MOM Report Galina Vankova RAL, 1. 09. 2011 MICE Video Conference.

Slides:



Advertisements
Similar presentations
MOM Report Ray Gamet MICE Operations Manager University of Liverpool MICO 18 th May 2009.
Advertisements

MICE Superconducting Solenoids: Status and Update RAL: T W Bradshaw M Courthold J Rochford M Hills D Baynham Oxford: J Cobb W Lau S Yang MICE.
MICE Hall – South Mezzanine Jason Tarrant - STFC l Contents »Device checks with current South Mezzanine »South Mezzanine change summary »Conclusion.
1 MICE Video Conference Installations to date Future installation work Plans for May shutdown MICO organisation Use of Technical Board.
MICE Collaboration meeting May 31 st – June 3 rd 2009 RAL Tim Hayler, Andy Lintern DRAFT SEQUENCE OF EVENTS STEPS
MOM Summary 19/01/10 Water Now the ice has cleared I am able to get on the roof again. Could do with getting the conductivity readings fed back similarly.
MOM Summary 11/01/10 Due to the Inclement Weather it has perhaps been quieter than usual Water - Tank has been holding water fine. Some ice has been forming.
MICE: Hall Infrastructure Chris Nelson CEng CM16 8 th Oct 2006.
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
MICE RF TEST STAND Major Milestones (2006) –Testing of BURLE 4616 circuit September 2006 –Testing of 4616 circuit with full amplitude and phase control.
Project Report Paul Drumm CM15, FNAL June MICE Schedule Overview First beam September/October 2007 –Shutdown from January 2007 –Eight months for.
MOM - M.ApollonioMICO meeting - RAL - 17/3/20081 NEXT steps + proposed aims Today - START Cherenkov INSTALLATION (?) Tuesday 25 MARCH - MICO Meeting (?
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
Pierrick Hanlet MICO June 6, 2011 MICE Operations Manager Report.
UK Costs Beam & Infrastructure Coils Tracking Detector.
MOM - M.ApollonioAccel. R&D/Physics and IADR - RAL - 19/3/ Summary of MICE operations – 14/15 March 2008 AIMS - establish MICE beamline in ISIS synchrotron.
Spectrometer Solenoid Update Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory MICO.
MICE Collaboration Meeting Harbin, China 13 – 17 January 2009 Integration Issues By Wing Lau, Oxford University.
1 Summary of MICE beamline & hall installations This is a very rough summary of the progress since mid-December Richard Apsimon & Andy Nichols MICO meeting.
MICE CM30 7 th July 2011 Liquid Hydrogen Delivery System M Hills (STFC, RAL) T Bradshaw (STFC, RAL) M Courthold (STFC, RAL) S Ishimoto (KEK) A Muir (STFC,
MICE - UK Project Progress Roy Preece 30 th April 2013.
1 MICE-Video Conference Status of MICE Hall Contents: General status Electrical Mechanical Preparing for Steps II & III Risks and worries Andy Nichols,
1 Hall & Beamline Installation Richard Apsimon, Andy Nichols, Willie Spensley MICE Collaboration Meeting, th Feb 2008.
1 MICE - INFRASTRUCTURE MICO meeting 7 th February 2008 Tim Hayler.
MICE: overview K. Long, 18 March, Contents ► Introduction ► Beam line ► Infrastructure ► MICE steps ► Phase II (comment) ► Conclusions.
Control and Monitoring System / EPICS Pete Owens Daresbury Laboratory.
Infrastructure Update As at 11 th March 2009 Remaining four plates now fitted to North shield wall North & South walls and all galleries are considered.
1 MICE Running L. Coney – UCR MPB – 31 Oct Coney - MPB - 31 Oct 2012Outline Current Running Current Running Shift personnel training Shift personnel.
Linda Coney MC VC May 19, 2011 MICE Operations Manager Report.
Preparations in the MICE hall Video Conference 25 th June 09 Tim Hayler Andy Lintern Peter Lau Geoff Barber.
Detector Systems For May/June Run MICE Video Meeting April 24, 2008.
Electrical Integration CM38 Steve Griffiths & Ian Mullacrane.
DAQ MICO Report Online Monitoring: –Status All histograms are now implemented Still not fully online –Only monitoring from data file (slightly offline,
Electrical & Control Power Supplies Trevor Hartnett.
MICE Integration Engineering Jason Tarrant - STFC l Contents »Device Interfaces – General »AFC »Spectrometer Solenoids »RFCC »EMR / KL »South Mezzanine.
1 MICE MPB/RLSR Integration of Step IV Readiness of the major subsystems Installation sequence and schedule considerations Logistics, staffing and local.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
Hydrogen Delivery System Schedule MICE Schedule Review 23 rd -25 th May 2011 M Hills STFC.
1 MICE Hall construction status Richard Apsimon MICE VC meeting 29th Nov 2007.
PRY Implementation - Contents l Fit with Experimental Devices (& services connections) l Fit with Tracker Cryo l Fit with Floor & Trench l Fit with Mezzanine.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
Issues with variable thickness absorbers Iouri Ivaniouchenkov, RAL MICE Video Conference, 22 Jan
MCTF 8/17/06 A. Bross MTA Activities and Plans MCTF August 17, 2006 A. Bross.
1 MICE Beamline Installation, status & plans Contents: Upstream & Target, BPM Decay solenoid DSA, D2, Q4,5,6 cKOV support Q7,8,9 Open issues & concerns.
UK Update Package Managers Meeting 001 Roy Preece 13 th January 2014.
MICE Oversight Committee Meeting RAL, 24 April 2014 Paul Soler on behalf of the MICE Collaboration Status of MICE and Spectrometer Solenoids.
Hydrogen Pre-Operation Safety Review 4 th October 2011 The Hydrogen Delivery System – An Introduction M Hills.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
PRad Recent Achievements 1)PRad Implementation (“Position”) document developed and submitted to Jlab. 2)Jlab’s Director Office scheduling review passed.
Pre-CM33 schedule planning SuperMICO meeting, June 6th Motivation: For all of us to understand the main drivers behind the top-level MICE schedule So that.
1 Mice Collaboration Meeting CM33 Glasgow University 25 th – 29 th June 2012 STFC Daresbury Laboratory Electrical Infrastructure Report Authors : Ian Mullacrane.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
1 MICE PM Report General Update –Phase I nearing completion –MICE Power –Actions for Decay solenoid & target –Follow-ups from last VC –Conclusions MICE.
Detector Summary Tracker. Well, as far as the tracker hardware is concerned, we are done. – Need to do the system test to make sure nothing has degraded.
Tracker 1. Status 2. Expected delivery date of system to RAL 3. Required support infrastructure needed for setup and initial debug. Things like vacuum,
1 Mice Collaboration Meeting CM27 STFC Rutherford Appleton Laboratory, UK 7 th -10 th July 2010 Daresbury Laboratory Electrical Infrastructure Report Authors.
WBS ? Proposed by IPRP … –Preparation for a review –MICE Costs & Time Scales need to be more accurate & Justified –Technical Leaders arranged by technology.
MOM Report Linda Coney MICE Operations Manager University of California, Riverside MICE Video Conference May 20, 2010.
1 Project Infrastructure for steps I-III Tim Hayler, STFC – RAL MICE Collaboration Meeting, RAL, nd October 2008.
MICE CM23 Introduction and Meeting Goals Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory.
Malcolm Ellis – Brunel University – 8th April The International Muon Ionization Cooling Experiment.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
MICE Project Progress Update Power Converters Rack housing MQ1 to MQ3 magnet power converters –Marshalling for all other quadrupole & dipole units –Houses.
MICE VC Alain Blondel 1 MICE NEWS MICE VC Next Collaboration meeting will be at Cosener’s14-16 February meeting at Coseners House.
1 MICE Hydrogen system Working group mtg – 01/09/14.
What do we want to achieve in this running period? Michael S. Zisman Deputy Spokesmouse Center for Beam Physics Lawrence Berkeley National Laboratory MICO.
Arnd Meyer (RWTH Aachen) Sep 8, 2003Page 1 Integrated Luminosity Total data sample on tape with complete detector > 200pb -1.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
L. Coney UC Riverside MICE CM32 – Glasgow – June 2012
MICE Target Report Video Conference 29/11/07
Presentation transcript:

