Fermilab Vertical Cavity Test Facility (VCTF) VTS2&3 Project Status Ruben Carcagno, Camille Ginsburg, and Cosmore Sylvester On behalf of the VTS Group.

Slides:



Advertisements
Similar presentations
Executive Session Director’s CD-1 Follow-Up Review of the APUL Project November 2-3, 2009 Dean A. Hoffer.
Advertisements

Superconducting Spoke Resonator Cavities and Cryomodules
1 LHC-DFBX Procurement Strategy Joseph Rasson LBNL Presented at the DFBX Production Readiness Review October 2002, LBNL Brookhaven - Fermilab - Berkeley.
Coupling Coil Test Facility Update Ruben Carcagno Fermilab September 20, 2012.
Alderman Road Residences Phase II Design Build. Extensive master planning preceded this phase 2003 – Dagit Saylor Master Plan Hanbury Evans Update.
Process Engineer’s Role in Project Management Dr Abdullah Malik.
An SRF Single Cavity Horizontal Test Facility Tom Peterson, Fermilab May 10, 2005.
MEBT & RT CH Section Thomas Page Fermilab Accelerator Advisory Committee May 10 th – 12 th, 2006.
US Cavities Status and Plan Mark Champion 01 October 2009.
Linac Front-End R&D --- Systems Integration and Meson Lab Setup
Project X RD&D Plan Conventional Facilities (Civil Construction) Russ Alber AAC Meeting February 3, 2009.
Server Virtualization: Navy Network Operations Centers
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
CERN LBNE Test Experiment. Plan view of Bat
Overview of the ILC and SRF Program (With an emphasis on Px) Shekhar Mishra ILC & SRF Program Fermilab.
Vertical Test Stand Update C.M. Ginsburg (Fermilab) For the VTS group: C.Sylvester, Y.Huang, R.Nehring, J.Ozelis, T.Peterson, V.Poloubotko, R.Rabehl, I.Rakhno,
NCSX Management Overview Hutch Neilson, NCSX Project Manager NCSX Conceptual Design Review Princeton, NJ May 23, 2002.
BROOKHAVEN SCIENCE ASSOCIATES National Synchrotron Light Source II Project Management Jim Yeck NLSL II Deputy Director (Project Management)
7/26/2006 Wyatt Merritt 1 DECam Preparations for Critical Decision 2/3a Preparations for CD2 Preparations for CD3a DECam MOUs.
Executive Session Director’s CD-3b Review of the MicroBooNE Project January 18, 2012 Dean Hoffer.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
Hydrogen system R&D. R&D programme – general points Hydrogen absorber system incorporates 2 novel aspects Hydrogen storage using a hydride bed Hydrogen.
Vertical Test Stand in IB1 C.M. Ginsburg (Fermilab) for the IB1 VTS Group SRF R&D Meeting 6.July 2006.
October 4-5, Status of ARRA funded AIPs Electron Lens Scope, Cost, and Schedule Wolfram Fischer October 4, 2010 Electron Lens.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
ILCTA_IB1_VTS An in-ground vertical test facility for ILC SRF cavities at Fermilab Camille M. Ginsburg ILC SRF Technical Status Meeting 5.May 2006 for.
Hall 180 Cryogenic test facility: Project management: Project Change Request, EVM and Interface Sheet L. Serio.
7/26/2006 Wyatt Merritt 1 DECam CD1 Documentation DOE Critical Decision Process Documentation Requirements.
Americas Region: T4CM Status and Plans H. Carter TD SRF Dev. Dept. July 14, 2006.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
Harry Carter – LCFOA Meeting 5/1/06 1 LCFOA Technical Briefings: Cryomodules H. Carter Fermilab Technical Division.
Americas Main Linac Cavity and Cryomodule WBS X.9 Resource Proposal.
Fermilab IB1 Vertical Test Stand Update C.M. Ginsburg (Fermilab) for the VTS group August 31, ft.
