Day-Ahead Market Coupling Proposal for algorithm approval process 8 th ACER Coordination Group for ERI Brussels, 9 th January 2012.

Slides:



Advertisements
Similar presentations
Handling of grid losses of HVDC cables in NWE Market Coupling - EMCC proposal for compensation of grid losses – NWE day-ahead meeting, Copenhagen, 22/08/2012.
Advertisements

Draft Cross-regional Roadmap for Day-Ahead Price Coupling NWE Day-ahead price coupling project meeting 15 June 2011.
Cross-regional roadmap for Day-Ahead Market Coupling XXI Florence Forum Florence, 5 December 2011.
4th CSE ERI Stakeholders Group meeting AEEG – European regulatory affairs 15 maggio 2012 Overview of the regional work programme towards 2014.
Draft cross-regional roadmap for Day-Ahead Market Coupling Work in progress, This version: 22 September 2011 updated after 5 th AESAG, 20 September 2011,
Draft Framework Guidelines on System Operation - Process Presentation Workshop, Ljubljana, 24 August 2011 Uroš Gabrijel (ACER)
TITRE Public Workshop on REMIT Ljubljana, 19 July 2012 Public consultation document on ACER recommendations on REMIT records of transactions and implementing.
TITRE 28/03/2012 NWE IG meeting – Amsterdam Schiphol NWE day-ahead price coupling – cost issues.
SWE IG Meeting Paris, CRE XBID Overview Supported by.
1 Madrid, 2 nd Nov th IG Meeting South Gas Regional Initiative VI. MIBGAS.
Florence Forum Multi Regional Day-Ahead Price Coupling Towards Implementation of the PCG Target Model December 10-11, 2009.
NWE Day-ahead price coupling project Cost Issue 2 nd IG Meeting 26 October APX ENDEX.
Cross-Regional Roadmap for Intraday DRAFT Updated 31/10/2011.
Cross-regional roadmap for Capacity Calculation XXI Florence Forum Florence 5 December 2011.
Update on Transparency Obligations Martin Reisner Junior Adviser, Transparency ENTSOGs Transparency Workshop Brussels – 11 September 2012.
Action plan covering 2008 activities for the implementation of day-ahead implicit auction in Central-South Europe as a mean to allocate cross border capacity.
1 TITRE Identifying priorities for GRI NW and setting agenda for Menno van Liere Programme Officer GRI NW 11 th Stakeholder Group meeting GRI.
New structure of GRI NW following revised road map Stakeholder Group meeting Brussels, 26 November 2010 Peter Plug Chairman GRI NW.
TSO Transparency project Gas Regional Initiative North West Ofgem, Great Britain Regional Co-ordination Committee 18th February 2011.
Disclaimer Some elements of the following presentation are extracted from documents approved by the 11 CWE Project Parties. However, this presentation.
1 page 1 NWE Intraday - Joint TSO and PX presentation London.
Framework Guideline on gas capacity allocation Stefanie Neveling, Co-Chair CAM TF 20 th Madrid Forum, 27 September 2011.
The role of ACER In the Regional Initiatives Steve Gordon Head Of the Gas Department North West Regional Initiatives 2011.
09/12/2011 NWE Stakeholders Group meeting-London Getting to 2014 A contribution from the Regional Initiatives Process Christophe Gence-Creux Head of the.
FUI Feedback on PCG Target Model and roadmap propositions FUI Stakeholder Group Meeting Paris, 4 th November 2009 These comments reflect the general views.
Click to edit Master title style TITRE CEE IG – 20/02/2014 ACER Long-Term Rights Task Force Current status of the discussion with ENTSO-E.
1 page 1 C O U P L E D Joint TSO-PX presentation NWE Day-Ahead Price Coupling IG meeting May 9 th 2012 Copenhagen Joint Presentation from TSOs and PXs.
3. Update on status and implications of NWE intraday project (selection of the solution for the platform) 11 th Implementation Group Meeting 1 st March.
Florence Forum Third package December, The possibility given by the EC to all stakeholders to comment the ” Discussion paper on the Third Energy.
GRI-S : Infrastructures The Union list of projects of common interest European Commission DG Energy Internal Market I: Networks and Regional Initiatives.
