary protection to line AB and back-up to line BC. We start the setting process from the tail end of the system. (a) Deciding the CT ratios and plug settings (pickup current): (i) At relay B, the maximum load current, assuming 25% overload is: 80 A + (0.25 x 80 A) = 100 A Assuming 1 A relay to be used, the CT ratio can be selected to be 100 : 1. The plug setting PS can be done at 100%, i.e. PS = 1.0 A.

(ii) At relay A the maximum load current, assuming 25% overload is (160+80)+0.25(160+80) = 300 Assuming 1 A relay to be used, the CT ratio can be selected to be 300 : 1. The plug 1)setting can be done at 100%, i.e. PS = 1.0 A. (b) Deciding the time-multiplier settings: Starting from the most remote relay R B (i) Since R B does not have to maintain selectivity with any other relay, it can be made to operate the fastest. Thus the TMS of R B can be selected as 0.1. (ii) Now, to maintain selectivity between R A and R B, the following constraint must be met:

The operating time of R B for maximum fault just beyond bus B can be found from For maximum fault at B, fault current = 3000 A on primary side which becomes (3000/100) = 30 A secondary. Since plug setting is done at 1.0 A, The TMS of R B has already been set at 0.1. Substituting these values, we get