9/6/20121 PHENIX WEEKLY PLANNING 9/6/2012 Don Lynch
9/6/20122 This Week Complete Repair & Upgrade of station 1S quadrants – Done Re-install station 1 S MuTr qudrants - In progress Remove MPC South for repairs - Done Repair hall probe in station 2 South - Done VTX/FVTX Repairs at Chemistry/Physics Continue Repairs & Upgrades for MuTr Stations 2&3 N&S Remove MMN East vertical lampshade ? Prep for DC West – in progress sPHENIX design support MPC-Ex design support Reinstall Station 1 South FEE Plates - Done Rewire and re-plumb the MuTr south station 1 – In progress Continue Repairs & Upgrades for MuTr Stations 2&3 N&S Continue Prep for DC West – in progress sPHENIX design support MPC-Ex design support
9/6/20123 Next Week Continue Rewire and re-plumb the MuTr south station 1 Continue Repairs & Upgrades for MuTr Stations 2&3 N&S Continue Prep for DC West Continue MPC N&S Repairs Continue VTX/FVTX Repairs sPHENIX design support MPC-Ex design support
9/6/20124 VTX/FVTX Repairs and testing in Progress at Chemistry (VTX) and Physics (FVTX) Departments
9/6/20125 RPC Station 1 North and South Cooling Upgrade NorthSouth
9/6/20126 RPC Background Attenuation Project Looking towards RPC3 North EastWest Looking towards RPC3 South WestEast
9/6/20127 Under DX at RPC3 North EastWest Under DX at RPC3 South WestEast RPC Background Attenuation Project
9/6/20128 DC West Upgrade Design and measurements
9/6/20129 Station-1 South re-capacitation and termination 9
9/6/ Clamp-on Terminator Installation on North & South Station-3 Lower clamp-on terminators already installed for both north and south sta-3 (bottom 4 octants) With new work platforms that reaches all of sta-3; install remaining (upper) clamp-on terminators.
9/6/ MPC Repairs – North MPC Removed for Evaluation
9/6/ DC West Repairs
9/6/ RPC Recirculation Upgrade VTX/FVTX Cooling Upgrade
9/6/ MuID Collar IR Holding Area Support Structural support improvements designed Parts to be ordered Installation this fall prior to EC roll in
9/6/ New Electrical Work for 2012 Shutdown, to be accomplished as time is available 1.Add Transient Surge Suppressor to 3 phase power panel on the Central Magnet Bridge. 2.The Gas Mixing House Breaker Panel for the Gas Mixing side is almost out of spare breaker slots and needs to be reviewed for increased capacity panel to replace it. 3.New computer rack replacements/additions for upcoming Run 13 & Rack Room computer infrastructure changes involving power distribution circuit (UPS and normal AC power) re-work – check with Martin Purschke Additional Work for 2012, not yet scheduled, to be fit in as available 1.Replaced aging magnet hoses (CM only) 2.identify obsolete services passing through sill and remove them. 3.Cover for services coming from IR through sill. 4.Plan for stripping out TEC electronics and services to free up TEC racks. 5.Add limit switch and improved spooling control for window washer cable.
9/6/ PHENIX Shutdown 2012 Electronics Upgrade /Repair Replace remaining RS-485 type ADAMs on West carriage with MODBUS/TCP type. Install Ethernet switches and MODBUS/TCP ADAMs on Central Magnet arm. Install second MODBUS server in counting house. Install MTP patch bay and jumpers for FVTX in counting house. Add several backup MTP fibers from CH to IR
9/6/ MPC-Ex Upgrade We will be making measurements and test fitting mockups this summer in preparation for design and fabrication next fall, if proposed upgrade is approved North MPC 07/25/12
9/6/ sPHENIX
9/6/ Carpenter – Assist with Station 1, MMS, MMN and DC West scaffolding and work platforms - -7/23-Oct. 26 (2 weeks at beginning, 1 week at end, ½ days at various intervals between) Articulated manlift – For removal and re-installation of MPC N - week of 10/16 CAD Mech techs – remove and restore MMS and MMN lampshades – week of 7/23 Survey – VTX/FVTX at Chemistry and PHENIX IR - 10/8-11/9 Riggers – transport VTX/FVTX to IR from Chemistry - week of 10/29 Carpenters and Riggers – erect and disassemble Summer Sunday dance floor - 8/1-8/7 Riggers and Carpenters – restore dumbwaiter and ladder to EC - week of 11/26 Riggers – Assemble shield wall and Install plug door – 12/26-12/28 Blue Sheets and White Sheets - 12/3-12/21 A/C evaluation and repairs, IR and rack room A/C’s – complete by start of run 13 Requested CAD Support for 2012 Shutdown
