Cooperation Fund Progress report Plans Maintenance, ownership and change ALICANTE, 23/04/2013
The CF is a major undertaking by any standards: - Total budget of 50 million individuals working on the Fund. - Approximately 455 man years now planned across the lifetime of the Fund national project implementations until 2015 at EU Offices. More expected already completed. By end of 2013, expected 225 total. - The November go-live proves that the network…. works. We can do it. A MAJOR UNDERTAKING
Overview and brief description of CF Projects Search Image TMview TM Class Seniority Quality Standards User Satisfaction Survey Designview Similarity Cesto 2.13 XML Standards & Arch E-Learning - Approval of Project Brief in October 2010, - Kick-off in January 2011 Packet 1: PROJECTS OVERVIEW
Overview and brief description of CF Projects Approval of Project Brief in April 2011, - Kick-off in September 2011 Packet 2: Common Gateway Forecasting 2.14 Future Software Package 3.21 Call Centre Tool 4.22 Enforcement Database 4.23 Counterfeiting Tool PROJECTS OVERVIEW
Already live before November TMview Seniority TMclass Live since November Search Image Quality Standards Designview Similarity Cesto 3.20 E-Learning Common Gateway User Satisfaction Survey 2.14 FSP e-Filing TM Finland LAUNCH PLAN
* April or June 2013 LAUNCH PLAN Planned go live in Forecasting* 3.21 Call Centre Tool* 4.22 Enforcement Database* 4.23 Anti-Counterfeiting Tool* Planned go live in 2014 Planned go live in FSP E-Filing TM & DS 2.14 FSP Back Office 2.14 FSP e-Services 2.14 FSP Adoption
Action: Lesson learned: Core business work in Offices takes time. Planned go live in 2014 Planned go live in FSP E-Filing TM & DS LAUNCH PLAN 2.14 FSP Back Office TM 2.14 FSP e-Services 2.14 FSP Adoption 2.14 FSP Back Office Designs So: Work more intensively with pilots – multiple pilots Be clear from the outset on the workload Use workshops to be clear on needs Accelerate pilots to allow more time for others.
Action: Lesson learned: Implementation is not as expensive as we expected, but it can be complex. Planned go live in 2013 Content 128 Designview LAUNCH PLAN 111 Search Image 1210 CESTO 1211 Gateway So: Try to further improve the technology Extend the deployed project managers Do more work on Quality Intensify work with National Contact points on planning and reporting Better searches and technology, closer link to images Relative grounds; improvements in use of TMiew data Enhanced security for enforcement Deployed project managers Increase numbers; extend time 1212 Quality Best practice: link Convergence
= total intents (324) = total implementations (130) INTENTS TO IMPLEMENT VS. REAL IMPLEMENTATIONS
CF Search Image BX, IT, PT, UK FICPI, MARQUES CF CESTO BG, PL, PT, SK INTA CF Common Gateway DK, ES, GR GGE, PL, RO, SE EFPIA CF Quality Standards DK, ES, HU, PT ECTA, INTA CF Forecasting DK, ES, HU, PL, PT, UK CF Satisfaction Survey BG, DE, DK, ES, HU, GRUR, INTA CF Designview CZ, DE, DK, ES, GR OBI, UK APRAM, ECTA CF Similarity BG, DE, ES, GR GGE, HU, PL, PT, ECTA CF 2.14 FSP AT, FI, IE, MT, PL, LV, SK, UK CNIPA CF 3.20 E-Learning BG, ES, RO, SI, SK INTA, MARQUES CF 3.21 Call Centre CY, DE, DK, PL ECTA CF 4.22 Enforcement DB ES, HU, RO, UK, AIM, APRAM, BUSEUR, UNION CF 4.23 Counterfeiting Tool ES FR, IT, PT, UK ECTA, INTA PARTICIPATION 24 National Offices and 11 User Associations have participated in the CF Project Working Groups. OHIM subject matter experts are in all of them, not just as Project manager…. User Group National Associations: CNIPA, APRAM, IE, LV, MT, PL, SK, RO STILL WORKING COMPLETED
EE LV MT GR CY BG RO SI IE PL SK OVERVIEW CF DPMS (DEPLOYED PROJECT MANAGERS) So far, DPMs are present in 11 National Offices. Their cost until the end of 2012 amounted to roughly 1,2 million euros.