MOM Report Galina Vankova RAL, MICE Video Conference

MICE Hall current activities , 2011 Installation of Step IV and Preparation of the fall MICE run Decay solenoid and cryogenic system - PSU - DL Group to replace selected components; order of pumping rigs - in progress ; Focus is on quench detector replacement Liquid Hydrogen system - Heater/chiller pipe work making good progress - Building of vacuum system - mezzanine supports and gate valve/cross installation, various PPS activities - in progress Vacuum installation on roof - vacuum control panel has been installed and roof handrails have been completed Gas bottle rack outside the MICE Hall - has almost completed

Detector preparations - EMR - removed to offline position, awaiting electronics removal and shipment to UNIGE - Report of LK/TOF/EMR survey received from DLS - Both BPMs have been removed - The missing spanner (wrench) for the mechanical beamstop frame has been replaced Online Reconstruction tests - DAQ system modified to run without the EMR, miceraid2 problem needs to be solved - experts involved,DAQ - ready - as soon as possible Target & upstream beam line - T1 removed - Phase II controller installed - Re-build scheduled for , re-installation on three bobbins has been ordered and cooper for cooling jacket has been provided; T2.8 upgraded, tested and installed Tracker integration in Lab 7 has been completed - efficient operational condition Electrical Infrastructure - cable over main door is installed, earth testing in Hall has to be performed