High-pressure gas pipelines projects JASENOVAC VEL. KLADUSA BOS. BROD BOS. DUBICA BOS. NOVI BOS. GRADISKA BOS. SAMAC ORASJE CAZIN LAKTASI DERVENTA MODRICA TR.RASTELA BOS. KRUPA PRIJEDOR PRNJAVOR GRADACAC BRCKO BIHAC BANJA LUKA PTG1 DOBOJ BIJELJINA PTG4 SANSKI MOST GRACANICA PGG4 TESANJ PTGS6 KLJUC MAGLAJ LUKAVAC Tetima PETROVAC ZEPCE TUZLA SEPAK ZAVIDOVICI TPP ZVORNIK JAJCE ZIVINICE SEKOVICI ZENICA PTG3 KLADANJ TRAVNIK TPP VLASENICA BUGOJNO KAKANJ OLOVO SREDNJE BRATUNAC VISOKO G. VAKUF BRNJACI ILIJAS SEMIZOVAC TOMISLAVGRAD SARAJEVO JABLANICA GORAZDE KONJIC SPILT POSUŠJE PTG2 MOSTAR CAPLJINA 6/7th april 2010 PLOCE NEUM
Natural gas sector highlights – opportunities for future development
Natural gas network development – defined in the Strategic plan and program of development of energy sector in Federation BiH
BH-GAS d.o.o. Sarajevo
Transmission gas pipeline Bosanski Brod - Zenica Length: cca 130 km Diameter: 16 inch/20 inch Working pressure: 50 bar/75 bar Max. capacity: 1.0/2.0 billion m3 Investment value: 16 inch cca 45 million EUR 20 inch cca 57 million EUR Project status: completed feasibility study Investment cycle: 2011 – 2014 Note: In parallel with transmission gas pipeline construction, local authorities will start activities on distribution network development
GASIFICATION OF UNA-SANA CANTON PROJECT PHASE I: Pipeline Trzac - Cazin - B. Krupa with branches to Bihac and Velika Kladusa Length: 40 km (branches 40 km) Diameter: 20 inch (10.75 inch) Working pressure: 50 bar Investment value: cca 25 million EUR PROJECT PHASE II: Pipeline Bosanska Krupa – Kljuc PROJECT PHASE III: Pipelines Kljuc – B. Petrovac and Pecingrad – Buzim _________________________ Project status: Tender for Detailed Design for Phase I Maximum capacity: 1 billion m3 Investment cycle: 2010 – 2013 Note: In parallel with transmission gas pipeline construction, local authorities will start activities on distribution network development
GASIFICATION OF CENTRAL BOSNIA CANTON PROJECT PHASE I: Lasva Region, Pipeline Zenica - Travnik Length/Diameter: cca 40 km/16 inch Max. estimated consumption: cca 80 million m3/year Investment value: cca 17 million EUR PROJECT PHASE II: Vrbas Region, Pipelines Travnik - Gornji Vakuf and Travnik – Jajce _______________________________ Project status: planned construction within Phase I Maximum capacity: 1 billion m3 Investment cycle: 2010 – 2011 Note: In parallel with transmission gas pipeline construction, local authorities will start activities on distribution network development
TRANSMISSION GAS PIPELINE SARAJEVO - MOSTAR - PLOCE Length: cca 175 km Diameter: 16 inch/20 inch Working pressure: 50/75 bar Max. capacity: 1.0/2.0 billion m3 Investment value: 16 inch cca 59 million EUR 20 inch cca 73 million EUR Project status: Techno-economic study completed Investment cycle: 2014 – 2017 Interconnection on croatian transimission gas system Note: In parallel with transmission gas pipeline construction, local authorities will start activities on distribution network development
TRANSMISSION GAS PIPELINE POSUSJE - TOMISLAVGRAD -BUGOJNO Length: 107 km Diameter: 16/20 inch Working pressure: 50/75 bar Investment value: 55 million EUR Max. capacity: 1.0-2.0 billion m3 Investment cycle: 2011-2014 Project status: completed feasibility study Note: In parallel with transmission gas pipeline construction, local authorities will start activities on distribution network development
NATURAL GAS INTRODUCTION IN TPP KAKANJ Cooperation of BH-Gas and Power Utility EPBiH Project status: completion of the Techno-economic study by the middle of 2010 Planned CCGT with capacity of 100 MW --------------------------------------------------- Precondition construction on compressor station: estimated value cca 10 million USD Tender for Basic Design in 2010
UNDERGROUND NATURAL GAS STORAGE IN SALT TETIMA Minimal usefull volume of storage: 60 million m3 Number of storage caverns: 4 Investment value: I option: cca 42 million EUR II option: cca 44 million EUR III option: cca 35 million EUR Project status: completed Pre-feasibility study