WECC Composite Load Model WECC MVWG Meeting Bellevue, WA August 25, 2011
Motion Approve the implementation plant for replacing the “interim” load model with a Phase 1 “composite” load model Use default data sets Residential air-conditioner stalling disabled* * No revision of the WECC reliability criteria is needed
Composite Load Model Development
Load Modeling In the first 40 years of digital simulations, the focus was on modeling the supply side We have reasonably good power plant models Models data is to get more consistent as more plants have digital controls We have tools for power plant model validation using disturbance data Now, the focus is shifting on modeling the supply side
Load Modeling Upcoming big changes on demand-side: Loads will play much more influential role in power system stability Resistive-type loads are phasing out (incandescent lights and resistive heating) Energy inefficient but exhibit “grid-friendly” behavior Power Electronic loads, VFDs, AC compressors, heat pumps, CFLs, LEDs are gaining their presence Energy efficient but have undesirable characteristics from standpoint of dynamic stability Increasing penetration of residential air-conditioners Upcoming big changes on demand-side: Electric vehicl chargers Distributed generation Reasonable models are needed to understand the system impacts of these changes, to plan and operate the system and to develop appropriate standards
Load Modeling – Setting Expectations We can now achieve the great accuracy with generator models: We model physical equipment that is well defined and under our control We will never be able to achieve a comparable level of accuracy with load models Load models will not be able to predict details Load models should be capable of representing the load response in principle
WECC Load Modeling Philosophy WECC uses a physical-based modeling approach: Bottom-up model development Develop models that represent physics and characteristics of the actual end-use components Top-down model validation Validate and calibrate model data using disturbance recordings
History Of Load Modeling in WECC 1980’s – Constant current real, constant impedance reactive models connected to a transmission bus Reflected the limitation of computing technologies of that time 1990’s – EPRI Loadsyn effort Several utilities use static polynomial characteristics for load representation 1990’s – IEEE Task Force recommends dynamic load modeling The recommendation does not get much traction in the industry 1996 – BPA model validation study for August 10 1996 outage: Need for motor load modeling to represent oscillations and voltage instability
History Of Load Modeling in WECC 2000 – 2001 – WECC “Interim” Load Model: Presently used in planning and operational studies in WECC 20% of load is represented with induction motors, the remaining load is static, mainly constant current active, constant impedance reactive components Tuned to match inter-area oscillations for August 10 1996 and August 4, 2000 events “Interim” load model was intended as a temporary solution to address oscillation issues observed at California – Oregon Intertie The model limitations and the need for a composite load model were recognized
History Of Load Modeling in WECC Late 1980’s – Southern California Edison observed events of delayed voltage recovery attributed to stalling of residential air-conditioners Tested residential air-conditioners, developed empirical AC models 1997 – SCE model validation study of Lugo event: Need to represent a distribution equivalent Need to have special models for air-conditioning load
Southern California Edison Lugo Event – Load Modeling Lessons: A. Need to represent a distribution equivalent B. Need to have special models for residential air-conditioners
Load Modeling Efforts in the East 1994 – Florida Power published an IEEE paper, used a similar load model 1998 – Events of delayed voltage recovery were observed in Atlanta area by Southern Company, the events are analyzed and modeled Southern Company and Florida Power used in principle similar approaches to SCE’s and eventually WECC model
WECC Load Modeling Task Force 2005 – WECC developed “explicit” load model: Adding distribution equivalent to powerflow case (PG&E) Modeling load with induction motors and static loads Numerically stable in WECC-wide studies ! 2007 – PSLF has the first version of the composite load model (three-phase motor models only) 2006-2009 – SCE-BPA-EPRI testing residential air-conditioners and developing models 2009 – residential air-conditioner model is added to the composite load mode
