Sandrine Thomas (T&S Project Scientist) & Telescope and Site Team.

Slides:



Advertisements
Similar presentations
CMSC 2006 Orlando Active Alignment System for the LSST William J. Gressler LSST Project National Optical Astronomy Observatory (NOAO) Scott Sandwith New.
Advertisements

1 Second Safety Council Meeting Tucson, AZ April 10-11, 2014 Name of Meeting Location Date - Change in Slide Master The Dome Project Bill Gressler Telescope.
PALM-3000 Management Update A. Bouchez, J. Roberts Team Meeting #15 10/29/09.
NGAO Instrumentation Overview September 2008 Updated Sean Adkins.
WBS & AO Controls Jason Chin, Don Gavel, Erik Johansson, Mark Reinig Design Meeting (Team meeting #10) Sept 17 th, 2007.
NGAO Management Update Peter Wizinowich NGAO Meeting #11 November 5, 2007.
HARPS-NEF PDR December 6 & 7, HARPS-NEF Program Project Manager Tim Norton.
LSST Wavefront Sensing Bo Xin Systems Analysis Scientist (LSSTPO) Chuck Claver, Ming liang, Srinivasan Chadrasekharan, George Angeli (LSST wavefront sensing.
1 Engineering the James Webb Space Telescope Paul Geithner JWST Deputy Project Manager - Technical March 26, 2011.
Effective Methods for Software and Systems Integration
SAM PDR1 SAM LGS Mechanical Design A. Montane, A. Tokovinin, H. Ochoa SAM LGS Preliminary Design Review September 2007, La Serena.
Server Virtualization: Navy Network Operations Centers
Control Software Integration German Schumacher T&S Software Lead.
M2 Status & Near Term Major Milestones C. Araujo/B. Gressler 1.
Framework for Compliance, Verification, and Non-Conformance George Angeli LSST All-Hands Meeting Bremerton August 17, 2015.
LSST Scheduler status Francisco Delgado Sr. Software Engineer Telescope & Site.
From Research Prototype to Production
MCAO Adaptive Optics Module Mechanical Design Eric James.
Monday Morning J. Sebag T&S Systems Engineer. Close Past… 2 M1M3 acceptance and transportation to storage Reviews and RFPs (Dome, Software, Coating Plant,
August 2 and 3, 2010 Project Cost, Schedule, Risk and Contingency Jay Elias.
Telescope Control System Paul J. Lotz. Scope 2 TCS components 3.
Telescope Integration and Tests Tuesday Afternoon.
M1M3 Status & Near Future Milestones C.Araujo/ J. Sebag 1.
IFE Plant Structural Concepts Including Shielding and Optical Stability Requirements Thomas Kozub, Charles Gentile, Irving Zatz - PPPL.
FLAO system test plan in solar tower S. Esposito, G. Brusa, L. Busoni FLAO system external review, Florence, 30/31 March 2009.
Magellan F/5 System Status A.Szentgyorgyi / Ann Arbor 25 Sept 2005.
John Peoples for the DES Collaboration BIRP Review August 12, 2004 Tucson1 DES Management  Survey Organization  Survey Deliverables  Proposed funding.
The Active Optics System S. Thomas and the AO team.
3.1.1 Optics, Optical Corrector, Mechanical Systems M. Johns, C. Claver.
M1M3 Cell and Support System. M1M3 on Telescope 2 Location of the M1M3 Cell and Mirror on the Telescope.
Response to TAC8 and Annual Review Recommendations John Haines Head of Target Division April 2, 2014.
AURA New Initiatives Office. GSMT SWG Meeting L. Stepp, July 30, 2002 NSF Science Working Group Support Available from AURA NIO Available Personnel Current.
Telescope Mount Assembly (TMA) Status and Schedule Design Contractor: Empresarios Agrupados (Madrid Spain) Fabricator: Asturfeito (Asturias, Spain) LSST.
Reproduction interdite © ALMA EUROPEAN CONSORTIUM Reproduction forbidden Design, Manufacture, Transport and Integration in Chile of ALMA Antennas Page.
COSMO Large Coronagraph Preliminary Design Review
SPIE 2014 Montreal, Quebec, Canada June 22 nd - June 27 th, LSST Telescope and Site Status William J. Gressler Telescope and Site Manager J. Andrew,
FLAO_08 FLAO System Shipping Plan Document 646f010a Richard Demers, Guido Brusa, Armando Riccardi, Daniele Galieni FLAO system external review, Florence,
 Project Time Management includes the processes required to accomplish timely completion of the project  Part of Triple Constraints  Managers often.
Proposal for ESS DTL Roadmap. Divide Into Four Phases 1.Conceptual Design Phase (In progress) 2.Technical Design Phase 3.Prototyping Phase 4.Construction.
Content Lessons from writing proposals and work on PTDR How can this meeting help to remedy problems SCT AOB.
1 OBSERVATORY CONTROL SYSTEM (OCS) FRANCISCO DELGADO OCS CAM.
Commissioning Planning
LSST Commissioning Overview and Data Plan Charles (Chuck) Claver Beth Willman LSST System Scientist LSST Deputy Director SAC Meeting.
Camera PDR/CD1 Planning 19 September 2008
Accelerator Readiness Review October 31, 2006
ComCam Hardware and Interfaces James Howard ComCam CAM LSST 2017 Project & Community Workshop 2017 Aug 15.
Agenda ComCam planning and scheduling (James & Jacques) CCS & CCS-TCS Interface (Tony) Software to use ComCam Software to get data out of ComCam (Mike)
Telescope Assembly, Integration and Verification (AIV) WBS 04C. 14 J
Systems Engineering, Verification, and Commissioning for LSST George Z
ComCam Hardware and Interfaces James Howard ComCam CAM LSST 2017 Project & Community Workshop 2017 Aug 15.
LSST Commissioning Overview and Data Plan Charles (Chuck) Claver Beth Willman LSST System Scientist LSST Deputy Director SAC Meeting.
LSST Commissioning: FY18 Planning
Facility Concept Design and Study
LSST Commissioning Kevin Reil LSST Commissioning Camera Rep
Integration & Commissioning
Chuck F Claver LSST System Scientist & Commissioning Lead
OCS Scheduler Status Francisco Delgado T&S Software Manager
Camera to Top End Assembly Integration Travis Lange Camera I&T M. E
2K CB FDR Overview:  Agenda, Charge, Review Process
DOE: Transition from MIE to Early Operations Kevin Reil LSST Camera Commissioning Lead LSST Commissioning Plan Review January 24-26, 2017.
Management Breakout: MREFC Budget Summary Victor L
X-ray Pump-Probe Instrument
LSST Control Software Integration Francisco Delgado OCS Software Manager LSST Commissioning Plan Review January 24-26, 2017.
OCS Scheduler Status Francisco Delgado T&S Software Manager
Software & Hardware for Wavefront Estimation Pipeline Development Te-Wei Tsai Software Engineer Joint Technical Meeting March 6, 2017.
Click to add title Planning for LSST Verification George Angeli LSST All Hands Meeting Tucson August 15, 2016.
Vendor Interactions Paul J. Lotz.
PSS verification and validation
DOE Review of the LCLS Project October 2006
Bunker Project Schedule/Budget
Presentation transcript:

Sandrine Thomas (T&S Project Scientist) & Telescope and Site Team

Telescope and Site Subsystem 2 TMA (EA) TMA (EA) Hexapods (Moog/CSA) Hexapods (Moog/CSA) M1M3 (SOML) M1M3 (SOML) M1M3 Mirror Cell (TBD) M1M3 Mirror Cell (TBD) M2 (Harris) M2 (Harris) Dome (EIE) Dome (EIE) Summit A&E Construction ( Arcadis/Besalco) Summit A&E Construction ( Arcadis/Besalco) Base Construction (TBD) Base Construction (TBD) Auxiliary Telescope and Calibration Coating Plant (TBD) Active optics System Software

Schedule Summit Construction Dome Construction Mount Construction Dome Integration M1M3 Cell Weldment Mount Factory Test Mount Integration Telescope Integration M1M3 Assy Ship to Chile Telescope On-Sky Testing Summit Construction Dome Design Mount Design Dome Integration Coating Plant Design Mount Integration Telescope Integration On Summit Coatings Telescope ComCam On-Sky Testing M1M3 Cell Hardware M1M3 Assy Optical Testing M2 Cell Assy Design Mount Fabrication Dome Fabrication Mount Factory Test M2 Cell Assy Fabrication M2 Cell Assy Optical Testing M2 Assy Ship to Chile Calypso Refurbishment Calibration Instrument Fab Calibration Instrument Test Coating Plant Construction Breakout: Monday 11am-12:30pm

