10/03/021 2002 Report on Existing and Potential Electric System Constraints and Needs Within the ERCOT Region October 3, 2002.

Slides:



Advertisements
Similar presentations
Additional CREs to address Stability Limits Beth Garza TAC June 26, 2008.
Advertisements

Houston Region Import Capacity Project Planning for Reliable Power.
October 16, 2009 RPG Meeting ERCOT RPG Project Review Update Jeff Billo.
Regional Planning Group Project
2004 Congestion Costs. 2 Transmission Congestion Occurs when analysis shows a given outage of a transmission element (contingency) will result in the.
1 Regulatory Developments and Impacts Involving Electricity Storage in Texas Elizabeth Drews 31 st USAEE/IAEE North American Conference Austin TX, November.
Houston Import Evaluation Cross Texas Transmission & Garland Power & Light ERCOT RPG Meeting August 27th, 2013.
Economic Criteria for Transmission Planning in the ERCOT Region Public Utility Law Seminar DeAnn Walker August 3, 2012.
THE POWER OF POSSIBILITY Electric Transmission System Development in Alberta Neil J. Brausen, P. Eng., Director System Planning APEGGA Calgary Branch Luncheon.
January 5, 2012 TAC Cross Valley 345 kV Project Jeff Billo Manager, Mid-Term Planning.
The Status Of The Electric Grid In ERCOT The Electric Reliability Council Of Texas Sam R. Jones, P.E. ERCOT – Retired As a retiree of ERCOT this presentation.
Federal Energy Regulatory Commission Large Generator Interconnection Final Rule RM July 23, 2003.
RenewElec October 21, 2010 Robert Nordhaus, David Yaffe Van Ness Feldman 1050 Thomas Jefferson Street, NW Washington, DC (202) FERC’s.
U.S. Energy Information Administration Independent Statistics & Analysis EIA Reporting Proposal: Balancing Authority Hourly Operating Information.
ISO Grid Planning Presentation to CREPC October 1, 2002
JACKSBORO TO WEST DENTON 345-kV PROJECT Presentation to Technical Advisory Committee April 8, 2004 Transmission Services Operations.
Warren Lasher Director, System Planning October 4, 2014 Our Energy Future.
System Operations Staffing Request Presented to the ERCOT Board Of Directors By Sam Jones, COO November 16, 2004.
Eagle Crest Energy Company February Page 2 New Hydro: Making it Happen Background on the Eagle Mountain Pumped Storage Project Need for Eagle.
NRG Comments/Concerns with HIP Assumptions January 21, 2014 RPG Meeting NRG Comments/Concerns with HIP Assumptions - January 21, 2014.
Reliable Power Reliable Markets Reliable People Performance Targets for the Customer Interconnection Process January, 2008.
DC Tie Reservation and Scheduling with Mexico Shams Siddiqi representing Sharyland Utilities WMS Meeting May 15, 2007.
POWER SYSTEM PLANNING CHARTER AND PROCESSES Presentation to TAC 10/09/2003 KENNETH A. DONOHOO, P.E. Manager of System Planning Transmission Services
Public Meeting on ERCOT’s Proposed 2004 Budget September 3, 2003 Preliminary - Subject to ERCOT Board Approval.
1 WMS Report To TAC September In Brief Four Working Group Reports Four Working Group Reports One Task Force Report One Task Force Report Three.
LAREDO PLANT RMR EXIT STRATEGY Presentation to Board of Directors March 16, 2004 Transmission Services Operations.
March 11, 2011 RPG Meeting Lower Rio Grande Valley (LRGV) Import.
John Dumas Director of Wholesale Market Operations Jeff Billo Manager of Mid Term Planning Dan Jones Director with Potomac Economics, the ERCOT IMM Board.
Presentation to House Regulated Industries Committee Chairman Phil King Trip Doggett Chief Operating Officer The Electric Reliability Council of Texas.
MISO Northwest Exploratory Study Presented to National Wind Coordinating Committee Participants in study – MISO, Various utilities in Minnesota, North.
PRR 547 – Trading Hubs CMWG Presentation to WMS October 21, 2004.
1 Market Evolution Program Long-Term Resource Adequacy Regulatory Affairs Standing Committee Meeting May 14, 2003.