WECC Load Modeling Task Force Composite Load Model Structure Default data sets Load composition Load component data Distribution equivalent Tools for data management Validation studies System impact studies
WECC Composite Load Model (CMPLDW) 12.5-kV 13.8-kV M 69-kV 115-kV 138-kV M AC UVLS Electronic UFLS Static
Composite Load Model Structure Composite load model structure is implemented in General Electric’s PSLF, Siemens PTI PSS®E, Power World Simulator Similar model exists in PowerTech’s TSAT TSS approved Composite Load Model Structure
Load Model Data
WECC Composite Load Model Load Component Model Data Distribution Equivalent Data M M 115-kV 230-kV M Load Model Composition Data M UVLS and UFLS Data Electronic Static
Distribution Equivalent Data M M R + j X 69-kV 115-kV 138-kV M M B1 B2 Bss Electronic DV = 4 to 6% X/R = 1.5 PL < 7% B1:B2 = 3:1 X = 8% LF = 110% Tap = +/- 10% Static
WECC Climate Areas ID Climate Zone Representative City NWC Northwest Coast Seattle, Vancouver BC NWV Northwest Valley Portland OR NWI Northwest Inland Boise, Tri-Cities, Spokane RMN Rocky Mountain North Calgary, Montana, Wyoming NCC Northern California Coast Bay Area NCV Northern California Valley Sacramento NCI Northern California Inland Fresno SCC Southern California Coast LA, San Diego SCV Southern California Valley SCI Southern California Inland DSW Desert Southwest Phoenix, Riverside, Las Vegas HID High Desert Salt Lake City, Albuquerque, Denver, Reno
Load Composition Information California Energy Commission: 2006 California Commercial End-Use Survey (CEUS) LBNL Reports on Electricity Use in California PNNL DOE2 building simulations BPA-PNNL End-Use Load Characterization Assessment Program (ELCAP) BPA Building Data Load shapes provided by WECC members
California Commercial End-Use Survey 15 climate zones in California Four seasons Typical, Hot, Cold, Weekend 24-hour data Data is available on CEC web-site bottom top
LBNL Electricity Use In California Study Residential AC Lighting Commercial AC
PNNL Load Composition Model CEC / BPA hired PNNL to develop load composition data Detailed models of various building types Residential loads are modeled using ELCAP data and DOE-2 models Commercial loads are taken from CEUS WECC developed mapping from end-uses to models
Load Class Model Components
Portland Metro Area – BPA SCADA
Portland Metro Area – BPA SCADA
WECC Load Composition Model There is a balance between precision and the amount of effort required to maintain the data sets Based on the understanding developed using PNNL tool, WECC developed a simplified LCM version to create default data sets Produces load composition data for summer (normal, peak, cool), shoulder (normal) and winter (normal) days
WECC Load Composition Model (Light)
Future work Better understanding of “electrification” by regions, and ultimately by substations Validation of building models Right now commercial data is extrapolated from California CEUS, and residential data is used from ELCAP Validation of load shapes at substation level: Use customer mix data and models to produce load shapes Validate the load shapes using SCADA data (5-min and 1–hour are available from BPAT)
Expert Help is Available If you want detailed load composition information for your specific area, please contact David Chassin at PNNL David.Chassin@pnl.gov Detailed analysis is currently done for substations in Seattle, Portland and Phoenix
Motor Data
Commercial Compressor Motor
Commercial Fan and Pump Motors
Commercial Fan and Pump Motors
Protection Industrial compressors: Industrial fans and pumps Trip and lock-out - half at 75%, half at 65%, 3 to 5 cycles Industrial fans and pumps Trip and lock-out - half at 75%, half at 65%, 3 to 5 cycles Commercial compressors Trip and lock-out: 20% of motors, trip < 60% 2 cycles Trip and reclose: remaining, trip < 50% 2 cycles , reclose > 60% for 0.2 sec Fans and pumps
Tools for Load Model Data Management