DUSEL Beamline Working Group Meeting March 09, :00 AM – Snake Pit (WH2NE) By Dean Hoffer - OPMO.
Project X RD&D Plan Cryogenics Arkadiy Klebaner AAC Meeting February 3, 2009.
22 October 2005MICE Meeting at RAL1 Tracker Solenoid Overview Michael A. Green Lawrence Berkeley Laboratory MICE Collaboration Meeting 22 October 2005.
Industrial Participation & SRF Infrastructure at Fermilab Phil Pfund with input from Harry Carter, Rich Stanek, Mike Foley, Dan Olis, and others.
Proton Driver Resources & Schedule (R&D Plan) Rich Stanek May 10, 2005.
Power Upgrade Project SNS September 21-22, TBM Cost Estimate Cost Estimate Schedule Approach Tom Mann October 27, 2005.
4/27/06 1 US LHC ACCELERATOR RESEARCH PROGRAM brookhaven - fermilab – berkeley - slac US LARP Inner Triplet Cryogenics and Heat Transfer LARP Collaboration.
HiLumi-LARP Annual Meeting November 2014 MQXF pre-series and series magnets fabrication plans Ruben Carcagno November 19,
PIP-II Cryogenics Arkadiy Klebaner and Jay Theilacker PIP-II Collaboration Meeting 9 November 2015.
LCLS-II Prototype Cryomodule Vacuum Vessel and HGRP Tom Peterson 4 December 2014 Design Review.
CMTF Cryogenics (status and plans) SRF program and AD/Cryogenics work presented by Arkadiy Klebaner May 21, 2013.
DOE Review of LARP – Feb 17-18, 2014 DOE Critical Decision Process Ruben Carcagno February 17,
F ILC/SRF Strategic Planning OHAP Rich Stanek September 17, 2009.
Main Linac Technology (MLT) Meeting To be held through WebEx July 13, 2007.
MICE Coupling Coil Test Proposal Ruben Carcagno Fermilab July 9, MICE CC Test Proposal7/11/2011.
Shrikant_Pattalwar ICEC 26, March 7-11, 2016, Delhi 1 Horizontal Tests in a Vertical Cryostat Shrikant Pattalwar STFC Daresbury Laboratory UK.
1 Project X Workshop November 21-22, 2008 Richard York Chris Compton Walter Hartung Xiaoyu Wu Michigan State University.
9-cell cavity coordination CM Ginsburg 15 Mar
PXIE Layout and Infrastructure Building, Cryogenics, Utilities… Rich Stanek On behalf of the CMTF Team PXIE Collaboration Meeting November 28, 2012.
February 13, 2007C.M. Ginsburg (Fermilab-TD)1 Fermilab Vertical Test Facility for ILC cavities Vertical Cavity Test Facility (VCTF) IB1 infrastructure.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
International Collaborations: DAE-DOE Discovery Science Collaboration Shekhar Mishra, PIP-II MAC Review March 9-11, 2012.
Development of Cryo-Module Test Stand (CMTS) for Fermi Lab (R.L.Suthar, Head,CDM, BARC) Cryo-Module Test stand (CMTS) is a very sophisticated equipment.
Cryomodule Safety Approvals Jay Theilacker LCLS-II Production Cryomodule Final Design Review May 12-14, 2015.
650 MHz Cryomodule -- Discussions at RRCAT October 2010 Tom Peterson, with Harry Carter, Camille Ginsburg, and Jim Kerby 19 Nov 2010.
Fermilab-India Agreements and Collaboration Shekhar Mishra Project-X, International Collaboration Coodinator Fermi National Accelerator Laboratory Batavia,
Cavities, Cryomodules, and Cryogenics Working Group 2 Summary Report Mark Champion, Sang-ho Kim Project X Collaboration Meeting April 12-14, 2011.
ESS Program Plan and Schedule Update
WP High Beta Cavities Delivery
Plans towards CC in the LHC a US – centric perspective
Crab Cavities Contribution from the U.S.
Progress and Issues with VTS Upgrade
MICE CM31 Schedule summary
ILC Cryogenics -- Technical Design Report Planning
Presented by: Ruben Carcagno
SNS-PPU upgrades the existing accelerator structure
SuRf Lab: (STFC) VTF Infrastructure and Process
Presentation transcript:

Fermilab Vertical Cavity Test Facility (VCTF) VTS2&3 Project Status Ruben Carcagno, Camille Ginsburg, and Cosmore Sylvester On behalf of the VTS Group August 31, 2009

31.Aug, 2009SRF Mtg2  Cavities to accommodate  ILC/SRF R&D  9-cell and 1-cell elliptical ILC cavities  HINS/Project X  SSR1  SSR2  TSR  9-cell elliptical cavities  Conclusion  VTS1 is sufficient to support FY09, FY10 test plans  VTS2 with larger diameter operational by ~Dec to support increased throughput and SSR2, TSR as needed  VTS3 needed by ~Sep  Our Plan: New design with Indian Institutions for VTS2&3  Build VTS2 in U.S. Industry  Build VTS3 slightly later in Indian Industry with same design VCTF Upgrade Cavity Requirements Do not fit in VTS1 Total ~200 VT/year

31.Aug, 2009SRF Mtg3 VTS2&3 Cavity Requirements Provisions for testing the following types of cavities are required: 1.bare 1-cell 1.3 GHz elliptical cavities 2.bare 9-cell 1.3 GHz elliptical cavities 3.dressed 9-cell 1.3 GHz elliptical cavities, with helium gas return pipe absent 4.bare 325 MHz single-spoke resonator SSR1 5.bare 325 MHz single-spoke resonator SSR2 (preliminary design) 6.bare 325 MHz triple-spoke resonator TSR (preliminary design)

31.Aug, 2009SRF Mtg4 Projected cavity throughput Projected Americas total R&D cavity process/tests for Project X and the ILC. Projected Americas annual production process/test for Project X Note: SSR2 and TSR designs and requirements are preliminary. Cavity typeCavitiesVertical Tests 1-cell 1.3 GHz beta= cell 1.3 GHz, beta= SSR1, SSR2, TSR812 A. Rowe, DOE/SRF Review, 18 May Cavity typeVertical Tests 9-cell155 SSR1, SSR2, TSR40 Total (minimum)195

31.Aug, 2009SRF Mtg5 VCTF Upgrade  Increase cavity test throughput  Current throughput estimate: 48 cavity tests/year  Increase throughput to >200 cavity tests/year by Oct 2011  Planned upgrades  Improve cryogenic system reliability  Reduce interference with magnet test program  Two more cryostats and staging area existing cryostat & radiation shield Very similar to Feb.2007 plan

31.Aug, 2009SRF Mtg6 VCTF Throughput VCTF cavity test throughput per month for Oct.2007-Apr Throughput goal of 48 cavity tests per year has been achieved short-term under ideal conditions. Projected number of cavity tests per quarter, assuming the completion of the planned cryogenic system upgrades and the addition of two cryostats on the timescale shown.

31.Aug, 2009SRF Mtg7 VTS/IB1 FY09 Plans Plan to obligate funds in FY09 for VTS Upgrades (VTS2&3 plus cryogenic infrastructure upgrade) using ARRA + SRF funding Prepare space for new cryogenic equipment – ready FY09 Procure two purifiers, cryogenic piping & instrum, 1,500 KVA Transformer - FY09 IB1 civil construction for upgrades: two larger diameter pits plus trenches, dedicated 10-ton crane bridge –Place POs before end of FY09, civil construction summer FY09 –Very disruptive to cavity and magnet test programs (~ 6 weeks IB1 downtime) –Fermilab internal (FESS/TD Support) activity for civil construction started Complete design of full VTS cavity staging area – FY09 Design VTS2&3 cryostats as part of FNAL-Indian Inst. collaboration –As similar as possible to VTS1 to minimize design effort/time: major changes include larger diameter & length, higher capacity J-T heat exchanger –Includes top plates, magnetic & radiation shields, cryostat internal cryogenic piping and instrumentation Preliminary Design Review in May 2009 Procure VTS2 – FY09 – end of CY09 Shown at May DOE/SRF Review

