LHC “progress” Wednesday 29 th April 2015 Coordination: Mike Lamont, Wolfgang Hofle.

Slides:



Advertisements
Similar presentations
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Advertisements

Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
LHC progress week 19 Monday 11 th May 2015 Coordination: Jan Uythoven, Massimo Giavannozzi, Mike Lamont.
LHC progress Saturday 2 nd May 2015 Coordination: Mike Lamont, Wolfgang Hofle.
LHC progress Thursday 30 th April 2015 Coordination: Mike Lamont, Wolfgang Hofle.
LHC 18 & 19 April 2015 At 450 GeV with bumps, no increased MUFO activity. Beam screen 15R8 warming up to 80 K, ongoing for the day 09:00: Orbit studies.
LHC 15 April :19: UFO event detected by on BLM 15.R8 and beam dump 8:46: P2 cold compressor trip and recovery during morning shift. Access given.
Friday, h10: Stable beams at 1.38 TeV. 09h03: Beam dump.  One bunch dropped too much in intensity and gave BPMS interlock (dump protection). 10h36:
Monday 4 th to Friday 8 th Technical stop  Coordination: Katy Foraz  Machine back to Operations Friday evening on schedule Major cryogenics intervention.
PROFIBUS controller problem (SEU) on cryo valve on DFBMH (600 A circuit RQ6.L7B1/2). Loss of cryo maintain ==> Beam dump. End of fill #1975 after ~2.5.
Wednesday 12 th September Pumping, removal of vacuum equipment from tunnel in the morning TOTEM & ALFA, RP movement tests: OK 11:50 pre-cycle started,
Tuesday 10 th April - morning Access for:  point 3 Jerome Landaro TCSG one jaw didn't move  point 5 Qps expert on RPMBB.UJ56.RCBXH1.R5  point 6 TCDQ.
21/05/2012LHC 8:30 meeting Overview Week 20 Injectors, LHCb polarity, Beam-Beam Coordinators: Bernhard Holzer, Jan Uythoven.
LHC progress with beam & plans. Of note since last time Transverse damper Beta beating in the ramp Collimation set-up at 450 GeV & validation LBDS – systematic.
Sat 18/6 – Sun 19/6 07:48 Beam dump due to spurious interlock from BIS 08:30 access BIC repair. RF intervention in parallel. 13:00 Intervention on BIC.
5/11/2012LHC 8:30 meeting Summary of Week 44 Coordination: Mike Lamont & Jan Uythoven.
Monday 29 October 08:48 V/dM scan CMS end of fill #3236. Check of “fast scan”. 10:06 V/dM scan finished, start of RF studies, reducing RF voltage. 11:10.
● 08:30 Loaded by mistake squeeze function to 2 m  Dumped beams ● 10:30-13:00 Test of new algorithm for long. Emittance blow-up to minimize oscillations.
“we believe the reason why the first bunch is more intense than the following 3 is that it's on that one that the SPS RF loops are locked” Philippe & Django.
Friday March 4 th LHC morning report the short story: from a global point of view we had basically only one access !!!
Monday h00: End of fill #1640: 3.7 pb h14: RB S12 and S23 tripped before loading rampdown table, active filter. MPE piquet. Fip_Com_Lost.
RHIC Run14 Time Meeting. Run14 Status – Apr. 15 Operations running well, 12 stores over the past 7 days with 1 lost to another “super quench”. Testing.
RHIC Run14 Time Meeting. Run14 Status – Apr. 22 Operations running well, 12 stores over the past 7 days with 1 “super store” of 17 hours. Repositioned.
LHC Progress Friday 30 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
LHC Progress Thursday 29 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
Last night Lhc closed 15:00 Beam on Ti 8 /Ti2 Prepulse check synchronisation ok with LHCb /RF 17:00 Open Point 4 PC’s and RF 19:00 LBDS energy tracking.
Shortened program (2 days), as decided in LMC. MD program worked very well  all MD’s on plan with ~foreseen beam time. LHC in very good shape with excellent.
Monday 12 th November 04:50 Beam dump, trip of RF line 4B, integrated L ~120 pb-1. Access for RF. 07:00 Injecting. FBCT phasing. Line steering. 09:59 Beam.
LHC progress Sunday 3rd May 2015 Coordination: Mike Lamont, Wolfgang Hofle.
LHC progress Tuesday 28 th April 2015 Coordination: Mike Lamont, Wolfgang Hofle.
08:30 Machines in stand-by 12:30 Access in LHC for QPS and PC:  QPS quench heater power supply RB.A12  EPC for RSF2.A67B2 and RQ9.R8B1.  RCBH27.L1B2.
LHC Fri 6 & Sat 7 Nov :00 End instabilities MD, dump to refresh air at dump TDE cavern 08:00 Access for vacuum team at the TDE starting 10:30 Access.
Tuesday 24 th July - morning 10:15 Operator dump of fill 2873  Initial luminosity: 5.83e33 cm-2s-1  12 hours stable beams  151 pb-1 delivered  Initial.
Outline of 2014/2015 plans V. Kain, M. Lamont, J. Wenninger 6/18/2013Optics Measurement and Correction Review
06:00 – Ongoing injection problems on beam 2  07:42 – Start of injection investigations  11:11 – Injection problem fixed. Resteering of transfer line.
– Machine closed. Ramp for powering tests & pre-cycle – Pilots through nominal cycle up to collisions. Measure chroma during squeeze. Check dump of pilots.
Saturday 11.9 ● From Friday – Minimum required crossing angle is 100  rad in 2010 – Plenty of aperture at triplets: > 13  (n1 > 10) – Can stay with 170.
LHC 8 & 9 May :10: Injection kicker B1 faulty on oil level –Check in UA and RA. Leaks fixed, to be further checked in TS1 10:30: Pre-cycle started.
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
Thursday 20 th April 01:53 RCBV17.R7B2 tripped as happened few days ago: SIS intercepted. 05:54 Stable beams, 1380b, still RF problems B1, abort gap cleaning.
Another typical LHC day. 06:15 Fill 2000 dumped 08:44 Stable beams – fill 2001  1.675e14  1.21e11  ~2 microns normalized emittance 11:34 Beams dump.
04h36: Cryo problem in arc 81. Access. 09h14: Injection.  TI8 injection collimator setup.  Testing new sequence.  New version of vacuum application.
:00 meetingEBH 1  6:39 beam dump by BLM 655ms RS on BLMEI.05L4.B2E10_MBRB (which is downstream of BSRT B2).  The losses increased during.
Monday 19 th March 07:33 Lost (another) beam in the squeeze, beyond 2 m, B2 hits 1/3 resonance. 08:30 Start (another) ramp  Try to correct coupling and.
Tuesday 3 rd October STABLE BEAMS until 12:25 when we switched to ADJUST for a EOF test for Tobias  dump B2 first and then B1.  Dump at EOF test because.
LHC Status Sat Morning 30-June Bernhard Holzer, Jan Uythoven Status Friday Late: preparing restart some issues... LHCb dipole tripped / router problem.
Saturday Coordinators weekend: Mike Lamont, Eva Barbara Holzer
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Summary Friday h38: Ramp down and pre-cycle.
Tuesday Fill lost #1855 at 7:28 due to the trip of RQX.R1. This was traced to a software bug in the FGC… The Class 51 (LHC_PC) FGC software has been upgraded.
Monday 11/07: Recovery Plenty of accesses.
Saturday 30th June - Sunday: Rocky !
02/08/ :35: Lost access chain in point 2 (PX24 PAD)  Dump after ~14.5 hours ~100 nb-1.
Thursday morning – optics correction
Saturday 2/4/ :00-09:00 Problems with SPS:
MD#2 News & Plan Tue – Wed (19. – 20.6.)
04-05/08/2010 End of physics at ~11:00 after 18.5 hours ~120 nb-1.
Summary of week 19 Machine Coordinators: G. Arduini, M. Lamont Main aim: Luminosity production.
Wednesday 10:00 test of the un-squeeze to 90 m at 4 TeV.
Friday 14th September 03:15 Beta* at 1 km. Optics measurements, see yesterday. 07:00 Dump. 08:00 Refill with 3 nominal bunches for high beta. 11:15 Beams.
LHC - Week 38 Technical stop: Katy Foraz
Friday 28 October 2011.
Summary Tuesday h23: Machine closed. Precycle started.
Wednesday 23/2 Thanks CRYO!!!.
Thursday
Friday 15th February - morning
Wednesday 26 October 2011.
Thu :00 Dumped beams, refill for Pb-Pb physics. No more protons in 2011… Some changes: Increase of flat top total voltage to 14 MV. Feed-forward.
Presentation transcript:

LHC “progress” Wednesday 29 th April 2015 Coordination: Mike Lamont, Wolfgang Hofle

Morning 07:30 beam eventually back in after LBDS switch change/accesses/Q5.LR7 etc 09:00 cancel TDI set-up to allow resolution of inhibiting BLM problem in the SPS preventing start of NA physics 450 GeV – testing LHC tune chirp on beam 2 (Marek, Daniel, Maria). ADT is working. Tried tune chirp since 9:20h on B2. For now tune chirp is not working. Access needed to check where the problem is. 10:10 Ramp Flat-top: – K-modulation – Initial BPMSX tests – bumps – BSRT

Midday – major event 1 - BA6: 11:28: We saw an emergency stop alarm in BA6, the button was pushed by an EN-CV technician on-site who saw smoke coming from an electrical breaker. – This breaker was later confirmed to be for the power supply for HIRADMAT. 11:46 The emergency stop cut all power, including to the cooling towers of BA6, and worse yet the ”WSSPS” pumping station from SIG that also supply the CRYO in SM18 and the pressure for the whole SPS. – We saw the WSSPS alarm immediately and followed the temperature live with the cryo operator, degree by degree.. The electrician was literally running to try and switch back on the WSSPS in time, but was less than a minute late! 11:56 CRYO lost in SM18. 12:15 Most cooling systems up and running again. The breaker that caught fire was pulled out, to allow for a quicker restart since HIRADMAT is not to be used before Friday. Jesper Nielsen

