Start Counter Construction Update Eric Pooser 08/21/2014.

Slides:



Advertisements
Similar presentations
n-DVCS/E status report
Advertisements

Some cryostat scintillator slides for Monday’s meeting Michigan State University.
Collaboration Meeting, Oct : Start Counter Start Counter Eric Pooser W. U. Boeglin L. Guo P. Khetarpal Experimental Setup SiPM Scan Attenuation Lengths.
Muon g-2 Muon g-2 Experiment Quarterly Report Aria Soha All Experimenter’s Meeting March 2, 2015.
Detector Systems Update MICO March 17, MICE Detector Systems  CKOV u Mississippi RAL  TOF0/1 u Hamamatsu PMT assemblies show an increasing.
Takashi Matsushita Imperial College T. Matsushita 1 Station 5.
Prototype Status. 2 Status Update Safety Cage arriving soon Safety Cage arriving soon Torque transducer up and running Torque transducer up and running.
Spectrometer Solenoid Fabrication Update Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 14, 2009.
G.Barber Tracker Update, Berkeley 10 Feb Tracker Progress Contents:- Station Space Frame Patch Panel / Vacuum Seal Light Guide Map Position of Degrader/Support.
EMCal Meeting CERN – July 2 nd 2007 LPSC Status 1 J-F Muraz LPSC Status LPSC Status.  Assembly Hall. - Removal starts and is in progress. - Main infrastructure.
Lab5 Production Status: Optics and RBX integration Pawel de Barbaro U. of Rochester.
Target Controller Electronics Upgrade Status P. Smith J. Leaver.
Status of CLAS12 PCAL project
PXL Electronics Status update for HFT TC meeting on May 11, 2010 at LBNL 1HFT TC 05/11/ LG.
WP7&8 Progress Report ITS Plenary meeting, 23 April 2014 LG, PK, VM, JR Objectives 2014 and current status.
M. Bonesini - MICE CM18 RAL 16/06/071 M. Bonesini INFN Milano Updates on TOF project.
CLAS12 CalCom Activity: a progress report V. Burkert, D. Carman, R. De Vita, D. Weygand CLAS12 meeting, February 22 nd 2012.
Helene Felice HQ02 Assembly status 02/28/2012. HQ02 layout COIL 16COIL 15 COIL 17COIL 20 VIEW LOOKING AT LEAD END A C BD Sector A Sector B Sector C Sector.
TMDB delay and production plan Augusto. TMDB Prototype Status The prototype boards almost fully assembled should be delivered this week ( May 5 th ) First.
Office of Science Coupling Coil Status S. Gourlay August 1, 2012.
Oct C. Smith - PCAL/EC Commissioning 1 PCAL/EC Commissioning Document
L. Greiner 1IPHC meeting – May 7, 2012 STAR HFT Plans for the next year A short report on HFT/PXL plans for post May 2012 TPC – Time Projection Chamber.
Telescope Integration and Tests Tuesday Afternoon.
G.Barber KEK Test Beam Update, Berkeley 9 Feb KEK Test Beam – Tracker Progress Contents:- Station Space Frame Light Guide Map Station Connectors.
DVCS-2 Assembly & Installation Charles Hyde DVCS Collaboration Meeting 18 December 2009 Clermont-Ferrand.
Tracker Summary Alan Bross MICE CM October 10, 2007.
Ronald Lipton PMG June Layer 0 Status 48 modules, 96 SVX4 readout chips 6-fold symmetry 8 module types different in sensor and analog cable length.
CHANTI update F. Ambrosino, T. Capussela, D. Di Filippo, P. Massarotti, M. Mirra, M. Napolitano, L. Roscilli, G. Saracino.
LNF activities on WPC Panels Construction of prototypes and layout Status of tooling Proto 0, open items, plan,...
PFP Instrument Status All PFP Instruments Except SWEA have been delivered, integrated, and tested; supporting environmental tests Issues: –EUV alignment.
1M. Ellis - NFMCC - 31st January 2007 MICE Tracker.
M. Bonesini - MICE Inst Meeting M. Bonesini INFN Milano TOF installation plans.
VVS Prototype Construction at Fermilab Erik Ramberg 26 February,2002 Design issues for VVS Details of VVS prototype design Schedule and Budget Testing.
ECAL Lab measurements: summer plans What we have – Fully functionnal scan setup with electron gun – 2 batches of 4 scintillators (already scanned) 4x 15x15.
MICE RF Cavities and RFCC Module Update Allan DeMello and Derun Li Lawrence Berkeley National Laboratory MICE CM32 at RAL, UK February 9, 2012 February.
9 September 2004The Straw Tube Chamber1 The CDC Curtis A. Meyer Carnegie Mellon University Physics Requirements and Specifications Prototype Construction.
Update on Module Mounting on Staves and Stavelets 25/8/11 1.
M. Brooks DC Meeting, 15-Sep-00 MuTr Mechanics Status SOUTH ARM: Chambers fabrication complete Stations 2+3 installed Station 1 test-installed will be.
Update on the GRINCH Detector SBS meeting, 21 Oct 2015 T. Averett, W&M JLab, NC A&T, JMU, Glasgow Timing-based gas Cherenkov detector PMT array-510 tubes.
CERN adb Chamber Support Structure Installation MUON SYSTEM INTEGRATION MEETING - Status of Production of support panels - Things to be settled.
LBT Q Engineering Review SAB Static Balancing.
1/10/2016Collaboration Meeting Feb 2011 Start Counter 1 Start Counter Update W. U. Boeglin L. Guo E. Pooser Measurements on EJ-212 scintillator bars Attenuation.
PRad Recent Achievements 1)PRad Implementation (“Position”) document developed and submitted to Jlab. 2)Jlab’s Director Office scheduling review passed.
L. Greiner1IPHC-LBNL Phone Conference 05/2012 STAR IPHC-LBNL Phone Conference News and updated ladder testing.
1 Integration and Milestones Elton Smith Hall D Detector Review October 20-22, 2004.
1 HBD: Update and Schedule Itzhak Tserruya DC Meeting, BNL, April 13, 2005 Outline:  Full scale prototype status  Light source test  Construction Schedule.
Lavs Issues Lav 12. Tube Planning future activities. Conclusions.
Update on the HBD Craig Woody BNL DC Meeting May 11, 2005.
MICE Prototype Coupling Coil Fabrication Update Allan DeMello Lawrence Berkeley National Laboratory MICE CM38 - Napa California February 25, 2014 February.
L. Greiner1IPHC-LBNL Phone Conference 07/10/2012 STAR IPHC-LBNL Phone Conference News and updated ladder testing.
EMCal Meeting Nantes – July J-F Muraz  Grenoble Status  Assembly and test Hall.
Tile HCAL status Felix Sefkow CALICE Technical Board Review April 19, 2007.
CLAS12 – CND PARAMETERDESIGN VALUE Detector typeBarrel of scintillators Angular coverage40 o to 120 o Number of radial layers3 Number of azimuthal segments48.
EMCAL Calibration & Assembly at Yale University Mark Heinz, Project Mgr EMCAL Meeting Nantes July 15, 2008.
Preparations to Install the HBD for Run 6 Craig Woody BNL PHENIX Weekly Meeting January 26, 2006.
IRC/SAC status Venelin Kozhuharov for the SAC/IRC working group NA62 Meeting
Status of the NOνA Experiment Satish Desai - University of Minnesota For the NOνA Collaboration APS Meeting - April 2013 Denver, Colorado.
MICE Coupling Coil Update Allan DeMello Lawrence Berkeley National Laboratory Illinois Institute of Technology June 17, 2013 June 17, 2013.
Status of NEWCHOD E.Guschin (INR), S.Kholodenko (IHEP), Yu.Kudenko (INR), I.Mannelli (Pisa), O.Mineev (INR), V.Obraztsov (IHEP), V.Semenov(IHEP), V.Sugonyaev.
H. Weick, 8 th MAC meeting, GSI, Super-FRS Status Target Area H. Weick / M. Winkler 8th FAIR - Machine Advisory Committee Meeting
RF Module Update MICE Collaboration Meeting 44 Andrew Lambert Lawrence Berkeley National Laboratory March 30 th, 2016.
MICE Coupling Coil Vacuum Vessel Fabrication Update Allan DeMello Lawrence Berkeley National Laboratory Coupling Coil Working Group January 28, 2014 January.
RFCC Engineering Status and Plans Allan DeMello Lawrence Berkeley National Laboratory MAP Winter Meeting March 6, 2012 March 6, 2012.
Cryomodule Interconnect Installation Issues A Comparison of XFEL to LCLSII Karen Fant 7/29/2015.
USTileCal Planning UTA ITC Scintillator Project R. Miller May 13, E3 C10 B11 E1 D5 A14 - A15 B14 D6 A D4 A12 A13 B12 - B
LIU Wire Scanner Milestones June 2017
Step IV PRY Preparation - Contents
first light! new laser driver board (revD)
Signal Conditioning.
Prototype cryomodule development
Presentation transcript:

Start Counter Construction Update Eric Pooser 08/21/2014

Current Status The 30 best scintillators have been selected and fully tested Rohacell support has been painted black and all gaps have been filled with black caulking Shimming height has been determined (some materials are yet to be delivered) – We require approximately 30 mils (762 um) of shimming – Material is Kapton polyimide heavy duty film (type HN ρ = 1.42 g/cc) – All ST1 PCBs have been positioned so that all paddles require approximately the same shimming height of 30 mils (20 mil < shim < 40 mil) Final construction of the Start Counter is underway

Wrapped Prototype Results

Wrapped Prototype Results (continued)

Results of Best 30 Paddles Wrapped

Results of Best 30 Paddles Wrapped (continued)

Calibration Measurement (3.02 mm)

No Shimming (786 um)

10 mil Shimming (507 um)

20 mil Shimming (254 um)

25 mil Shimming (152 um)

30 mil Shimming (Best Possible Alignment)

Future Plans Fully Assemble Start Counter by Friday (08/22/2014) – This includes shimming and sub 200 um coupling Next Week: – Wrap Start Counter with 80 gauge (0.8 mil) Bundling Wrap – Finalize Start Counter Construction – Verify all 30 channels are able to be read out Use 90 Sr source to verify that all signal sizes are identical Prepare Start Counter for transportation to Jlab Ship MPOD, cables, and tools back to Nick Deliver Start Counter to Jlab 09/02/2014

Topics for Discussion Documentation for delivery of Start Counter Schedule upon arrival at JLab (09/02/2014) – Light tightening – Testing of read out channels – Mounting to target – Survey & Alignment – Installation into Hall – Commissioning/Calibration