According to current estimates, a significant amount of man days have been foreseen for the whole lifespan of the Cooperation Fund. PROGRESS
CF Maintenance Model Outline
Background - principles CF MAINTENANCE SUPPORT MODEL The business responsibilities of National Offices should not be taken over by the OHIM. The OHIM will help create tools and jumpstart their adoption so that Offices can lead their own process of modernization and improvement. There will be a transition period to ensure that the tools can be put into operation and that National Offices have the capacity to use, operate and maintain them. Projects supported in two groups: Common tools Software package
Background – approach – Common tools CF MAINTENANCE SUPPORT MODEL Common tools: Search Image TMview Euroclass and TMC Quality Forecasting User Satisfaction Survey Designview Similarity Common Examiner Support Tool Gateway e-learning Contact Centre Database E-learning Enforcement Tools OHIM will take on the management and maintenance of the common tools built under the Cooperation Fund. The central index model worked well for TMview and will be used for Designview
Adaptation of FSP to Office needs A year of OHIM financial or expert support Creation of a problem-solving & knowledge sharing network Funding for one SNE (IT profile) for one year to the OHIM, maximising knowledge transfer and ensuring effective delivery. Plus one of: 1.A full-time consultant from OHIM´s providers for one year working days of a local contractor. OHIM will establish a contact network between the experts This includes information and communications via the Common Gateway and regular meetings OHIM will administer the platform and provide a secretariat Budget is per NO that implements the whole package Supported by OHIM experts covering Architecture, Security, Operations. Overall management is assured by the PSO. New: Focused into one project (SP Adopt) separate from pilot developments. 123 Background – approach – Software Package CF MAINTENANCE SUPPORT MODEL
CF Maintenance Model Proposed outline
HAND-OVER - PROPOSAL FOR DATA AND SYSTEM OWNERS OF CF TOOLS The Cooperation Fund is a programme built to deliver the projects: it is not a permanent structure Once a project becomes a product, the CF must ensure handover of maintenance and ownership to NOs and OHIM units, and step aside. Each project has experts from Operations, Operations Support or other relevant Services directly involved as working group members representing OHIMs views as an implementing office. This means that at the end of each project there needs to be a handover process to the new owner in the relevant business unit, and to the OHIM IT maintenance structure. A coordinating point remains in the Cooperation Programmes service. at the OHIM…
IT Support (OHIM or PO) OHIM contact point Acts as coordinating point for POs and OHIM business units, supporting the regular contact network Supports reporting to, and actions from, Liaison Meeting on Technical Cooperation Coordinates ranking and budgeting in Gateway, handles queries on outcome Shows availability of tools in Gateway Owns formal change management process to deliver changes into common IT tools Monitors and delivers through release calendar Maintains service levels Supports and advises on preparation of cards Proposes changes and fixes where necessary, especially in urgent or critical cases. 2 3 Who does what? CF MAINTENANCE SUPPORT MODEL Business area – OHIM or NO, or user association Proposes changes or fixes. If necessary with support from 1 or 2, completes card on explanation and urgency When advised, reviews changes submitted on the Gateway and ranks in terms of relative importance. Raises any substantive issues at LMTC or in bilateral communication with contact point. 1
ETMDN The Gateway
Change Management and ownership
CF CHANGE MANAGEMENT - HIGH LEVEL PROCESS Contact point Impact Assessment Liaison Meeting March, year N Liaison Meeting March, year N Output: detailed assessment, plan with deliverables and costs POs and OHIM units POs and OHIM units Changes 1 Project execution, development and release Major change and improvement cycle Clarifies Ranks Outputs: - Formal approval - Team and workgroup established Outputs: - Formal approval - Team and workgroup established Liaison Meeting (year N+1?) Outputs: - Closure report - Acceptance Outputs: - Closure report - Acceptance 5 6