12:30 Major event 2 12:27 All cooling distribution circuits for the SF6 cooling towers stopped. We actually managed to restart the most important remotely, but the CRYO had interlocked immediately on a cooling fault. We lost the CRYO and also the compensator in LHC6. Our first idea is that we tripped on a low level in the cooling towers, looking at the trends we see a level going down steadily since yesterday at 20h. But that has to be verified with CV. 12:30 Called in the expert from EN-CV, he will go on-site immediately. 12:58 The compensator was put back in service and all systems are good to go again. Jesper Nielsen

28/4 Primary water stop in point 6 Failure of the filling valve: the axle of the valve disconnected from the actuator Serge Deleval

28/4 Primary water stop in point 6 One low level alarm based on the analog measurement of the basin level Two level switches which is stopping the whole system Why no alarm before the stop ? The two level switches was activated at ≈1600 mm (nominal 700mm) higher than the low level alarm The good functioning of the level switches at the good level was validated the 5th of November 2014 during the maintenance The level switches partially detached from their support. Action taken: the filling valve was temporarily repaired Increased to low level alarm to 1800 mm Action foreseen during TS1: Replace the filling valve Check the level switches Serge Deleval

Access in shadow of cryo recovery Update on the BLM system: – access to replace filter-box in B6R2 – update on the Connectivity Check limits (part of the Sequencer BLM Sanity Checks) calculated with modulation data collected since Easter. Aim is to reduce the number of false positives (seen many especially in points 6 and 7). ADT to investigate chirp issue

Wednesday AM 00:00 Cryogenics back QPS problem: 4 QPS controller on the same crate are stuck (DQGPU.05RR73) – Fixed by piquet (Stephen Pemberton) 00:35 Precycling 01:45 Beam back ULO scan 04:00 Lost CRYO conditions in MSR1. – wrong temperature measurement that caused a valve on a DFB to close. Quick recovery. Precycle need 06:00 Injecting for interlocked BPM set-up

Interlocked BPMs Summary of this Tuesday morning tests at top energy with pilot – The new firmware was tested without the FESA class running and the BIS reacts correctly when sending dump signals from the firmware. – The FESA class was started and no spurious dump were observed so far. – The calibration of B1 R was tested using +/- 0.5mm orbit bumps. Test without beams during afternoon: – Using calibration signals – Check logging and post mortem buffer (capture data for IntBPM) Ongoing (Wednesday) morning: – Scrape nominal bunches at injection to validate the new high/low sensitivity ranges – Orbit bumps or change the MPP limit to make sure the system works correctly – Full qualification with MPP (procedure specified by Jan) – Start to run the interlock process unmasked Thibaut Lefevre and team

ULO scan this night More-or-less as measured on Sunday Delphine/Stefano

Longitudinal blow-up blues Currently Heiko implemented a long blow-up in the PS for the probe so that the bunch length at extraction of SPS is 1.4 ns to 1.5 ns at SPS extraction to best mimic a nominal bunch in LHC, as requested by Philippe. – 1.4 ns coming out of SPS – ~1 ns after capture Last Thursday night, we have tested an upgraded version of the LHC long. blow-up. The test was not conclusive The problem was traced to the algorithm generating the phase noise excitation and it has been solved. So we are now ready for a second test. The plans: – First a test at 450 GeV (1 hour) – Then, but not necessarily just after the previous test, a first ramp with the new algorithm – Our RF controls expert must be present. Can we have a timeslot on Wednesday or Thursday? Philippe.Baudrenghien

INCOMING

MUFOs/ULO Beam screen now at around 80 K (second warm- up – prolonged this time) MUFOs appear to be supressed by beam screen warm-up – But perhaps not definitively Some indications of vertical movement of restriction Questions: – Does restriction move with BS temperature? – How does restriction behave with higher intensities?

Machine protection Markus Zerlauth

Today Tests of BPMSX (interlocked BPMs) - ongoing Measure 15R8 aperture - beam screen cold Global aperture measurement Longitudinal blow-up TDI set-up

Batch-by-batch blow-up Philippe would also like to proceed with re-commissioning of the batch-by-batch long blow-up in LHC which would permit to have bunches of different distribution and use this for method for momentum collimation set-up. They discussed this with Stefano. In order to get the batch-by-batch mode for the long. blow- up working Mic Jaussi would need 30 minutes to 1 h to qualify his software with probe beam at 450 GeV before any attempt to use it operationally. Can ? e slot this in some time perhaps in parallel to the ULO scans on beam 2. Mic said he is available and I think it can be first tried with beam 1.