PHENIX WEEKLY PLANNING 9/6/2007 Don Lynch. 9/6/2007 Weekly Planning Meeting 2007 Summer Shutdown Schedule ItemStartComplete RPC Factory set upin progress.

Slides:



Advertisements
Similar presentations
PHENIX WEEKLY PLANNING 9/13/2007 Don Lynch. 9/13/2007 Weekly Planning Meeting 2007 PHENIX Shutdown April-June 2007: Complete run, De-mount HBD West, Begin.
Advertisements

PHENIX WEEKLY PLANNING 2/8/2007 Don Lynch. 2/8/207 Weekly Planning Meeting 2 Remaining Schedule StartComplete Cosmic Ray Run (Run 6.9)In Progress Pink.
PHENIX WEEKLY PLANNING 1/17/2008 Don Lynch. 1/17/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn Going1/18 Gas.
PHENIX WEEKLY PLANNING 6/7/2007 Don Lynch. 6/7/2007 Weekly Planning Meeting 2 Schedule End of Run Party 6/29/07 Next Maintenance Day No More Planned Remove.
2/2/20121 PHENIX WEEKLY PLANNING 2/2/2012 Don Lynch.
PHENIX WEEKLY PLANNING 2/15/2007 Don Lynch. 2/15/207 Weekly Planning Meeting 2 Remaining Schedule StartComplete Cosmic Ray Run (Run 6.9)In Progress All.
PHENIX WEEKLY PLANNING 10/25/2007 Don Lynch. 10/25/2007 Weekly Planning Meeting2 Run 8 Prep Schedule ItemStartFinish MPC South InstallationDoneDone Elec.
PHENIX WEEKLY PLANNING 11/1/2007 Don Lynch Daylight Savings Time ends Sunday Nov. 4 at 2:00 AM.
2/9/20121 PHENIX WEEKLY PLANNING 2/9/2012 Don Lynch.
PHENIX WEEKLY PLANNING 5/17/2007 Don Lynch. 5/17/2007 Weekly Planning Meeting 2.
PHENIX WEEKLY PLANNING 5/31/2007 Don Lynch. 5/31/2007 Weekly Planning Meeting 2 Schedule End of Run Party 6/29/07 Next Maintenance Day 6/6 or 6/13/07?
6/6/ PHENIX WEEKLY PLANNING 6/6/2013 Don Lynch Note: No PHENIX planning meeting this week due to end of run party. Feel free to discuss safety and.
PHENIX WEEKLY PLANNING 2/21/2008 Don Lynch. 2/21/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
Technical Support /26/08 PHENIX WEEKLY PLANNING 10/2/2008 Don Lynch.
8/9/20121 PHENIX WEEKLY PLANNING 8/9/2012 Don Lynch.
PHENIX WEEKLY PLANNING 4/10/2008 Don Lynch. 04/10/08 Shutdown ’08 Schedule Purge Flammable Gas, Magnet & DAQ TestsDone Remove lock-out & open shield wallDone.
PHENIX WEEKLY PLANNING 5/24/2007 Don Lynch. 5/24/2007 Weekly Planning Meeting 2 Schedule End of Run Party 6/29/07 Next Maintenance Day 6/6/07 Remove HBD.
PHENIX WEEKLY PLANNING 3/8/2007 Don Lynch. 3/8/207 Weekly Planning Meeting 2 Schedule Cosmic Ray Run (Run 6.9) Continues…. All Up Commissioning In Progress.
12/29/20121 PHENIX WEEKLY PLANNING 12/29/2011 Don Lynch.
Technical Support /4/08 PHENIX WEEKLY PLANNING 9/4/2008 Don Lynch.
PHENIX WEEKLY PLANNING 2/14/2008 Don Lynch. 1/31/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