31.Aug, 2009SRF Mtg8 Since the May DOE/SRF Review VTS2&3 Cryostat –Preliminary Design Review May 22, 2009 Thanks to committee: Jay Theilacker, Phil Pfund, Tom Nicol and Arkadiy Klebaner (ex officio, MTF cryo safety chair) Committee report delivered May 29, 2009 revealed that the level/detail of documentation used for VTS-1 would be significantly insufficient for VTS 2&3 –We came up with a plan for improved documentation June 17, 2009, based on guidelines being adopted in TD, as well as responses to the committee’s detailed questions –We received a final memo from the committee Aug.28, 2009, accepting our documentation plan, and largely accepting our responses

31.Aug, 2009SRF Mtg9 Documentation Plan 1.Functional Requirements Specification (FRS): – will define the programmatic needs for VTS 2&3, clearly specify what type and what configuration of SRF cavities will be tested in these cryostats, and specify what are the test parameters (e.g., temperature range, maximum power dissipation, etc.). This specification will motivate the VTS2&3 cryostat subproject and other subprojects for the VTS2&3 project; whereas the remaining documents in this list are specific to the VTS2&3 cryostats. 2.Statement of Work (SOW): –will define the work scope, objective (using the FRS as a reference), institutional responsibilities, and top level organization of the VTS2&3 cryostat work. It will clearly state the responsibilities of Fermilab and Indian Institutions in more detail than the existing MOU addendum. 3.Project Management Plan (PMP): –will define how the SOW will be executed. The PMP will include the project approach, project organization with team members and their affiliations, a list of major project documents, the document control system, a list of project reviews with level of formality, the Work Breakdown Structure (WBS), the top-level project schedule with milestones, a cost estimate, and a risk assessment. 4.Technical Requirements Specification (TRS): –will specify the requirements for the VTS 2&3 cryostat design to satisfy the FRS. This document is not a procurement specification, and it does not include fabrication details or vendor responsibilities. This document provides the necessary design input information, independent of which institution or organization is responsible for developing the design. 5.Technical Design Report (TDR): –will describe the VTS 2&3 cryostat design based on the TRS. This document will include design details such as calculations and drawings, and may reference design notes. 6.Procurement Plan (PP): –will define the procurement strategy for the VTS 2&3 cryostats. This document will define procurement packages, type of procurement (e.g., built to print, built to performance), procurement steps (e.g., RFI, RFP), vendor selection criteria, fabrication reviews, etc. 7.Procurement Specification (PS) for VTS-2 from a US vendor: –based on a reviewed and approved TDR, and vendor feedback from the RFI, procurement specifications for U.S. vendors for the VTS-2 cryostat will be written. These specifications will include fabrication details and vendor responsibilities and a complete set of design drawings from the TDR. A separate procurement specification will be written by RRCAT colleagues, and approved by Fermilab, for procurement of VTS-3 in India.

31.Aug, 2009SRF Mtg10 Latest Updates Functional Requirements Specification –First draft released today; awaiting comments –A document addressing need for J-T heat exchanger containing calculations and measurements was released last week; internal review in progress VTS2&3 Civil Construction –Selected (new) vendor eventually declined to do the work –New RFP with one vendor (same as for VTS-1) submitting bid –Pre-construction meeting with that vendor tomorrow –Expect IB1 operations/cryo system shutdown to start this week –Shutdown of IB1 operations ~6 weeks duration Few if any vertical cavity tests possible before mid- November

31.Aug, 2009SRF Mtg11 Milestones VTS2&3 civil construction –July/August 2009 VTS 2 cryostat preliminary design review May 2009 –fabrication & delivery in FY10 –installation in FY10-FY11 –commissioned in FY11 Cryogenic system upgrades –procurement completed by end of FY09 –commissioned in FY11 VTS 3 cryostat –fabrication & delivery in FY10-FY11 –installation in FY11 –commissioned in FY11 Sept.2009