Summit Facility Status 4 January 2015: Contract for construction was initiated with Besalco Construcciones (Chilean) Major excavation is now almost complete – after major remediation of subsurface rock/soil conditions under the building. Initial foundation work and raising of columns is in progress. Major equipment approved for purchase – electrical transformer, generator, cranes. Structural steel fabrication subcontract initiated. Work force of over 50 on site daily

Base Facility Status 5 May 2015: Requirements for Base Facility in La Serena Chile were finalized with input from Data Management team. Cooperation in project with AURA and NOAO-S was formalized. Requirements for Data Center were defined by DM and T&S teams. July 1 st : Request for Proposals for Architectural and Engineering Services was issued, proposals received. Recommendation of committee has been forwarded for approval. September 2015: Anticipate start of design of Base Facility ~ October 2016 Anticipate start of construction Design concept layout from one of the Proposals

Dome Status 6 May 2015: Design-Build Contract with European Industrial Engineering (EIE) was signed May 27-28: Kick-off meeting was held at EIE offices in Mestre, Italy Early emphasis was placed on interface to building (already in construction!) and definition of major subsystems. Early progress has included: Verification of mass budget for dome. Initial finite element analysis. Definition of mounting plates and anchor bolts to lower enclosure. Location and sizing of drive units and bogies. Breakout: Monday 1:30pm-3pm

7 Telescope Mount Assembly (TMA): Preliminary Design Design Contractor: Empresarios Agrupados (Madrid Spain) Fabricator: Asturfeito (Asturias, Spain) LSST Telescope and Site Manager: Shawn Callahan (Tucson, Az) Dynamic performance meets all TMA requirements. YearMilestoneDate 2015Preliminary Design Review 80% completion September 28-October Final Design review by subsystems October 30 – December Azimuth track and concrete pier complete April All TMA components ready for installation December Factory testing reviewMarch All hardware delivered to port July TMA assembled at siteMay TMA testing complete on site July 15 Breakout: Monday 1:30pm-3pm

M1M3 Acceptance (April 10th 2015) 8 More information here: Collection-3272,Document Breakout: Tuesday 11am-12:30pm SOML -Interferometric measurements done by SOML: surface uniformity and figure accuracy for both M1 and M3 meet or exceed requirements. -Position of M1 relative to M3 within tolerance -Radii of curvature, conic constants ….. are within tolerance. -Existence of small additional residuals: studies show a negligible scientific impact.

9 M1M3 Mirror Storage in Tucson Plan to visit/inspect mirror every months May July Arrival at Storage Facility Final Placement of the mirror container Last Inspection at Storage Facility

M1M3 Acceptance (April 10th 2015) : Before Shipping to Chile, M1M3 + cell+mirror support system will be tested at SOML with the same interferometric testing configuration SOML -Interferometric measurements done by SOML: surface uniformity and figure accuracy for both M1 and M3 meet or exceed requirements. -Position of M1 relative to M3 within tolerance -Radii of curvature, conic constants ….. are within tolerance. -Existence of small additional residuals: studies show a negligible scientific impact. More information here: Collection-3272,Document Breakout: Tuesday 11am-12:30pm

M1M3 on Telescope 11 Location of the M1M3 Cell and Mirror on the Telescope

Mirror supported on Cell 12 Mirror Wt: ~17000 kg Total Wt (Mirror + Cell + Internals): ~53000 kg Key systems:  Gravity support and figure control force actuators: pneumatic support actuators  Hardpoint Struts to locate mirror  Thermal control via cooling air injection into mirror cores Breakout: Tuesday 11am-12:30pm July: RFP sent out August 14 th : received answers October: anticipates answers to the vendors

Mirror M2 13 Before shipping of the M2 mirror to Chile, the M2 mirror cell assembly (mirror+cell+mirror support system) will be tested in Rochester NY in the downward orientation, the same configuration used during ion figuring. Breakout: Tuesday 11am-12:30pm Sept 2017: Expected completion by Exelis

