Proton Source Vacuum Plan By David B. Augustine Ben Ogert Jr. August 30, 2011.

Slides:



Advertisements
Similar presentations
Antero Punttila Analyzing most typical energy saving measures Energy Efficiency of Steam and Condensate Systems Antero Punttila, Motiva Oy.
Advertisements

Thermostats, Pressure Switches, and Other Electric Control Devices
LCW Upgrades - Final Booster RF Cavity LCW Isolation Valve Replacement. – 8 valves and unions previously replaced – An additional 10 valves and unions.
ATD Assembly. ATD Assembly #1 Dewar Assembly #1 Status: Dewar has been completely assembled and vacuum tested. No vacuum leaks were detected on the outer.
Proton Source Workshop Booster Downtime Wednesday, December 8, 2010 T. Sullivan.
RHIC CRYOGENICS SYSTEM Time meeting /28/20141TIME MEETING RUN 14 –CRYOGENIC.
GlueX Solenoid Recent progress and Coil cold tests Paul Brindza September 9, 2004.
Progress and Plan for Superconducting RF Cavity RF Group.
Vacuum Box Systems.
Head (Project & Service)
Acceptance Criteria for the Decay Solenoid Tom Bradshaw Mike Courthold Matthew Hills.
Non-welded Window Option Edgar L. Black IIT August 15,2003.
CURRENT STATUS OF CV INSTALLATIONS, WORKS DURING LS1 AND PROBLEMS ENCOUNTERED DURING START-UP NORTH AREA Bill Bannister / Jani Lehtinen EATM – 7 th October.
IR2 and IR4 Summary PEP-II meeting Jan. 23, 2006 M. Sullivan.
Proton Source Task Shutdown 2014 RFQ Injection Linac Tank 1 to 2 emmittance probe and Collimator NTF Beam Line Repair 400 MeV Turbo Station Replacement.
Chemical Engineering 3P04 Process Control Tutorial # 2 Learning goals 1.The feedback cause-effect principle 2. Key element in the loop: The control valve.
NOvA meeting PIP Update W. Pellico. PIP Goals and Scope (Provided in 2011 – Directorate S. H. / DOE Talk ) Goals: Specific to the issues surrounding the.
PIP Update July Agenda Summary Update – Budget/RLS – Current Activities – Upcoming Activities/ Changes Update Slides High-Power Ferrite TestingDennis.
ALICE Recovering the cryogenic system from major contamination.
The Tevatron Decommissioning Plans AEM 10/17/11 Paul C. Czarapata.
VAC – CTRL SYS 8 Feb VAC : MSRC equipment Central area links, to be discussed Ion Tmp aux.
Some results of vacuum stand investigation.. 1. Restoration of turbopump inlet valve V1 tightness The inlet turbopump valve of the first pump station.
Test Mass Discharging System (TMDS) Design Review 20 Nov 2014 Rich Abbott, Dennis Coyne, Eddie Sanchez, Calum Torrie 1 LIGO-G v1.
TEAM UP! FOR FAN AND PUMP SAVINGS It can be as easy as replacing an old drive belt.
Directed Inspection & Maintenance At Compressor and Gate Stations
© 2008 Data Power Services, LLC By: Tom Taranto 2010 Energy Expo Hosted by National Grid NYSERDA Reducing Compressed Air Energy Cost Using a Systems Approach.
NUMI NuMI Review of the Infrastructure – W, G & V 20 July 2001 WBS Page 1 1 Infrastructure Review - W.B.S Water Systems Water Systems –Upstream.
PIP Update Aug 6 th Agenda Summary Update – Current Activities/Updates – New Tuner Test Result: Reid & Slabaugh – Anode Supplies: Crawford.
The Safe Transfer of Pressurized Gas. Collect the Necessary Tools and Equipment Safety Glasses for EVERYONE SCUBA Tank filled to 3000 psi Fill Station.
10 October 2003S. DeBarger PEP-II Vacuum Failures PEP-II Machine Advisory Committee.
Accelerators for ADS March 2014 CERN Approach for a reliable cryogenic system T. Junquera (ACS) *Work supported by the EU, FP7 MAX contract number.
Proton Source Water Systems Proton Source Workshop December 8, 2010 Maurice Ball.
Best Operating Practices for Reducing Emissions From Natural Gas STAR Partners Murphy Exploration & Production, Gulf Coast Environmental Affairs Group,
2015 Shutdown Joe Compton 3/11/2015. RIL PIP Work  Install operational laser notcher  5 days  Dave Johnson & Todd Johnson.
HVAC- Body Works 1 Energy Analysis and Comfort Solutions Inc. Consumers – understanding how an HVAC system works.
CM1 Thermal Cycle CM1 Warmup –1/4/12 (Wed.) to 1/6/12 (Fri.) (~50 hours) –Verified turbo interlock system works CM1 Cooldown –Began 1/9/12 (Monday) –At.
