Bubble Chamber Installation Kick-Off Meeting May 28, 2014, Grames Let’s discuss two jobs between the cryounit and injector gate. Bubble chamber (5D) New.

Slides:



Advertisements
Similar presentations
PEPPo Weekly Status Meeting February 16, 2011 & 6MSD Planning Meeting February 23, 2011 Part 1 – Technical summary of layout Part 2 – Month-by-Month Installation.
Advertisements

New 5 MeV Dipole Magnet (“DL”) Planning Meeting May 23, 2014.
INJECTOR TEST FACILITY UPGRADE PHASE I: 5-10 MEV INJECTOR Feb. 7, 2014.
G2P Target installation and Beyond. Schedule Pivot before.
FAC, 10/12/06 D. Schultz 1 e-Beams Systems Update Linac Injector Undulator Production MMF commissioning ARR David Schultz.
TAGGER MAGNET DESIGN Presented by Tim Whitlatch Hall D Tagger Magnet Design Review July 10,
D. Schultz FAC 6/17/08 1 e-Beams Systems Update People Progress the last review LTU and Dump Installation Status Undulator.
A. Bross MTA RF WS August 22, Welcome MTA RF Workshop.
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
Geoff Pile LCLS Und. System Fabrication FAC 29 th, 30 th & 31 st October 2007 LCLS Undulator System Fabrication Schedule FAC.
LINACs Michael Bevins May 17, GeV Upgrade - Beam Transport Injection, Linac, Extraction, & Correctors Preliminary Design and Safety Review.
Bubble Chamber Planning Meeting 04 September
We are Here! Gluex Collaboration Meeting May Engineering Status - Presented by Tim Whitlatch1.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
1 BROOKHAVEN SCIENCE ASSOCIATES Vacuum Systems H.C. Hseuh, Vacuum Group Leader 8 th ASAC Meeting for NSLS-II Project May 10-11, 2011.
Bubble Chamber Experimental Readiness Review September.
05/30/08J. Dunne -- SANE Collaboration Meeting 1 Beamline Status Upstream beamline –Chicane –SEM –Rasters –Girder Downstream beamline –Helium bag –Extension.
ACTIVITY J A J O J A Schedule( ) UCN Timeline & Major Milestones Remove.
09/28/07Shutdown’07 Week 8 F.G. Garcia1 MTA beam line installation Weekly Report September 28, 2007 Period covered: September 24 th September 28 th (Week.
ANU Shutdown Status AEM meeting Cons Gattuso 7 May 2012.
August 05, Startup 2013 Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster  Main Injector Startup.
Injector/Re-injection Chicane Michael Bevins May 17, GeV Upgrade - Beam Transport Injection, Linac, Extraction, & Correctors Preliminary Design.
Experiment beam line installation (9/4/2014) SystemThus FarTo Do Vacuum~ Torr, IP’s on, Vac interlock checkNone Fast valveValve + CCG installed,
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
G2p/GEp Beamline Tim Michalski Project Lead. Beamline Overview Slow Raster Tungsten Calorimeter Upside Down Girder (correctors, BCM, superharp) FZ1 Magnet.
G 0 Coordinator Update & “To-Do List” Joe Grames William & Mary, June 5-6, 2006  Hall C Beam Line Tasks  Accelerator Preparation Tasks  Beam Halo 
Accelerator and NuMI Upgrades Shutdown Update Cons Gattuso July 02, 2012 July 2, 2012 Cons Gattuso1.
J. Alessi Implementation Plan EBIS Project Technical Review 1/28/05 Implementation Plan WBS exists Working on a “bottoms up” cost estimate The following.
Spectrometer Solenoid Fabrication Status and Schedule Steve Virostek Lawrence Berkeley National Lab MICE RAL October 20, 2008.
Beam Line Layout – Cooling Section There seems to be two options for energy measurement: at the 180 dipole and/or in a diagnostic branch at the end of.
The Stripping Foil Test Stand in the Linac4 Transfer Line
PIP Budget Codes Budget FY12 Updates October 19, 2011 PIP Meeting.
Extraction Michael Bevins May 17, GeV Upgrade - Beam Transport Injection, Linac, Extraction, & Correctors Preliminary Design and Safety Review.
SBS Magnet and Infrastructure Status Robin Wines July 2015.
Spectrometer Solenoid Fabrication Update Steve Virostek Lawrence Berkeley National Lab NFMCC at LBNL January 25, 2009.
Spreaders & Recombiners Beam Transport Michael Bevins May 30, GeV Upgrade - Beam Transport Spreader/Recombiner Dipoles and Layout, & Installation.
09/07/07Shutdown’07 Week 5 F.G. Garcia1 MTA beam line installation Weekly Report September 07, 2007 Period covered: August 31 st to September 7 th (Week.
Bubble Chamber Planning Meeting 07 August
August 12, Machine Status: 2013  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac : Roof hatch installed Booster : Magnet.
G2P Installation Readiness. Fast raster & Calorimeter.
Update: Puck and Gun Magnet March 1, Magnetized Gun 2 K 2 CsSb Preparation Chamber HV Chamber.
Design Update Puck and Gun Magnet February 16, 2016.
SPHENIX MECHANICAL D. Lynch August 21, /15/2014sPHENIX Mechanical Design.
DTL prototype summary and production sequence F.Grespan LNL _06_22 CDR.
Warm Girder UHV Components John Heckman Anthony DiPette Vacuum Group 2/29/2016.
Proton PMG September 3 rd 2015 Cons Gattuso AD Shutdown Manager.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
PIP Update May Agenda Summary Update – Activities – Budget – Plans Update Slides – Solid StateTom – ModulatorsRene – High Power Ferrite Testing.
MI/RR Shutdown 2012 Dec Gev Lines/Injection region: Staging equipment, cleaning and prepping new part to start vacuum work. Preparing to modify the.
Proton PMG May 7 th 2015 Cons Gattuso AD Shutdown Manager.
Report Technical Director Storage-Ring-Installation Completed
Why are we removing our very good gun?
WP11: electron and proton beam testing
Linac4-PSB 160 MeV connection readiness review ( TE/VSC )
Bubble Chamber Planning Meeting
Bubble Chamber Summer 2015 Installation and Beam Test Schedule
Bubble Chamber – Beam Requirements
Upgraded Injector Test Facility
J. Seeman Assistant Director for PPA/LCLS
A. Freyberg Aug 2016 ECT’16 =>
Injector / Linac Installation Current Status
Installation and Beam Test Schedule
LCLS Undulator System Status and Schedule
Upgraded Injector Test Facility
Extraction Michael Bevins May 17, 2007
LCLS Undulator System Production Management
LCLS Undulator System Status and Schedule
Cu67 Isotope Radiator & Target
Injector/Linac Design Status C. E
Isotope Readiness Review Run Plans
Presentation transcript:

Bubble Chamber Installation Kick-Off Meeting May 28, 2014, Grames Let’s discuss two jobs between the cryounit and injector gate. Bubble chamber (5D) New fast valve (0L) cryounit gate

5D NEW: 5D NOW: Adding photon collimator/target/dump Upgrading “5 MeV Dipole” Reconfiguring electron beam line

Upgrading “5 MeV Dipole” 1.Plan is to built two (magnet + spare) in-hand by August 1 st 2.Design of magnet complete... waiting on magnet vendor quote. 3.Design of fixture complete … due here this week. 4.Magnet measurement plan discussed last week … looks reasonable. 5.New insitu Hall probe + tunnel meter in-hand … software (Croke) to do controls 6.EGG will swap magnets when NEW is ready, latter half of August 7.Will use same 10A trim PS 8.Will need alignment support … using new fixture 9.Will need to update field map, CED, songsheet, name instances NOW:NEW:

Decommission 5D beam line (prep task for Bubble installation) 1.De-Post dump and dismantle lead hut – done 2.Temporarily disconnect and safe BPM electronics - done 3.Temporarily dismount ITV5D01 electronics 4.De-energize and disconnect power to MQD5D00, MQD5D01 (others have safe connectors) 5.EGG will temporarily isolate quad and dump LCW + viewer air lines 6.EGG will temporarily vent to remove red boxed items

Bubble Installation : one perspective to get overall size / positioning

Old NameTypeProposedComment MBV0L02DipoleMDL0L02Same 10A, but new field map, limits. New Hall probe instrument. MBH5D00HCorrectorsameNo change MBH5D00VCorrectorsameNo change VBV5D00ValvesameNo change VIP5D00Ion pumpsameNo change ITV5D00ViewersameNo change MQD5D00QuadsameNo change IPM5D00BPMsameNo change MBH5D00AHCorrectorsameNo change MBH5D00AVCorrectorsameNo change Bubble Installation (1 st half of beam line, continues on next page)

Old NameTypeProposedComment MQD5D01QuadsameNew position IPM5D01BPMsameNew position n/aCorrectorMBH5D01HNew – needs 1A n/aCorrectorMBH5D01VNew – needs 1A n/aFV gaugeVCG5D01New – fast valve n/aFaraday CupIFY5D01PEPPo cross, Interlock ITV5D01, new LCW spigot, new picoammeter ITV5D01ViewersameNew position, PEPPo cross, Interlock IFY5D01 VIP5D01Ion pumpsameNew position n/aCorrectorMBH5D01AHNew – needs 1A n/aCorrectorMBH5D01AVNew – needs 1A IDL5D01Dump (1kW radiator)sameNew position, Reuse LCW spigot, reuse picoammeter channel n/aPhoton collimatorIPC5D01 ?New, ANL ships copper annulus, S/A support n/aBubble ChamberITG5D01New, ANL ships, installation & S/A support, requires X (TBD) network/video cables to ISB n/aPhoton dumpIDL5D01 ?New, solid aluminum block positioned within 5mm on stand Bubble Installation (2 nd half of beam line, continues from previous page)

Bubble Installation – Supplemental Electron Dump/Radiator Image Dump (radiator) similar to Faraday cup 6mm Cu wall brazed to SS nipple LCW cooled Ceramic joint allow current monitoring Prelim design Final design

New fast valve downstream of cryounit Vacuum (Heckman) + ICN (Kortze) + PSS

Timeline June Final drawings and nomenclature Fabricate & purchase (pedestals, girders, vacuum components) Decommission 5D line components (viewer, magnets) Vacuum work to claim components for new beam line Fast valve install ??? July Complete fabrication Assemble and align new girders in Test Lab Points for new girders + Bubble Chamber Test new Hall probe in tunnel, new picoammeter in ISB Pull any cables Fast valve controls ??? August Receive + measure new dipole magnet Move girders to tunnel, vacuum hookup + alignment Controls hookup, testing Receive, install, align Bubble Chamber from ANL, date TBD

Charge Codes Labor on fast valve or new 5 MeV dipole = ACCCIS / RSRSRC Labor on Bubble Chamber beam line = ACCCIS / ARDSRC Procurements already rather well defined and largely complete, so accompany any unanticipated REQ’s w/ to and

Final Experiment Configuration (TBD): Winter SAD? Target chamber Dipole Beam dump Thin vacuum window One or two (super)harps