MQXF considerations MDT section 11/04/2012. Summary Revised planning Development Personnel Production: strategy and personnel Cost Planning issues not.

Slides:



Advertisements
Similar presentations
LM dipole status & plans – Fred Nobrega 1 Long Quadrupole (LQ) Workshop, February 7-9, 2007 BNL - FNAL - LBNL - SLAC Long Dipole Mirror (LM) Status and.
Advertisements

LQ & LM Status & Plan for FY08 – Fred Nobrega 1 LARP Collab. Meeting – SLAC, Oct , 2007 BNL - FNAL - LBNL - SLAC Long Quadrupole (LQ)-Long Dipole.
CIEMAT technological contributions to linear colliders Fernando ToralGandía, 3/12/2005.
A. Perin, CERN, TE-CRG, 26 May Review of the cryogenic by-pass for the LHC DS collimators 26 May 2011 Modifications to the DFBs, DSLC and cryogenic.
Coil working group video-meeting P. Ferracin, J. C. Perez, S. Izquierdo Bermudez, X. Sarasola February 4th, 2014.
11 T Dipole informal coil and assembly readiness review Long coil and fabrication tooling development status and plans September 22 nd, 2013 – F. Savary.
Coil Design and Fabrication Miao Yu Outline Introduction Coil Design –Coil Pole –Coil End Parts –Coil Insulation Coil Fabrication –Winding.
TD/MSD TORUS CMM PRODUCTION: OVERVIEW G. Velev Clas12 Torus CCM Production Readiness Review –Dec 4, 2013.
Project Planning for New Model Home Pre-construction Rey Ross GBA 573 July 10, 2003.
IR Quad Cost Estimate Status Marc Kaducak 02-Nov-2012 IR Quad Cost Estimate - M. Kaducak1.
AARD Sub-panel at Fermilab Feb , 2006 LARP Magnet R&D Program - S. Gourlay1 BNL -FNAL - LBNL - SLAC LARP Magnet R&D Program Steve Gourlay AARD Sub-Panel.
Project management Lecture 10. Topics covered Management activities Project planning Project scheduling Risk management.
Thoughts about the MQXF development plan P. Fessia Thanks to discussions within the MDT section (P. Ferracin, J. C. Perez, E. Todesco, P. Ferracin), L.
FReSCa2 Technical Review, 9 th June 2015, CEA Saclay FReSCa2 Technical Review June 2015 CEA Saclay J.C Perez on behalf of Fresca2 collaboration team.
LQ status and plans – G. Ambrosio 1 LARP Collaboration Meeting - LBNL, April , 2006 BNL - FNAL - LBNL - SLAC OUTLINE: Goals, Input and Output Sub-tasks.
DOE Review of LARP – February 17-18, 2014 Coil Design and Fabrication Miao Yu February 17,
11 T Nb3Sn Demonstrator Dipole R&D Strategy and Status
F. Savary. Click here to add footer 2 Outline Context Constraints & Boundary conditions Project plan Production strategy A few words on QA Conclusions.
Plans and schedule for QXF Giorgio Ambrosio and Paolo Ferracin Joint LARP/CM20 HiLumi meeting Napa Valley, CA, USA 8-10 April, 2013 The HiLumi LHC Design.
11 T Dipole Status at FNAL Fred Nobrega January 21, 2014.
6th ST workshop, Thoiry, 1-3 April ST-HM Design Section Strategy and working methods 3rd April 2003 C. Bertone ST-HM.
Title – xxxx 1 LARP & US-HiLumi Contribution to the Inner Triplet Quadrupoles G. Ambrosio Cost and Schedule Review CERN, March 9 th -11 th 2015.
CCM Resources 1. Project Cost Overview Boards 3&4 (production boards-130 each type ) – Eng. changes and designer layout work – Done – Tech time to place.
Plan. 12/05/ Who are we? PM (Project Management and Resource Planning) – APT – IMPACT – PPTEU2 – Plan LS1 – 2012 –…–… Plan V2 – From LS1 to LS2.
M. Bonesini - MICE Inst Meeting M. Bonesini INFN Milano TOF installation plans.
F. Savary Industrial service contracts for HL-LHC MSC Technical Meeting on
Hi-Lumi Conductor Procurement A.Ballarino, B. Bordini, L. Oberli HL-LHC/LARP International Review of Superconducting Cable for the HL-LHC Inner Triplets.
Long Quadrupole – G. Ambrosio 1 LARP Collaboration Meeting – FNAL, Oct , 2008 BNL - FNAL - LBNL - SLAC Long Quadrupole Giorgio Ambrosio LARP Collaboration.
High Order Mode Suppressors (HOMS) for SPS TWC200 (Sébastien Calvo, David Bastard) 25 November 2015 LIU-SPS Coordination Meeting.
Summary The process and the components The tooling Production back log estimation The handles and the estimated cost and delay.
FRESCA2 Technical Meeting 5-Validation of coil winding with Cu coils Françoise Rondeaux 09/06/ CEA-Irfu-SACM-LEAS - 5-Rondeaux- FRESCA2 Technical.
11 T Dipole Project Cold mass integration status & plan F. Savary / TE-MSC-LMF.
11 T Dipole Project CERN Status M. Karppinen 11 T Management meeting 1 July 2013.
Visual 4.1 Incident Commander and Command Staff Functions Unit 4: Incident Commander and Command Staff Functions.
QXF Coil Fabrication: Baseline Decisions QXF Coil Working Group Video Meeting (Revised from discussion during presentation) Dan Cheng April 16, 2013.
MQXF Short model and prototype plans P. Ferracin, G. Ambrosio HL-LHC/LARP International Review of the MQXF Design December 10-12, 2014 CERN.
Status of Contributions, Draft Budget Request for 2005 and Outlook for the Longer Term Future Martyn Davenport 8 TH October 2004 CAST FRC-D
PSB Reference Magnet (for the 2.0 GeV upgrade) A.Newborough 16 th October 2014.
HiLumi-LARP Annual Meeting November 2014 MQXF pre-series and series magnets fabrication plans Ruben Carcagno November 19,
DOE Review of LARP – February 17-18, 2014 SQXF Coil Design and Fabrication Winding and Curing Miao Yu February 17,
DOE Review of LARP – Feb 17-18, 2014 DOE Critical Decision Process Ruben Carcagno February 17,
Transport and Handling Manpower Planning S. Prodon – LEAF
LARP Review, June 10, 2013Magnet Cost and Schedule – M. Kaducak 1 IR Quadrupole Cost and Schedule Marc Kaducak LARP Review June 10, 2013.
Logo area 11 T Wire: Procurement Strategy and QA/QC B. Bordini, A. Ballarino, M. Macchini Acknowledgments: thanks to E. Charifoullina for her contribution.
LARP CM15, SLAC, 11/3/2010GianLuca SabbiSummary of MS Parallel Sessions Summary of Magnet Systems Parallel Sessions GianLuca Sabbi LARP Collaboration Meeting.
2 nd LARP / HiLumi Collaboration Mtg, May 9, 2012LHQ Goals and Status – G. Ambrosio 11 LHQ Goals and Status Giorgio Ambrosio Fermilab 2 nd LARP / HiLumi.
Long coil manufacturing plan and QC at CERN F. Lackner, P. Ferracin, H. Prin, M. Duret, F. Savary, L. Favier, S. Triquet, S. Luzieux, R. Principe, C. Scheuerlein,
TE-MSC-MDT. FTEC Follow-Up Meeting Juan Carlos Perez TE-MSC-MDT Jose Ferradas TE-MSC-MDT 28/04/2016.
EuCARD-WP7-HFM meeting 15 November 2011 Status of construction of FRESCA2 dummy coil assembly Attilio Milanese, Juan Carlos Perez.
P. Ferracin on behalf of the MQXF collaboration
BNL Progress with LR, application to LQ
Coil Design and Fabrication
11 T Dipole Integration & Plans M. Karppinen
CSP 25th November 2010 Technical agreement number 3: overview
MQXF Planning Paolo Fessia, Frederic Savary, Ezio Todesco, Lucio Rossi - CERN Mike Anerella, Peter Wanderer - BNL Giorgio Ambrosio, Mark Kaducak - FNAL.
11T Dipole – Single Aperture 2m Model
FCC 16 T dipole 4578 dipoles + 5 % spares : 4807 dipole magnets
J.C. Perez on behalf of SMC collaboration team J.C. Perez
Mechanical stability and QXF coil winding
P. Ferracin and G. Ambrosio
the MDP High Field Dipole Demonstrator
LIU Wire Scanner Series Costs
Paolo Ferracin, Giorgio Ambrosio
Large aperture IR Quadrupole (MQXF) development plan
MQXF updates P. Ferracin October 9th, 2014.
Research Accounting Office
QXF schedule and milestones
M E A S U R E ‘G’ P R O G R A M U P D A T E
MQXF quench heaters: tests and investigation (CERN)¶
East Hall under construction
Presentation transcript:

MQXF considerations MDT section 11/04/2012

Summary Revised planning Development Personnel Production: strategy and personnel Cost Planning issues not accounted for Conclusions

Production of 12 coils Reaction by two 30/07/2014->27/08/2015 Assembly MQXF0 (17/03/2015) after completion 5th coil start test 01/08/2015 Shipment 4 coil to LARP 01/07/2015 Coil number 1 12/03/2014- >15/07/2015

Personnel for development requiredAvailableStop other activities Not identified Eng-phys ( ) 1.4 ( ) 0.4 Tech eng1001 Fellow10.5 from recr Designers22 from recr. 00

Coil production PhasesLARP estimated time [working days] courtesy G. Ambrosio CERN assumed time [working days] Coil Wind / Cure15 20 Coil React23 22 Coil Impreg25 23 Coil Instrumentation10 9 Due to the furnace dimension we plan to react 2 coils at the same time As consequence the tooling will multiplied in 4 Estimated cost 1 full winding-> impregnations tooling line CHF Estimated cost for 4 sets CHF. This action reduce the apparent coil production time from about 70 working days down to 25

Production personnel identified and available teamCERN staff [n] External field support [n] Envelope occupation time CERN staff FTEFSU FTECERN costsFSU costs Winding team years kCHF160 kCHF Reaction team kCHF330 kCHF Impregnation team kCHF330 kCHF Instrumentation team kCHF80 kCHF Assembly team years11150 kCHF110 kCHF supervision kCHF0

Planning issues not accounted for Christmas holiday: 2 weeks of closures. At the end 6 weeks of delay to be added Summer holidays: 1 month at 50%-> other 6 weeks to be added at the end of the planning LS1 aleas: any request of help from tunnel will be in priority. Other projects: 11 T reaction shall be completed in 2013 and FRESCA2 reaction performed in the 1 st 3 quarters of 2014

Conclusions Identification of the personnel for development is the issue. Also stopping few project the resources found are ineffectively spread Lack of resource to follow up the tooling development and procurement at tech. engineering level Coil production and magnet assembly seems feasible from the plan and resource availability (if budget available)