05 Novembre 2003Chamonix XIV Workshop, January How to deal with leaks in the QRL and magnet insulation vacuum Paul Cruikshank for AT/VAC Germana.
AdV Vacuum system changes, 23Feb2011 Central area vacuum equipment SVC 2 (mini) towers 1 new HV tower (Inj) DT,IB from HV->UHV towers (with additional.
NuMI/MINOS Status All Exp. Mtg. June 2, 2008 Jim Hylen/FNAL Page 1 FAR DETECTOR: 98.0% live time (wall clock) There was a power outage on the morning of.
Proton Improvement Plan Keith Gollwitzer January 5th, 2015 All Experimenters’ Meeting 11/5/2015Gollwitzer AEM.
EBIS Accelerator Readiness Review Hazards and Controls for Pressure Systems May 4-7,
The Operation of the Tevatron Vacuum system Authors David Augustine Alex Chen Scott McCormick 1.
56 Mhz Vacuum Mike Mapes Mhz Insulating Vacuum TURBO PUMP WITH GATE VALVE AND GAUGE SET MOUNTED ON TANK SIMILAR TO RHIC CRYOSTAT & VALVE.
Overview of the main events related to TS equipment during 2007 Definition Number and category of the events Events and measures taken for each machine.
Best Operating Practices for Reducing Emissions F rom Natural Gas STAR Partners EPA’s Natural Gas STAR Program, Pioneer Natural Resources USA, Inc., and.
PIP Update Aug. 21 st Agenda Summary Update – Current Activities/Updates – Startup Plans – Upcoming Talks, Reports, Meetings Updates/Talks: B Pellico.
Machine Status  Proton Source Commissioning and Studies 8/13-8/14: Linac & Booster Maintenance Period  Main Injector MI30 vacuum ○ Work continues to.
Proton Plan PMG 10/13/05 E Prebys 1 Proton Plan Status September Report Eric Prebys.
August 2007 Booster RF Upgrades J.Reid Booster RF Upgrades West Gallery LCW modifications: – Headers in select locations to be upgraded by.
ATC / ABOC 23 January 2008SESSION 6 / MTTR and Spare Parts AB / RF GROUP MTTR, SPARE PARTS AND STAND-BY POLICY FOR RF EQUIPMENTS C. Rossi on behalf of.
MTA Installation Meeting February 21, 2007 Agenda 1)Progress report (Fernanda+Carol) 2)Floor Plan layout (Fernanda+Larry) 3)AOB Key Red – critical Orange.
Linac4 status and long-term schedule M. Vretenar, Project Meeting  status  timeline  open issues  status  timeline  open issues.
Thomas Jefferson National Accelerator Facility Page 1 CEBAF Cryo & SRF Workshop April 3, 2014 Mathew Wright Cryogenic Systems Operations Engineer
NML Cryogenic System Arkadiy Klebaner Cryomodule One Commissioning June 3, 2011.
At the Ballarat City Gate Construction and Commissioning of a Shell and Tube Heat Exchanger Speaker: Godwin Wong.
1 BNL LHC Hi-Lumi QXF Vertical Test Facility Status Update M. Anerella, H. Hocker, P. Joshi, P. Kovach, A. Marone September 25, 2015.
Thomas Jefferson National Accelerator Facility Page 1 Dana Arenius Cryogenics Control Account Manager 12 GeV Upgrade Project X Collaboration September.
© A.T.T.S. Inc IM Solutions May, Sessions #11: Repair Tech Training 1:30 a.m. – 12:30 p.m. G Truglia What’s Needed To Fix The PO420 & PO171.
LANL Cost and Schedule Review 02/11/05 1 Cryostat (lower half) WBS 3.1, 3.5, 3.6, 3.7, 3.8, 3.10 Paul Huffman, Chris O’Shaughnessy North Carolina State.
CV Activities for PSB-LIU POPS-B (new MPS for the PSB-LIU) B 245 PSB Demi water cooling plant Stefano Moccia, EN-CV Meeting 07/03/16.
WATER SYSTEM WORKSHOP February 27, 2012
18/March/2008OP-days S.Mataguez / O.Hans1 Hardware Problems in the PS complex LINAC 2 BOOSTER PS AD Thanks to all that helped and provided information,
10/3/2014 Proton Source Update. RIL Update Source B is back in place and under vacuum It will be baked over the weekend It will be started early next.
Spoke section of the ESS linac: - Status of prototypes and CDS-SL
Cryogenic System Operation and the Progress of SSRF II
Action People Time [h] Shutting down the SR 2 1
Linac4-PSB 160 MeV connection readiness review ( TE/VSC )
Regular cryomodule maintenance plans (radiation damage, seals, etc)
(WBS ) Alan Wootton, LLNL April 24, 2002
SNS PPU CRYOMODULE PDR Cleanroom Assembly Katherine Wilson
Presentation transcript:

Proton Source Vacuum Plan By David B. Augustine Ben Ogert Jr. August 30, 2011

Linac and Booster The vacuum system in the Proton Source is mostly original. Ie. Vacuum valves, Ion pumps, mechanical pumps, Ion pumps, etc In several cases – Vacuum valves are worn beyond repair – Will not lock closed with out air pressure – Mechanical pumps are obsolete – N2 gas systems in need of repair – Ion pump bodies worn 2

Linac and Booster About a year ago A detailed cost estimate created for – PreAcc – Linac – Booster – This estimate just shy of 800K in FY10 dollars 3

Linac MSD funds used to purchase newer equipment in FY11 to mitigate operational liability – New gate valves were purchased for the old Linac RF ~ 5K not installed – One LN2 dewar was repaired at A-0 ~40K, completed in May 2011 – One left to repair 4

Linac Low Energy This is a example of on of the four gate valves that will be replaced during a long shutdown or a large failure. 5

Linac 400 MeV Area Four of these each or 48K 6

Linac Low Energy Existing high capacity Roots Blower station on tanks one and two in the Linac tunnel. Used to pump out the low energy Linac ~50K 7

Linac Low Energy Existing high capacity Roots Blower station on tanks three and four in the Linac tunnel. Used to pump out the low energy Linac ~40K This is a floater station 8

Linac Low Energy Existing high capacity Roots Blower station on tank five in the Linac tunnel. Used to pump out the low energy Linac ~40K This is a floater station 9

Linac The o-rings used in the Linac low energy tanks are custom. We do have some minor amount of spares. It is assumed that these are beyond there shelf life. A manufacturer should be investigated and these o-ring made. I have no cost estimate. They would be a custom extrusion 10

Linac High Energy The Linac High Energy does not need extensive work – Spare vacuum equipment should be understood i.e valves, ion pumps, solenoids, etc 11

Liquid Nitrogen Dewars Dewar Before RepairDewar After Repair 12

Booster MSD funds used to mitigate operational liability – Purchased two Roots blower stations. – Purchased some replacement vacuum valves at these stations. 13

Booster Vacuum Valves in the ring are mostly the non-locking type when closed. They all will open upon loss of gas pressure. There are approximately 8 of these, 3K each ~ 24K. This does not include flange changes in the tunnel, seals, welding, etc 14

Booster The Mechanical pumps in the tunnel are obselete. MSD funds in the past two years have replaced 4 turbo pumps out of the 24. These are ~8K each or 160K 15

Booster The Roots Blower stations in the fan rooms are obsolete. Two have been replaced by MSD funds. One is dead and the last is a cobbled spare. Two will need to be purchased ~25K 16

Booster Example of cobbled together Roots blower station ~ 13K 17

Booster This is the last 40 year old station in Booster ~13 K to replace 18

2012 Purchases In Priority Order No funding from MSD Installation by Linac Booster Mechanical Group 19

Booster In many cases over the years vacuum leaks were patched over with glyptol, and vacuum epoxy. There is currently a three page list of these. They should all be fixed correctly before the tunnel gets too hot. I cannot estimate the cost of this. 20

Thank you for your attention 21