PHENIX WEEKLY PLANNING 7/19/2007 Don Lynch. 7/19/2007 Weekly Planning Meeting 2007 Summer Shutdown Schedule ItemStartComplete RPC Factory set upStarted.
PHENIX WEEKLY PLANNING 10/11/2007 Don Lynch. 10/11/2007 Weekly Planning Meeting2 Run 8 Prep Schedule ItemStartFinish MPC South InstallationDoneDone Elec.
PHENIX WEEKLY PLANNING 3/6/2008 Don Lynch. 3/6/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
Technical Support /1/08 PHENIX WEEKLY PLANNING 5/1/2008 Don Lynch.
PHENIX WEEKLY PLANNING 6/29/06 Don Lynch. 6/29/2006 Weekly Planning Meeting 2 This Week TOF W tests continue, modification decisions made? New HV connector.
PHENIX WEEKLY PLANNING 3/27/2008 Don Lynch. 3/27/2008 Weekly Planning Meeting2 Shutdown ’08 Schedule CM Crane ReviewMar Purge Flammable Gas, Magnet.
5/1/ PHENIX WEEKLY PLANNING May 1, 2014 Don Lynch.
PHENIX WEEKLY PLANNING 2/2/06 Don Lynch. Prep Schedule for Run 6 BBC N&S dried, tested re-installed, final tested [DONE] MuTr FEE and anode purge lines.
PHENIX WEEKLY PLANNING 11/2/06 Don Lynch. 11/2/06 Weekly Planning Meeting 2 New Detectors TOF West HBD RXNP MPC North.
PHENIX WEEKLY PLANNING 3/22/2007 Don Lynch. 3/22/2007 Weekly Planning Meeting 2 Schedule Re-Start 5 man shifts 3/20/07 Beam: blue ring 3/8/07, in yellow.
PHENIX WEEKLY PLANNING 8/9/2007 Don Lynch. 9/9/2007 Weekly Planning Meeting 2007 Summer Shutdown Schedule ItemStartComplete RPC Factory set upStarted.
PHENIX WEEKLY PLANNING 1/10/2008 Don Lynch. 1/10/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn Going1/18 Gas.
PHENIX WEEKLY PLANNING 2/9/06 Don Lynch. Prep Schedule for Run 6 BBC N&S dried, tested re-installed, final tested [DONE] MuTr FEE and anode purge lines.
PHENIX WEEKLY PLANNING 9/14/06 Don Lynch. 9/14/06 Weekly Planning Meeting 2 PHENIX Shutdown Overview Task_NameStart_DateFinish_Date PHENIX Shutdown '065/1/200612/8/2006.
Technical Support /8/08 PHENIX WEEKLY PLANNING 5/8/2008 Don Lynch.
PHENIX WEEKLY PLANNING 12/6/2007 Don Lynch. 12/6/2007 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn GoingOn Going.
1 3/10/2011 PHENIX WEEKLY PLANNING 3/10/2011 Don Lynch.
9/27/20121 PHENIX WEEKLY PLANNING 9/27/2012 Don Lynch.
PHENIX WEEKLY PLANNING 10/4/2007 Don Lynch. 10/4/2007 Weekly Planning Meeting 2007 PHENIX Shutdown October 2007: Finish MPC South Installation, replace.
PHENIX WEEKLY PLANNING 12/7/06 Don Lynch. 12/7/06 Weekly Planning Meeting 2.
PHENIX WEEKLY PLANNING 10/18/2007 Don Lynch. 10/18/2007 Weekly Planning Meeting2 Run 8 Prep Schedule ItemStartFinish MPC South InstallationDoneDone Elec.
12/6/20121 PHENIX WEEKLY PLANNING 12/6/12 Don Lynch.
1/26/20121 PHENIX WEEKLY PLANNING 1/26/2012 Don Lynch.