9/6/ Procedures for Shutdown 2012 Existing PHENIX General Purpose Recurring Task procedures - on line VTX Removal - Done FVTX/VTX installation - Done VTX Survey - Done FVTX Survey - Done FVTX Cooling SystemUpgrades - Done MuTr Maintenance & Upgrade (stations 1 2 & 3) - Done MuTrigger Maintenance and Upgrade - Done DC Repair – Incl. in WP MPC removal and re-installation – incl in WP - Done Work Permits for Shutdown 2012 Start of Shutdown (PHENIX) - Done VTX Removal/FVTX/VTX Installation – Approved MuTr/MuTrigger Maintenance and Upgrade 3 WP’s: Station 1, MMN and MMS work - at CAD for Approval RPC1 Cooling Upgrade (PHENIX) – Done DC West Repairs – in Design MPC repairs - Approved End of Shutdown (PHENIX) Procedures will be part of 1 WP for VTX and FVTX –Incl. in separate WP’s for MMN and MMS entry
9/6/ CM is currently moved north to gain access to station 1 south. Work on RPC1 South, DC West, MPC South and MuTr Station 1 South. Move CM north complete beampipe and CM survey. Move MMS North to run position. VTX/FVTX work may be done in any configuration. After all work finished move CM south, reinstall MPCN complete RPC1 North work, survey step 1 for beampipe,
9/6/ Shutdown Schedule Remove MMS & MMN vertical East lampshadesDone * MuTr South Station 1 work Install access (Sta. 1work platforms) Done Disconnect Cables, hoses etc, ID/label all In Progress Remove FEE plates and chambers Done Station 2 Terminators and manifold upgrade through Done access opened by station 1 removal Station 2 South Hall probe repairDone MPC South repairs8/20-9/15/2012 RPC 1 South cooling upgrade8/20-9/15/2012 Labor Day Holiday9/3/2012 MuTr South Station 1 work (Cont’d) Clean/install new MuTr Sta. 1 chamber parts and upgrades Done (concurrent At RPC Factory) Re-install chambers and FEE plates Done ? Re-cable, re-hose and test 9/5-9/21/2012 re-capacitation and air manifold upgrades Station 3 North and South (upper half)7/23-9/30/2012
9/6/ Repair upgrade, reassemble VTX/FVTXIn Progress Test, survey (at Chemistry and IR) and re-install VTX/FVTX10/5-10/31/12 Substation breaker upgrade/test (CAD)8/20-9/30 DC West maintenance (replace window)9/15-10/15 RPC stations 1 and 3, north and south maintenanceAs required Other detector maintenance as requiredAs required Infrastructure maintenance as requiredAs required TBD prototype tasksAs required Open Station 1 North, re-install MPC North 10/16-10/26/2012 RPC1 North Cooling upgrade 10/16-10/26/2012 Veterans Day Holiday11/12/ Pre-run commissioning and prep for run 1311/1-12/31/2012 Prep for EC roll in11/12-11/16/2012 Roll in EC11/19-11/23/2012 Thanksgiving Holidays11/22-23/2012 Prep IR for run11/26-12/3/2010 Pink/Blue/White sheets12/3-12/21/201 Christmas Holidays12/24-25/2012 Start run 131/1/ Shutdown Schedule (Continued)
9/6/ Safety, Security, Etc. PHENIX Ladder Update: Ladder to Muon ID Steel in Southeast IR: Yellow Tag: requires work permit to access Ladder to Muon ID Steel in Northeast IR: Red Tag: work around use yellow tower ships ladders and access from top level. Ladder on Southwest and Northwest of MuID steel: Red Tag: do not use, no work around Ladder to Eyebrow: Red Tag: work around – use new cross over from bridge; ladder repairs in planning stage Ladders to West carriage, North and South: Red Tag: do not use, work around: use portable ladder to access platforms, consult PHENIX work control coordinators first to plan work All other fixed vertical ladders at PHENIX: Red Tag: do not use, no work around All non-vertical (ships ladders), non-fixed ladders (portable extension, ships (e.g. CM access), A-frame, etc. are permissible to use with appropriate training and planning. Check with work control coordinators for more info.
9/6/ Safety and Security
9/6/201226
9/6/ Where To Find PHENIX Engineering Info September 6 th is Read a book Day and Fight procrastination Day September is Self Improvement Month, Be Kind To Editors and Writers Month, International Square Dance Month, Cable TV Month, National Bed Check Month, National Chicken Month, National Courtesy Month, National Honey Month, National Mind Mapping Month, National Piano Month, National Rice Month, National Papaya Month, Classical Music Month