Hexapods & Rotator Status Aug 11 th -12 th 2015: Interim Mechanical Review conducted (equivalent to critical design review) with no significant issues determined. Late 2016: Systems scheduled for completion 14 Breakout: Monday 1:30pm-3pm Flexure End Joints Strut Designed for M2 & Camera Hexapod

Coating Plant Design Review 15 June 29 th 2015: Coating Plant Design Review held Review covered baseline designs of the cleaning and stripping equipment and the magnetron coating chamber. Requirement on the coating (both Aluminum and Silver) July 2015: Coating Plant System RFP. A good variety of vendors expressed interest in the project. Sept. 11 th 2015: Vendor proposals are due January 2016: Expect contract award. Breakout: Monday 1:30pm-3pm Collection-2458 in Docushare

T & S Software Status Integration status: – SAL software utilized successfully in CCS, DMCS and OCS communications tests. – OCS Sequencer updated to latest device state model, as well as commanding and scripting. – ICD conformant interface simulators for major subsystems developed. – XML schemas developed for SAL and OCS. – LSE-70 and LSE-209 communications documents updated and to be submitted to CCB 16

T & S Software Status 17 Breakout: Tuesday 1:30pm-3pm 17 OCS Scheduler – Scheduler requirements document delivered. – OPSIM and Scheduler redesign of development achieved. TCS status: – Development planning in progress. – SAL software delivered to contractors of Mount, Dome, Hexapod/Rotator, M2. – Vendor ICDs updated to integration agreed model. – 3 Inner Loop Controller test stands completed. 17

18 LSST Active Optics & Wavefront Sensing 18 LSST Active Optics System (AOS): Maintain system alignment Maintain surface figure on three mirrors Challenges: 61% Central Obstruction f/1.23 Off-axis Distortion & Vignetting(~1.7 o ) Field Dependence (covering 1.51° to 1.84°) Degrees Of Freedom controlled by AOS M2 hexapod rigid body positions Camera hexapod rigid body positions M1M3 bending modes M2 bending modes Degrees Of Freedom controlled by AOS M2 hexapod rigid body positions Camera hexapod rigid body positions M1M3 bending modes M2 bending modes

AOS status and next steps  Publication of the update to the basic curvature sensing algorithm by Bo Xin (large central obscuration, small f/number, distortion and vignetting)  Working on the Active Optics System requirements document – Wavefront Estimation Pipeline (WEP) part of WBS 4.7 – Active Optics Control System (AOCS) part of WBS 4.11  WEP: 100% successfully translated from Matlab to Python  Start engaging work with the DM subsystem to incorporate optimization of the WEP in the DM framework.  AOCS: algorithm is written in Matlab to be translated into Labview  Include the telescope models and use PhoSim to built the look-up-table (temperature, elevation and azimuthal angle). Final delivery is scheduled for the end of Oct Breakout: Tuesday 11am-12:30am

Calibration Effort 20 New Hire: Patrick Ingraham – Calibration Hardware Scientist – Leading calibration hardware development with Chuck Claver Recent Calibration Re-planning Auxiliary Telescope (Calypso) Refurbishment expected to start in October 2015 Modification to the spectrograph design to offer increased cadence, versatility, flexibility Developing a Collimated Beam Projector (CBP): Will map transmission as a function of field position, pupil position and wavelength Breakout: Wednesday 9am-10:30am

Integration sequence in phase with subsystems delivery Integration and Test Plan (LTS-104) describes the general strategy, includes the integration and test sequence and provides a summary for all major key activities. Three Major Phases: Phase 1 (P1): Heavy Construction Phase 2 (P2): Mirrors Coating and Integration Phase 3 (P3): Alignment Phase START END P1 P2 P3 Breakout: Tuesday 3:30pm-5pm

Conclusion 22 It’s been a busy year with among others: – Start of construction – M1M3 acceptance and transportation to storage – Lots of new hires Next: – Final contracts being awarded – Calibration Hill getting more active – Integration Plans – Operation Plans We will use more actively the documentation Control

We’re heading south no matter the obstacles… 23