POWER SYSTEM PLANNING CHARTER AND PROCESSES UPDATES Presentation to TAC Sept 9, 2004 Transmission Services Ken Donohoo, Manager of System Planning
Updated 1/28/2011.
WEST LEVEE TO NORWOOD 345-kV PROJECT Presentation to Technical Advisory Committee April 8, 2004 Transmission Services Operations.
Electric Reliability Council of Texas (ERCOT) A Success Story… In Progress Ingmar Sterzing United States Association of Energy Economics (USAEE) Pittsburgh.
LAREDO RMR EXIT STRATEGY Presentation to Technical Advisory Committee March 4, 2004 Transmission Services Operations.
Reliable Power Reliable Markets Reliable People Hanna Region Transmission Development Ramaiah Divi, P.Eng Manager, Central System Planning.
Yellowhead Area Transmission System Development
ERCOT MARKET EDUCATION Retail 101. Legal Disclaimers and Admonitions PROTOCOL DISCLAIMER This presentation provides a general overview of the Texas Nodal.
SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX.
TAC02/01/2007 DW 1 TAC Briefing on: - Report on Constraints and Needs: Five Year Plan Development - Long Term System Assessment (LTSA) - Entergy Integration.
Wholesale Market Subcommittee Update May 2 nd, 2013 Technical Advisory Committee.
2010 CSC & Zone Selection: 6 Lines W-N & 4 Zones (WN2_SN0-4Z) Shams Siddiqi, Ph.D. Crescent Power, Inc. (512) August 19,
ERCOT TAC11/2/ CREZ Study Update ERCOT TAC 11/2/2006.
TRANSMISSION CONSTRAINTS KENNETH A. DONOHOO, P.E. Manager of System Planning, Technical Operations
1.
ERCOT CSC – Vote “Yes” to 3b Jan A. Bagnall Sr. Director Transmission, Reliability & Compliance October 2008.
October 16, 2009 RPG Meeting ERCOT Independent Review of the Corpus Christi Improvements Project Jeff Billo.
Current Operational Challenges Computing the West – North Limits Potential IROLs Local Voltage & Thermal issue (OOME) High Voltage Outages.
LCRA TSC/ CPS Energy Transmission System Addition Regional Planning Group Project Jeff Billo Sr. Manager, Transmission Planning TAC ERCOT Public March.
RPG: September 24, Long-Term System Assessment Introduction Jeff Billo, Manager, Transmission Planning September 2013 Regional Planning Group.
ERCOT Public 1 Project Panel 1 Dan Woodfin Director, System Operations August 15, 2014.
September 1, 2011 TAC Lower Rio Grande Valley Regional Planning Group Project Jeff Billo Manager, Mid-Term Planning.
Planning for Texas’ Energy Future Select Committee on Electric Generation Capacity and Environmental Effects Bob Kahn President & CEO February 6, 2008.
Role of Account Management at ERCOT 2006 TAC Subcommittee Review ERCOT Board February 21, 2006.
May14, 2010 RPG Meeting Houston Import Study Update Jeff Billo.
Oncor Transmission Service Provider Kenneth A. Donohoo Director – System Planning, Distribution and Transmission Oncor Electric Delivery Co LLC
1 TAC Report to the ERCOT Board November 14, 2006.
POWER SYSTEM PLANNING CHARTER AND PROCESSES Presentation to TAC May 6, 2004 Transmission Services Ken Donohoo, Manager of System Planning Dan Woodfin,
2006 Report on the Capacity, Demand, & Resources for the ERCOT Region Technical Advisory Committee June 1, 2006 Kenneth A. Donohoo. P.E. Manager, Transmission.
ERCOT Transmission Planning Process Overview and Recommendations November 6, 2002.
2006 Reliability Study James Manning Bryan Guy May 12, 2006.
03/06/2008 TAC CREZ Transmission Optimization (CTO) Study Update Dan Woodfin Director, System Planning.
Congestion Management Work Group 2008 Overview CMWG Marguerite Wagner, Reliant Energy Inc.
Houston Area Constraint Mitigation Project ERCOT Board of Directors March 15, 2005.
CSC DETERMINATION PROCESS
SYSTEM PLANNING THE KEY TO RELIABILITY AND A LIQUID ELECTRIC MARKET
The New Texas Wholesale/Retail Market
31st USAEE/IAEE North American Conference
Presentation transcript:

10/03/ Report on Existing and Potential Electric System Constraints and Needs Within the ERCOT Region October 3, 2002

10/03/022 Contents Transmission system and constraints overview Cost of CSC and Local congestion Completed transmission Transmission underway Transmission under review ERCOT generation and demand outlook Transmission planning outlook

10/03/023 Transmission System Backbone for retail and wholesale competition Complex network –Not a one way system –Flows change with changing system conditions –Events on the network can have far reaching effects across the whole system Under rapid and continuous change –New generation interconnections –Generation retirements –Transmission upgrades

10/03/024 Transmission Constraints Function of the impedance and voltage of network Three types of limits: –Thermal Limits –Voltage Limits/Stability –Unit Stability Limits

10/03/025 Complicates system security management Leads to economic inefficiencies Creates captive markets Reduces liquidity of the market Creates for “Must Run” generation Reduces utilization of efficient units Creates opportunity for market power Transmission Constraints’ Impacts:

10/03/ Commercially Significant Constraints (CSCs) and Local Constraints (LCs) Wind Significant LC Areas Valley Laredo Wind North Austin San Antonio Corpus Christi West

10/03/027 Congestion Costs

10/03/028 TCRs and Direct Assignment Costs

10/03/029 Limestone-Watermill 345-kV Double-Circuit Line Monticello-Farmersville 345-kV Line Lon Hill-Rio Hondo and Lon Hill-Edinburgh 345-kV Lines Series Capacitor Compensation Military Highway STATCOM Laredo STATCOM San Miguel-Pawnee 345-kV Line and Establish Pawnee 345-kV Station Centerville Switch-McCree Switch 345-kV Line White Point 345-kV Switching Station and 138-kV Upgrades Cedar Bayou-King-North Belt-TH Wharton 345-kV Corridor Upgrades Many 138-kV and 69-kV System Additions/Upgrades including Autotransformers Completed Transmission

10/03/0210 Morgan Creek-Twin Buttes-Red Creek-Comanche Switch 345- kV Line Graham-Jacksboro 345-kV Line Farmersville-Valley Junction-Anna Switch 345-kV Line Paris-Anna 345-kV Line Venus-Liggett 345-kV Line Edinburg-Bates-McAllen 345-kV Line McAllen-Brownsville-La Palma 345-kV Line Pawnee-Coleto Creek 345-kV Line Many 138-kV and 69-kV System Additions/Upgrades including Autotransformers Transmission Underway

10/03/0211 Dallas/Fort Worth Jacksboro-West Denton 345-kV Line Jacksboro-Willow Creek-Parker 345-kV Line Upgrade West Denton-NW Carrollton 345-kV Second Circuit Watermill-Cedar Hill 345-kV Second Circuit Anna Switch-Collin-NW Carrollton 345-kV Line Upgrade South to North and South to Houston Salem-Bryan/College Station-TNP One 345-kV Line and Establish New 345/138-kV Station Clear Springs-Zorn-Harris Branch-Gabriel-Salado 345-kV Line Cuero-Holman 345-kV Line and Establish Cuero 345-kV Switch Station Coleto Creek-Cuero 345-kV Line Whitney-Concorde 345-kV Line Twin Oak-Lake Creek 345-kV Second Circuit Transmission Under Review

10/03/0212 Laredo and Valley San Miguel-Laredo 345-kV Line Laredo-Bates-Edinburg 345-kV Line West Texas to North Texas and Wind Area Red Creek-Comanche Switch 345-kV Second Circuit Twin Buttes-McCamey 345-kV Line and 345/138-kV Autotransformers Comanche Switch-Killeen Switch 345-kV Line Many 138-kV and 69-kV System Additions/Upgrades including Autotransformers Transmission Under Review (cont.)

10/03/0213 Overview of ERCOT Load Typical picture:  Load growth reflects historic “load management” efforts Demand participation opportunities: Energy price reductions Lower probability of outages

10/03/0214 ERCOT Capacity and Demand ERCOT Generation Capacity and Demand MW Total Capacity w/o units >50 years Capacity w/o units >40 years Capacity w/o units >30 years Peak Demand at 2.1% growth Demand

10/03/0215 Transmission Planning Process  Propose needed bulk transmission facility additions based on identified constraints.  TDSPs  ERCOT  Any interested party  Conduct regional planning evaluation  Conduct an open process of public review and comment on proposed facility additions through committees.  Submit all final recommended bulk/large transmission facility additions to the ERCOT Board of Directors.  Determine the designated transmission service providers of the additions.  Notify the Public Utility Commission of Texas (PUCT) of all Board supported transmission facility additions and their designated providers.

10/03/0216 Regional Planning Groups ERCOT Regional Transmission Planning Process –Includes TDSP’s and PUCT Staff –Confidentiality Major Issue Market Sensitive Information –Review by Stakeholders via Committee’s ROS, WMS, TAC Large projects reviewed by ERCOT Board of Directors –Final Authority is PUCT in the form of a CCN

10/03/0217 Key Issues in Planning OLDNEW Planning Coordination Generation and transmission planned within vertically integrated utilities Competitive generation and regulated transmission; coordination more difficult to achieve Level of Adequacy Determined by utility with approval from regulator Generation adequacy being defined; Transmission adequacy determined through public process with regulatory approval Lead Times for Planning & Construction Long lead times for new generation; shorter lead times for transmission The opposite is normally true Roles of Markets & Regulation Regulation and planning dominate adequacy decisions Markets dominate generation adequacy decisions (and operational decisions) and affect transmission adequacy decisions

10/03/0218 ERCOT’s Perspective  Focus on security of the entire control area  Take multiple needs and plans into account  Look beyond specific entities’ requests  Identify broader regional needs  Promote efficient use of transmission corridors  Promote margins on new transmission additions  Consolidate projects where practical  Ensure compliance with ERCOT planning criteria

10/03/0219 Planning Internet Links SYSTEM PLANNING – –Capacity, Demand & Reserve Reports (CDR) –Generation Project Interconnection Information DETAILED SYSTEM PLANNING DATA & TRANSMISSION MAPS – –Includes data sharing items with transmission plans of TDSP’s –Includes Power Flow Base Cases –CSC detailed data & CM zone maps –Controlled access area due to security requirements MANUALS, DOCUMENTS AND REPORTS – –Demand & Energy Reports (D&E) Includes ERCOT Load by Settlement Period for Each Month –Historical ERCOT Hourly Load (FERC 714)

10/03/0220 Questions?