Adeline Lassource (CRE) Charlotte Ramsay (OFGEM) 10 th FUI SG, London, 11 th March 2011 Progress with market integration: European initiatives and impact.
ACER’s view on the future role of the Gas Regional Initiative Dennis Hesseling Head of the Gas Department, ACER 11 th Stakeholders group meeting of GRI.
1 page 1 C O U P L E D NWE TSO Day Ahead Project NRA – TSO – PX meeting, 15 June 2011 ENTSO-E Regional Group Northwest Europe C O U P L E D.
1 page 1 C O U P L E D NWE Day-Ahead Project 1 st NWE Stakeholder Workshop London 9 th December 2011 ENTSO-E Regional Group Northwest Europe.
Draft Cross-regional roadmap for Capacity Calculation Still work in progress, for discussion 27 June 2011.
SG MEETING GRI NW– 28 N OVEMBER 2013 Incentives and Cross-border Cost Allocation in the Energy Infrastructure Package Benoît Esnault (CRE) Chair of the.
on Congestion Management (IG)
Day-Ahead Market Coupling Algorithm approval coordination NWE IG, Schipol, 28. March 2012.
1 TITRE Update on approval processes for NWE price coupling NWE IG on DA and ID Copenhagen, 9 May 2012.
Cross-regional roadmap for Long- Term Transmission Rights XXI Florence Forum Florence 5 December 2011.
Report on ACER Progress An exchange of views with the Committee on Industry, Energy and Research of the European Parliament Brussels, 11 July 2011.
Update on Ofgem’s interconnector policy consultation FUI IG, London, 13 th September.
1 page 1 C O U P L E D Joint TSO-PX presentation NWE Day-Ahead Project Status Update 2 nd IG meeting NRA meeting October 26 th Joint Presentation from.
SWE Day- Ahead market coupling 7 April 2014 Implementation Group meeting – Paris.
Draft Cross-regional roadmap for intraday Work in progress, for discussion 13 July 2011.
Status of Implementation of PCR for Day-Ahead Price Coupling Florence Forum 5 December 2012.
Draft cross-regional roadmap for Day-Ahead Market Coupling - Work in progress - NWE day-ahead price coupling project IG meeting 26 October 2011.
Draft cross-regional roadmap for Long-Term Transmission Rights Still work in progress, for discussion 27 June 2011.
Madrid Forum 15 October 2014 Massimo Ricci Chairman.
SWE Day- Ahead market coupling 25 February 2014 Implementation Group meeting – Madrid Draft.
Action for establishing a Single Auction Office for CSE Electricity Regional Initiative - Central-South Region 2 nd Stakeholders Group Meeting 21 April.
PCR Status report AESAG, September Supported by:
Electricity Regional Initiative Central South European Region Draft Report on Transparency for the CSE-Region Jan Müller Bundesnetzagentur ERI Central.
Electricity Regional Initiative Central Eastern European Region Congestion Management – Status & Prospects Tahir Kapetanovic E-Control CEE Stakeholder.
0 Congestion management Congestion management Giedrius Radvila AB “LIETUVOS ENERGIJA” Minifora Vilnius.
Gas Regional Initiative Region North-West Transparency Project Nicola Meheran, Ofgem.
1 The regulators’ view on the Central West REM: Emphasis on the completion of existing initiatives Presentation for the Mini-Forum 20 June 2006.
TSO Transparency project Gas Regional Initiative North West Nicola Meheran, Ofgem Regional Co-ordination Committee 15 September 2011.
1 May 2012CACM Network Code Capacity Allocation and Congestion Management for Electricity Network Code ROME, 15 th May 2012.
The EU’s Third Energy Package European Code Development UNC Transmission W/S - 4 th December 2008.
1 15 th July 2015 Teleconference 32 nd IG Meeting South Gas Regional Initiative.
Florence Forum, November 2008 Regulation (EC) 1228/ ERGEG Compliance Monitoring.
Status of Implementation of PCR for Day-Ahead Price Coupling
Supported by: PCR Status report AESAG, September
Capacity Allocation and Congestion Management for Electricity Network Code ROME, 15th May 2012.
REPORT OF THE ELECTRONIC WORKING GROUP UNEP(DEC)/CAR WG.29/INF.12
NWE Day-Ahead Price Coupling
Capacity Allocation and Congestion Management for Electricity Network Code ROME, 15th May 2012.
Supported by: PCR Status report AESAG, September
Scene setter European Commission DG Environment
Presentation transcript:

Day-Ahead Market Coupling Proposal for algorithm approval process 8 th ACER Coordination Group for ERI Brussels, 9 th January 2012

2 Background. Cross-regional roadmap: ACER shall coordinate NRAs endorsement (e.g. through letter of comfort) of: [the] starting point of the PCR algorithm in Q All NRAs shall agree on [a] common, coordinated approval/review process for the algorithm. This agreement shall also be finalised in Q and it is dedicated also towards the final algorithm to be used in operation in NWE and EPC.. To contribute to this process, NWE Day-Ahead Cross-Regional Coordination Committee (CRCC) drafted common approval process for the algorithm with the aim to align as far as possible aspects of national processes and to limit duplication of work.. The draft will be submitted to ACER in order to coordinate NRAs endorsement of the starting point of the PCR algorithm.

3 Proposal for common, coordinated regional approval/review process (I) Step 1: Description of methodology. After NWE IG meeting in October 2011 PX were asked to provide NRAs with a high-level description of the PCR algorithm, inter alia objective function, side conditions, requirements, functioning of the algorithm.. Main elements/components of PCR starting point algorithm (i.e. COSMOS algorithm in production in CWE) already published ( Moreover, the algorithm has to be made fully transparent and accessible for regulators, so that every detail can be assessed.. ENTSO-E shall evaluate the PCR algorithm starting point (now delayed) by January Furthermore, ENTSO-E shall send algorithm requirements to Europex and NRAs. This will be another basis for regulators approval.. ENTSO-E and Europex shall consult market participants on starting point PCR algorithm as validated by ENTSO-E and report outcome to ACER and NRAs Deadline: Q / early Q1 2012

4 Proposal for common, coordinated regional approval/review process (I) Step 2: Regulators task force. NRAs establish algorithm task force to evaluate (1) first the starting point of the PCR algorithm based on the information received in step 1 and (2) afterwards further assess the detailed descriptions of the algorithm from the TSO/PX NWE design phase and the further development towards EPC. Main contact persons from the task force and the TSO/PX project are nominated.. Task force gives recommendation for endorsement of the starting point of the PCR algorithm based on an assessment of compliance with the CACM framework guideline (Chapter 3.1 and 3.2) and Annex 1 of regulation 714/2009. Deadline: Q This is then evaluated by the NWE CRCC and afterwards submitted to the ACER in order to coordinate NRAs endorsement of the starting point of the PCR algorithm, e.g. letter of comfort. Deadline: end Q1 2012

5 Proposal for common, coordinated regional approval/review process (III) Step 3: Final algorithm for implementation in NWE and EPC. For approval of final algorithm for operation in NWE PXs shall demonstrate to NRAs that algorithm is running stable and producing robust results also in extreme situations. Minimum condition: Simulation results using historical data (also including critical days). Deadline: Q Task force gives recommendation for approval/review of the final algorithm based on the above information and on an assessment of compliance with the CACM framework guideline (Chapter 3.1 and 3.2) and Annex 1 of regulation 714/2009. Deadline: Q Thisis then evaluated by the NWE CRCC and ACER and afterwards submitted to NRAs as input to the national approval/review process. Deadline: Q3 2012

6 Proposal for common, coordinated regional approval/review process (IV) Step 4: National approval/review processes. In parallel to the common coordinated regional approval process, there will also be national approval processes, depending on the respective national legislations. Deadline: End Q for NWE and repeated for further step towards EPC.

7 Proposal for common, coordinated regional approval/review process (IV) Step 5: Evaluation after implementation. The regulators will continuously evaluate the functioning of the price coupling algorithm in order to (i) monitor the price coupling, (ii) capture effects that were not anticipated in the approval of the algorithm and (iii) propose changes to the algorithm if deemed necessary.. The first evaluation of the pricing algorithm will take place after one year of operation.. The TSOs/PXs will be asked to provide a report based on all relevant data, e.g. on flow, capacity allocation and prices.. Regulators will evaluate whether the results live up to the criteria in the approval. Deadline: Q / Q for NEW; periodically with further extension towards EPC

8 Thank you for your attention