Service Review and Plans Carmine Cioffi Database Administrator and Developer 3D Workshop, Barcelona (ES), April 2009
Guess Where? 2
3 BARCELLONA POZZO DI GOTTO Messina
Outline Systems Overview Oracle configurations Hardware Specifications Issues Future plans 4
Systems Overview ATLAS: 3 nodes RAC (OGMA) –third node added last week !!! LHCb: 2 nodes RAC (LUGH) ATLAS LFC: single instance FTS: single instance TAG: single instance 5
Oracle configuration OGMA and LUGH: –Oracle –Jan 09 CPU –Processes = 800 –Sessions = 885 –open_cursors = 300 –_buffered_publisher_flow_control_threshold = –_db_block_numa = 1 –_enable_NUMA_optimization = FALSE –_job_queue_interval = 1 –streams_pool_size = 608MB ATLAS LFC: –Oracle –July 08 CPU –Processes = 150 –Sessions = 170 6
Oracle configuration FTS: –Oracle –Jan 09 CPU –Processes = 350 –Sessions = 390 TAG: –Oracle –July 08 CPU –Processes = 150 –Sessions = 170 All systems are supported 24/7 7
Hardware Specification OGMA and LUGH: –32bit –Red Hat Enterprise Linux AS release 4 (Nahant Update 7) –RAM: 4GB –Single Dual core AMD Opteron 2.4GHz –Third node: Two dual core AMD Opteron 2.4GH RAM 8GB even though it uses only 4. LFC: –32 bit –Red Hat Enterprise Linux AS release 4 (Nahant Update 7) –RAM: 4GB –Dual core Intel(R) Xeon(TM) CPU 2.80GHz 8
Hardware Specification FTS: –32 bit –Red Hat Enterprise Linux AS release 4 (Nahant Update 7) –RAM: 4GB –Dual core Intel(R) Xeon(TM) CPU 2.80GHz TAG: –32bit –Red Hat Enterprise Linux AS release 4 (Nahant Update 7) –RAM: 4GB –CPU: Dual quad core Intel(R) Xeon(TM) CPU 2.80GHz 9
Issues Little memory especially for LFC and FTS OGMA and LUGH run on old machines and are out of warranty No hardware redundancy: single path, single switch and single disk array Lost one of the TAG disk array. At the moment the database is broken Mix hardware (OGMA) 10
Future plans Move to new hardware Install Oracle 64 bit Add more RAM Add hardware resilience Migrate FTS and LFC to 3 nodes RAC (6 th May 09): –RAC already installed –64 bit system –8GB RAM –Two Dual Core AMD Opteron(tm) 2.4Gh Looking into offsite availability 11
Estimated dates for migration 3D ATLAS ~mid June 3D LHCb ~end August TAG ~beginning of September 12