PHENIX WEEKLY PLANNING 11/15/2007 Don Lynch. 11/8/2007 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn Going11/30.
PHENIX WEEKLY PLANNING 12/27/2007 Don Lynch. 12/27/2007 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn GoingOn Going.
Technical Support /19/08 PHENIX WEEKLY PLANNING 6/19/2008 Don Lynch.
PHENIX WEEKLY PLANNING 3/15/2007 Don Lynch. 3/15/2007 Weekly Planning Meeting 2 Schedule Cosmic Ray Run (Run 6.9) Done All Up Commissioning On Going Re-Start.
PHENIX WEEKLY PLANNING 3/02/06 Don Lynch. BLM Test.
Technical Support /15/08 PHENIX WEEKLY PLANNING 5/15/2008 Don Lynch.
PHENIX WEEKLY PLANNING 1/24/2008 Don Lynch. 1/17/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going Switch.
5/24/20121 PHENIX WEEKLY PLANNING 5/24/2012 Don Lynch.
PHENIX WEEKLY PLANNING 6/28/2007 Don Lynch. 6/14/2007 Weekly Planning Meeting 2007 Summer Shutdown Schedule ItemStartComplete RPC Factory set up5/ ?
PHENIX WEEKLY PLANNING 12/20/2007 Don Lynch. 12/20/2007 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn GoingOn Going.
12/19/ PHENIX WEEKLY PLANNING Dec. 19, 2013 Don Lynch.
PHENIX WEEKLY PLANNING 7/26/2007 Don Lynch. 7/26/2007 Weekly Planning Meeting 2007 Summer Shutdown Schedule ItemStartComplete RPC Factory set upStarted.
PHENIX WEEKLY PLANNING 5/7/2007 Don Lynch (Thursday is Monday this week)
PHENIX WEEKLY PLANNING 1/31/2008 Don Lynch. 1/31/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going Switch.
PHENIX WEEKLY PLANNING 10/26/06 Don Lynch. 10/20/06 Weekly Planning Meeting 2 PHENIX Shutdown Overview Task_NameStart_DateFinish_Date PHENIX Shutdown.
PHENIX WEEKLY PLANNING 5/3/2007 Don Lynch. 5/3/2007 Weekly Planning Meeting 2 Schedule HyTec CM vibration modes test5/23/07 End of Run Party 6/29/07 Next.
5/30/20131 PHENIX WEEKLY PLANNING 5/30/2013 Don Lynch.
1 1/29/2009 PHENIX WEEKLY PLANNING 1/29/2009 Don Lynch.
Technical Support /16/08 PHENIX WEEKLY PLANNING 10/16/2008 Don Lynch.
PHENIX WEEKLY PLANNING 3/1/2007 Don Lynch March: in like a lion Out like a lamb.
12/08/20111 PHENIX WEEKLY PLANNING 12/08/2011 Don Lynch.
1 7/9/2009 PHENIX WEEKLY PLANNING 7/9/2009 Don Lynch.
PHENIX WEEKLY PLANNING 11/8/2007 Don Lynch. 11/8/2007 Weekly Planning Meeting2 Run 8 Prep Schedule ItemStartFinish Elec. Cooling Water upgrade(CA) (under.
PHENIX WEEKLY PLANNING 6/8/06 Don Lynch. 6/8/2006 Weekly Planning Meeting 2 This Week Rec’d TOF West Access: move HBD to Dead Turtle Position Sec’y of.
1 2/19/2009 PHENIX WEEKLY PLANNING 2/19/2009 Don Lynch.
PHENIX WEEKLY PLANNING 2/14/2008 Don Lynch. 2/14/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
Presentation transcript:

PHENIX WEEKLY PLANNING 9/6/2007 Don Lynch

9/6/2007 Weekly Planning Meeting 2007 Summer Shutdown Schedule ItemStartComplete RPC Factory set upin progress 9/28 HBD West repairin progress 9/28? MPC South upgrade/ bench testsin progress 9/20 MuTr Capacitor Decap in progress 9/30 Work Platform documentationin progress9/7 MuTr FEE Prototype (wp done)in progress9/20 Reinstall MPC North (wp done) in progress9/20 Neutron shield support design & install.In progress9/30 BBC MaintenanceNone required this year Repair RXNP PhototubeDoneDone EC/EmCal survey9/59/30 Move CM North9/209/21 Install CM access ladder (wp needed)9/219/30 Reinstall MPC South9/249/28

9/6/2007 Weekly Planning Meeting Remove HBD East9/30?10/7? HBD Pre survey at SB9/23?9/30? HBD West Mechanical/Gas Reinstall9/30?10/7? HBD EAST Mechanical/Gas Reinstall 11/15?11/28? HBD Electrical Reinstall10/7?12/15? HBD installation survey10/1?12/22? Reinstall MMS East Vert. Lampshade10/110/5 EC Roll In10/810/10 C-A fold scaffolding10/810/8 Move MuID collars to IR10/910/9 Roll in-to IR and North to run pos.10/1010/11 PHENIX techs reconnect water, elect., gas, fibers10/1210/19 InstaCarpenters restore scaffolding, Re-install lift & ladder, re-connect gas sniffers10/1210/19 Mike Rau re-install lift wiring, Re-connectTOF blower 10/1210/19 DC East repair10/1210/19 HBD/MPC/Other TBD Commissioning10/110/31 Start of Run 811/111/ Summer Shutdown Schedule (cont’d)

9/6/2007 Weekly Planning Meeting CM Ladder/Stair Shutdown Access PO pinned Waiting for delivery Delivery ~9/21

9/6/2007 Weekly Planning Meeting CM Ladder/Stair Run Access Features: ~70 deg. Alum ships ladder (1 or 2) lifts off to store verticaly for run and/or to access rack doors. Step up platform above rack and cables. Can be used on either east or west side Hand rails on ladders. Safety rail on platform East access West access

9/6/2007 Weekly Planning Meeting Station 1, 2, 3 access plan Use existing MMN scaffolding components Sta. 1: modify to adapt to rails Sta 2N & 3N: Internal to MMN only. Adapt to work with most lampshades on. Sta 2S & 3S: TBD

9/6/2007 Weekly Planning Meeting RPC Factory Work is continuing. Please make sure that all work in 912 is properly planned and approved.

9/6/2007 Weekly Planning Meeting A. Factory Set Up: 1. PHENIX tech support: Gas: John T. Elect: Frank T. Mech: Kenny J. 2. Electrical work moving complete ~9/5. 3. floor to be painted after elec. In progress 4. HVAC specs 18,000 BTU AC (not ordered yet) 4 HEPA filters, internally recirculated (done) 5. Gas distribution design in progress start installing next week B. Safety Issues: Per Yousef’s Minutes from review RPC Factory Issues Calib./testing of SF6 monitors Gas system schematic in progress Fire protection piggy backed on 912 alarms. Replace tarps with fire rated hole covers Gas environmental impact Ralf update review numbers when gas system design is complete Electronics/equipment review Factory users safety manual interim Worker plan complete; final productiuon version needed C. Other Ali needs map showing internet and phone locations. Need sketch for outside gas bottle lean-to

9/6/2007 Weekly Planning Meeting RXNP Repair Bum phototube replaced

9/6/2007Weekly Planning Meeting MuTr FEE Upgrade Prototype Last week – Cooling water and dry air in station 2 (Thu) – Flammable gas safety permission in progress (Thu) – Isobutane start flowing (Thu) – 24h shift started from Thursday. – DAQ studies (Thu-Sat)

9/6/2007 North Arm, Station 2 Station 2, bottom octant, middle gap, non-stereo plane 5 AD boards & 5 TX boards Cooling water & Dry air (Thu) 11 AD boards TX boards MuTr Chamber

9/6/2007 Installation to station 1, bottom octant, middle gap, non- stereo plane completed 3 AD boards & 3 TX boards 12 North Arm, Staion 1 AD boards TX boards MuTr Chamber

9/6/2007 Merger board (MRG) Two MRG boards were installed near the MuID ROC north TX outputs x 3 CLK in Outputs to MuID ROC

9/6/2007 Cosmic data, first shot Cosmic ray data – Trigger : MuID LL1 + MuID BLT – Rate : ~650 Hz Digitized data from MuTr were successfully recorded. Time structure of the MuTr signal is being studied by scanning Level 1 latency. LV1 Latency-28 (Beam clock) N(MuTr)/Trigger Station 2 Octant 7 Half Oct 1 Station 2 Octant 7 Half Oct 2 Station 1 Octant 7 MuTrFEE DCM

9/6/2007 MuTr FEE analog signal events (~1% of run) at optimal latency Analysis by K. Karatsu Charge (arbitrary unit) Events No selection w/ AD signal

