Current Design and Implementation Challenges of Road Projects on the Coastland Ron Rahaman Chief Roads and Bridges Officer Ministry of Public Works Works Services Group
Project Life Cycle Project Manager Starting the Project Conceptualized Team Employer Organising & Preparing Feasibility, Planning & Design Consultant Stakeholders Carrying out the works Construct Sponsor Closing the project Contractor Test & Turnover
DESIGN PHASE
Design Phase (Feasibility Study and Tendering) Report submissions Preliminary Assessment Report Highlights the problems, challenges & deficiencies with its current usage Environmental and Social Impact Assessment Report Continuous engagement of stakeholders Compliance with the regulations of the EPA
Design Phase (Feasibility Study and Tendering) Project Selection Report Appropriate remedy to address problems, taking into account stakeholders need, appropriate standards and guidelines, sound engineering principles of safety, economic benefits verses cost of implementation Draft and Final Design Report Comprehensive reports, including drawings, bills of quantities Pre-bidder Conference
Design Challenges Inadequate record Keeping Loss of institutional Knowledge Missing road survey plans / road reserve / acquisition Culture of People / poor enforcement Inter agency coordination Underground utilities / structures
Design Challenges Site Conditions – Swamp, water Budget Constraints – availability, most economic (design / supervision / construct) Weight Control Competitive pricing – Tendering stage Attracting new contractors – Tendering stage Contractor overload – Tendering stage
implementation PHASE
Construction Stage Reports Project Design Review Review of design Review Report of Contractor QA/QC plan Review contractor’s submission Monthly Progress Reports Captures progress of works, issues, etc
Construction Stage Work Program Method Statement To be used by the contractor to plan & execute the works Initial program (First 3 months) Accepted Programme (entire work) Updated Programme (t least on monthly basis) Method Statement Same time with programme General description of the arrangements and methods of construction and temporary works design The statement should be fully cross-reference to the activities in the programme
Implementation Challenges On site Encroachment on road reserve Fences Structures
Implementation Challenges On site Utility Corridor no corridor Inadequate planning leads to poor usage
Implementation Challenges On site Limited road reserve Compromise road geometry By passes
Implementation Challenges On site Change in elevation modification to entrances Drainage issues
Implementation Challenges On site Geological conditions Poor soil Buried structures
Implementation Challenges Environment Time lapse between design and implementation Change in market prices Shortage of construction material Culture
Implementation Challenges Contractor Frequent down time Inadequate human resources Equipment fleet Poor planning / lack of planning tools Procurement of materials Quality / time Control Use of Mobilization Advances Traffic / Safety Management Social Engagement
Recommendations Materials Management Unit (Government level) Government roster with upcoming work projects in all areas Better contractor register – Database Procurement / Evaluation Criteria Improved Public Relations Multi stakeholders Committee throughout the project cycle
Recommendations Common spatial database for utilities Review and enforcement of weight control Establishment of equipment pool – renting of specialised equipment Value Engineering