WECC Composite Load Model cmpldw 43085 "CANYON " 115.00 "1 " : #1 mva=63.18 "Bss" 0 "Rfdr" 0.032 "Xfdr" 0.04 "Fb" 0.749/ "Xxf" 0.08 "TfixHS" 1 "TfixLS" 1 "LTC" 1 "Tmin" 0.9 "Tmax" 1.1 "step" 0.00625 / "Vmin" 1.025 "Vmax" 1.04 "Tdel" 30 "Ttap" 5 "Rcomp" 0 "Xcomp" 0 / "Fma" 0.234 "Fmb" 0.157 "Fmc" 0.032 "Fmd" 0.103 "Fel" 0.136 / "PFel" 1 "Vd1" 0.75 "Vd2" 0.65 "Frcel" 0.35 / "Pfs" -0.99274 "P1e" 2 "P1c" 0.307692 "P2e" 1 "P2c" 0.692308 "Pfreq" 0 / "Q1e" 2 "Q1c" -0.5 "Q2e" 1 "Q2c" 1.5 "Qfreq" -1 / "MtpA" 3 "MtpB" 3 "MtpC" 3 "MtpD" 1 / "LfmA" 0.75 "RsA" 0.04 "LsA" 1.8 "LpA" 0.12 "LppA" 0.104 / "TpoA" 0.095 "TppoA" 0.0021 "HA" 0.05 "etrqA" 0 / "Vtr1A" 0.7 "Ttr1A" 0.05 "Ftr1A" 0.2 "Vrc1A" 1 "Trc1A" 9999 / "Vtr2A" 0.55 "Ttr2A" 0.03 "Ftr2A" 0.75 "Vrc2A" 0.65 "Trc2A" 0.1 / "LfmB" 0.75 "RsB" 0.03 "LsB" 1.8 "LpB" 0.19 "LppB" 0.14 / "TpoB" 0.2 "TppoB" 0.0026 "HB" 0.5 "etrqB" 2 / "Vtr1B" 0.65 "Ttr1B" 0.05 "Ftr1B" 0.1 "Vrc1B" 1 "Trc1B" 9999 / "Vtr2B" 0.6 "Ttr2B" 0.03 "Ftr2B" 0.1 "Vrc2B" 1 "Trc2B" 99999 / "LfmC" 0.75 "RsC" 0.03 "LsC" 1.8 "LpC" 0.19 "LppC" 0.14 / "TpoC" 0.2 "TppoC" 0.0026 "HC" 0.15 "etrqc" 2 / "Vtr1C" 0.65 "Ttr1C" 0.05 "Ftr1C" 0.1 "Vrc1C" 1 "Trc1C" 9999 / "Vtr2C" 0.6 "Ttr2C" 0.03 "Ftr2C" 0.1 "Vrc2C" 1 "Trc2C" 99999 / "LfmD" 1 "CompPF" 0.98 / "Vstall" 0.54 "Rstall" 0.1 "Xstall" 0.1 "Tstall" 0.03 "Frst" 0.14 "Vrst" 0.95 "Trst" 0.3 / "fuvr" 0.1 "vtr1" 0.6 "ttr1" 0.02 "vtr2" 0.9 "ttr2" 5 / "Vc1off" 0.5 "Vc2off" 0.6 "Vc1on" 0.4 "Vc2on" 0.5 / "Tth" 15 "Th1t" 0.7 "Th2t" 1.9 "tv" 0.025
LMDT 3A Powerflow case (done by SRWG) Climate zone and load type are identified in “Long_ID” column of “load” table in PSLF E.g. DSW_RES = Desert Southwest, predominantly residential loads EPCL Programs (done by WECC Staff) Default data sets for each climate zone and feeder type Ability to over-ride defaults with specific information Creates composite load model records for PSLF PTI PSS®E Users Convert from PSLF models IPLAN tolls may be available ? Load models will be distributed by WECC staff with study cases LMDT 3A is posted on WECC web-site, including user’s manual
Load Model Validation Studies
August 4, 2000 Oscillation - CMPLDW
August 4, 2000 Oscillation - MotorW
August 4, 2000 Oscillation - CmpldW Default Data Set
August 4, 2000 Oscillation - CmpldW Tuning
June 14, 2004 Westwing Fault - CmpldW
July 28, 2003 Hasayampa Fault
July 28, 2009 Mid-Valley Fault Voltage Frequency
System Impact Studies
2011HS – Chief Joseph Brake Blue = MotorW Red = CmpldW phase 1 Green = CmpldW phase 2
2011HS – BC-Alberta Loss (546 MW) Blue = MotorW Red = CmpldW phase 1 Green = CmpldW phase 2
2011HS – 2 Palo Verde Outage Blue = MotorW Red = CmpldW phase 1 Green = CmpldW phase 2
2011HS – 2 Palo Verde Outage Blue = MotorW Red = CmpldW phase 1 Green = CmpldW phase 2
2014LS – Montana Blue = MotorW, 77% dip Green = CmpldW, 22:00, 82% dip Brown = CmpldW, 6:00, 82% dip
2014LS – Montana Blue = MotorW Red = CmpldW, Grey/Green = CmpldW, improved exciters at a hydro plant
Next Steps
Conclusions WECC Composite load model is implemented in GE PSLF, Siemens PTI PSS®E, Power World, Power Tech TSAT Tools are developed for load model data management Default sets are developed: 12 climate zones in WECC, four types of feeders Summer, winter and shoulder conditions
Conclusions Validation studies are done for FIDVR events and oscillations System impact studies Significant impact on faults in large load centers FIDVR Impact on inter-area oscillations
FIDVR Composite load model is capable of reproducing the FIDVR phenomenon Composite load model can be tuned with reasonable data sets to match the historic events MVWG at this point is not comfortable recommending using CMPLDW for FIDVR studies for compliance purposes There is a concern that the FIDVR modeling can result in over- investment or unnecessary operational restrictions
FIDVR – Planned Work Continue work on understanding the phenomenon of air-conditioner stalling in distribution systems (supported by DOE) Work with AHRI Feeder simulations Speed up efforts on collecting disturbance recordings SCE, SRP, Center Point Energy, PSE, BPA/PGE A letter was sent to grid operators in the East Tools for detecting FIDVR events in PMU data
CMPLDW – Phased Approach
CMPLDW CMPLDW has many benefits beyond FIDVR TSS delayed PSS Policy review until appropriate load models are developed Frequency response review studies are required
CMPLDW Plan Today – Approve the implementation plan for adopting Phase 1 CMPLDW for system studies Continue improvement of FIDVR modeling Disturbance recordings, system impact studies Start using the CMPLDW for studies to support the review of the WECC voltage dip criteria Seek the approval of the “CMLDW with FIDVR enabled” and the new reliability criteria by Fall 2012
Motion Approve the implementation plant for replacing the “interim” load model with a Phase 1 “composite” load model Use default data sets Residential air-conditioner stalling disabled* * No revision of the WECC reliability criteria is needed