9/6/2007 Schedules Total 150 M triggers were accumulated – ~250k cosmic events/octant – Goal : 600 k cosmic events/octant Evaluation of efficiency, position resolution, time resolution Stat. uncertainty <~3% Run plans – Accumulation of cosmic data till Sep. 12 morning – End station 1 data taking after Sep. 10 (to accommodate de-capacitor work by LANL group) – Uninstallation : Sep

9/6/2007 Required resources Gas – CF4 (MuTr) – Isobutan (MuID) Cooling water and dry air – station 2 Electricities – HV (MuID, MuTr, RxNP) – LV (MuID, MuTr, RxNP) DAQ – Standalone calibration – Big partition MuTr + MuID + (RxNP) – Disk space Buffer box 6 Need to change before weekend Computing resources – VA machines (va061-69) – Data transfer to HPSS and CCJ

9/6/2007 Weekly Planning Meeting Mu Trigger Station 1 and 2 Upgrades

9/6/2007 Weekly Planning Meeting Mu Trigger Station 1 and 2 Upgrades We plan to make a couple of mockups of the AD and TX boxes to test fit in potential station 1 locations

9/6/2007 Weekly Planning Meeting Other Work Empty (except clean metal waste) and discard old container NCC prototype & electronics Mike L. & Richie VTX prototype aluminum support strips needed for flimsy plexi test box - Done Neutron shielding test (4’ x 4’ x 2” borated polyethylene Shield support design in progress Install in September for Run 8 tests

9/6/2007 Weekly Planning Meeting Safety/Security Notes: Lab Director Directive on “PPE”: wearing non-complying attire (such as shorts, short sleeve shirts, and other garments that leave arms and legs exposed) in the laboratory, shop, and industrial work areas of the Laboratory. : “I am directing that this practice be discontinued immediately and the requirements of SBMS be enforced by all levels of supervision. This is applicable to all BNL people – employees, guests, contractors, students, etc – all who work or visit such areas.” C-A has interpretted this to mean long pants and long sleeve shirts everywhere but offices and lunchrooms. 912 tent work must comply. PHENIX interpretation: IR and AH require long sleeves and long pants. Elsewhere at 1008 is office space. A Significance Category (SC) 3 occurrence was declared today (09/05/07) at 10:15 AM as a result of the following event: On Thursday, August 30, 2007 at approximately 6:00 P.M., a biologist was working in a bacteriology hood in Bldg 463, Rm. B-134-C. While using a bunsen burner to facilitate transfer of cells to media, the wrist portion of the biologist disposable labcoat came into contact with the burner flame and ignited. The flame on the labcoat was immediately extinguished and the labcoat removed before any melting material came in contact with skin. There was no injury to the biologist.

9/6/2007 Weekly Planning Meeting 5 Year Plan 2007 HBD Repairs, DC (minor) repairs), MPC N&S upgrade,MuTr FEE upgrade prototype, infrastructure upgrades & repairs, misc. subsystem work 2008 MuTr FEE upgrades 1 octant 1&2 S, Cu absorber test, RPC3 S, infrastructure upgrades & repairs, misc. subsystem work 2009 Scaffolding in MMS and MMN, MuTr FEE N&S stn. 2 & 3, MuTr N&S stn. 2 & 3 repairs, RPC2 S&N, RPC3 N, Cu absorbers, infrastructure upgrades & repairs, misc. subsystem work 2010Remove HBD & RXNP, remove beampipe, DC West upgrade, VTX barrel, RPC1 N&S, MuTr FEE stn. 1 N&S, MuTr stn. 1 N&S repairs, infrastructure upgrades & repairs, misc. subsystem work 2011NCC S, FVTX, infrastructure upgrades & repairs, misc. subsystem work 2012NCC N, upgrades contingency & wishlist, infrastructure upgrades & repairs, misc. subsystem work * Years refer to the shutdown year and follow the run with the similar number (i.e. work in 2007 is to be done in the shutdown that follows run 7, and so on)

9/6/2007 Weekly Planning Meeting Links for the weekly planning meeting slides, long term planning, pictures, videos and other technical info can be found on the web site: Where To Find PHENIX Technical Info A Belated sentiment