Northwest ISD Lakeview Elementary School Additions and Renovations Lakeview Elementary School Additions and Renovations
Lakeview Elementary Additions and Renovations Improve Drop Off and Pick-up Areas Addition of Eight (8) Classrooms Additional Kindergarten and Staff Restrooms Additional Storage Renovate Existing Library into a Collaboration Area Addition of a New Library Expanding/Renovating the Gym New Cafeteria Connected to the Gym Relocation of New Art and Music Rooms Additional 61 Parking Spaces Upgrade to Security, Technology and Announcement Systems Roof Replacement on original building Carpet replacement ADA upgrades to the Building and playground Added square feet : 31,000+ Renovated Area: 53,000+
When?
Beginning During the Upcoming Holiday Break I.A temporary wall will be built in the gymnasium to separate the construction area. II.Both playground areas will be closed. A play area will be fenced off on the west side of the school in lieu of the playgrounds (soccer fields direction). III.Five (5) classrooms will be relocated internally. IV.One temporary classroom will be constructed in the library. V.The east parking lot (day-care side) will be fenced off and closed during construction. VI.The south parking(front parking lot) lot will be expanded.
What will I see after the Holiday Break? I.All parent drop-off and pick-up will be in the front parking lot. II.Bus pick-up will be in the front of the school. III.Five (5) classrooms will have been relocated to release parts of building for construction. IV.A new temporary classroom will be located in the library. V.Construction additions will be in full force outside of the school building.
Construction Phasing PHASE I : Front and Back Building Additions Exterior additions of 4 Classrooms, Storage, Gym, Café -back December 2012 – July 2013 PHASE II : Front Classrooms Addition Exterior additions of 4 classrooms to the building - front Library to the building - front March – July 2013 PHASE III : Renovations Interior renovations and alterations to the design and use of existing interior Summer 2013
Temporary Playground Phase I December July 2013 Phase I December July 2013 Phase III June 2013-July 2013 Phase II March July 2013 Phase II March July 2013
Phase I December July 2013 Phase I December July 2013 Relocation of 5 classrooms internally Rooms 102, 404, 405, 406 & 507
Phasing I Phase I
PHASE I Relocation Plan
Phase II March-- July 2013 Classrooms vacated in phase I will be available for use to accommodate rooms 307, 308, 803 & 806 which will be unoccupied for Construction
Phase II Relocate Portables
PHASE II Relocation Plan
Internal Renovations and Upgrade. Phase III Summer 2013
Interior Renovations for Lakeview Elementary
Lakeview Elementary Traffic Flow During Construction Back Parking Lot will be Closed Utilize the Bus Services, if available Car Pool All Drop-off and Pick-up will be in the Front Parking Lot Double Rows for Parent Pick-up Line Park in Street, Walk to School
Morning Drop-Off Procedures Look for students walking on Drive. Be patient. Watch for Buses. Listen to staff instructions. Drop off in front Parking Lot.
LINE Buses will be unloading and Departing BUS ALL TRAFFIC RIGHT TURN ONLY Under Constr uction
Afternoon Pick-Up Procedures Buses will park in front Drive. Once buses are in place, cars will form double rows in the front parking area. NISD staff is working with Town P.D. for the assistance in traffic changes. Vehicles will make right Village Trail.
CLOSED Parallel Parking Along Village Trail Lakeview Traffic Beginning January 2013 During Pick Up
BUS LINE Buses will be Loaded and Depart First Followed by the Parent Pick-up Line BUS ALL TRAFFIC RIGHT TURN ONLY Under Constr uction
How will the traffic flow change after construction is complete?
Lakeview Elementary Traffic Flow Comparison Currently, there is room for 57 cars in the front drive. Will increase to 118 cars in front drive and north parking lot. Lengthier Pick Up Line for Parents at the front and back
Visit Lakeview Elementary School Website www. NISDTX.org Select Announcements then Construction Updates Q&A Construction FAQs
Construction Related Contract Information Sarah Stewart, NISD Construction Manager Mark Leatherwood, Balfour Beatty Construction Job Superintendent Ben Reiners Balfour Beatty Construction Project Manager, Mehran Aghili, NISD Executive Director of Construction Sarah Stewart, NISD Construction Manager Mark Leatherwood, Balfour Beatty Construction Job Superintendent Ben Reiners Balfour Beatty Construction Project Manager, Mehran Aghili, NISD Executive Director of Construction
Northwest ISD Lakeview Elementary School Additions and Renovations Lakeview Elementary School Additions and Renovations