Collab 4/15/04 #1 EDMEDM Funding the Project Martin Cooper, Los Alamos Co-spokesperson for the EDM Project for presentation to The EDM Collaboration Los.

Slides:



Advertisements
Similar presentations
Project management.
Advertisements

July 28, 2011 ITER Thomas J. Vanek Senior Policy Advisor Fusion Energy Sciences.
ESEA Program Review Russ Sweet Preparing for ESEA Program Reviews of Titles I-A, II-A, VI-B (REAP), and X Summer 2014.
DOE/NSF U.S. CMS Operations Program Review Closeout Report Fermi National Accelerator Laboratory March 10, 2015 Anadi Canepa, TRIUMF Anna Goussiou, University.
1 BROOKHAVEN SCIENCE ASSOCIATES Procurement Dave Paveglio, Contract Administrator NSLS-II PAC Meeting May 25, 2007.
Breaching the Mahar Regional School Dam Presentation to Ralph C. Mahar Regional School Committee GZA GeoEnvironmental, Inc. February 9, 2011.
INPATIENT PROPOSAL INPATIENT PROPOSAL 4 MONTH CERTIFICATION SCHEDULE.
1 Neutron Electric Dipole Moment Experiment Jen-Chieh Peng International Workshop on “High Energy Physics in the LHC Era” Valparaiso, Chile, December 11-15,
LCLS Undulator Systems TDR Charge Linac Coherent Light Source Stanford Linear Accelerator Center Technical Review, March 3, 2004.
THE ADVANCED TECHNOLOGY ENVIRONMENTAL AND ENERGY CENTER (ATEEC) Summative External Evaluation July 1, 2013 – June 30, 2014 PRELIMINARY OUTLINE.
Development plan and quality plan for your Project
Collab 5/26/06 #1 EDMEDM Martin Cooper, Los Alamos Co-spokesperson and Contract Project Manager for the EDM Project for presentation to The EDM Collaboration.
Project X RD&D Plan Conventional Facilities (Civil Construction) Russ Alber AAC Meeting February 3, 2009.
October 24, 2000Milestones, Funding of USCMS S&C Matthias Kasemann1 US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab.
GlueX Collaboration Meeting February 2011 Jefferson Lab Our 30’th Collaboration Meeting.
Electric Dipole Moment of Neutron and Neutrinos
Collab 6/20/05 #1 EDMEDM Martin Cooper, Los Alamos Co-spokesperson for the EDM Project for presentation to The EDM Collaboration Los Alamos, NM January.
Facilities Appropriation Advisory Committee Update – (FAAB) CRIHB-NPAIHB Joint Biennial Board Meeting Thunder Valley Casino Resort Jim Roberts, Policy.
NCSX Management Overview Hutch Neilson, NCSX Project Manager NCSX Conceptual Design Review Princeton, NJ May 23, 2002.
1 OSEP Project Directors’ Conference April 28 th, 2015.
Collab 6/20/05 #1 EDMEDM Martin Cooper, Los Alamos Co-spokesperson for the EDM Project for presentation to The EDM Collaboration Raleigh, NC March 3, 2006.
Task: Copyright © 2003 PM tec, Inc; D. Sankey; D. Padelford. All rights reserved. 1 Fast Start For Projects  Electric Dipole Moment Project Facilitator:
New nEDM Sensitivity Calculation T. Langford B. Beise University of Maryland 7/3/2008 Simulation Teleconference Starting Points: Work by V. Cianciolo,
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Baseline Jim Yeck NSLS-II Deputy Project Director NSLS-II PAC Meeting November 20, 2007.
Research & Technology Implementation TxDOT RTI OFFICE.
Project Overview How to get here…. Half Way to the Test Run October 18, 2012HPS Project Overview2 …starting from here? John Jaros HPS Collaboration Meeting.
JLab preparations for upgrade, FY05 budget Elton Smith Hall D Collaboration Meeting May 20-22, 2004.
12 GeV Upgrade Project Status Allison Lung Hall C Users Meeting Jefferson Lab January 18, 2008.
John Peoples for the DES Collaboration BIRP Review August 12, 2004 Tucson1 DES Management  Survey Organization  Survey Deliverables  Proposed funding.
Keith O. Hodgson SSRL Director Brief Update on the Linac Coherent Light Source - LCLS February 26, 2002 Basic Energy Sciences Advisory Committee Undulator.
AGS RSVP Weekly Meeting P. Pile 16 September 2004 AGS RSVP Weekly Meeting, 16 Sep 2004 AGS Project Office - status of funding, comments on RSVP
International Accelerator Facility for Beams of Ions and Antiprotons at Darmstadt CBM Collaboration meeting Status Interim MoU J. Eschke, GSI.
LIGO-G M Planning and Implementation Strategy for Advanced LIGO Gary Sanders LSC Meeting Hanford, August 14, 2001.
7/26/2006 Wyatt Merritt 1 DECam CD1 Documentation DOE Critical Decision Process Documentation Requirements.
CARRUTHERS LSC 3/20/06 1 LIGO-G M The View from NSF Tom Carruthers LIGO Program Officer National Science Foundation (703)
Progress to Date PPPL Advisory Board Meeting May 20101NSTX Upgrade – R. L. Strykowsky CD-0 Approved February 2009 The NSTX Upgrade Project organization.
1 Project management. 2 Topics covered Management activities Project planning Project scheduling Risk management.
DOE 2/11/05 #1 EDM R&D Progress Steve Lamoreaux, Los Alamos Co-spokesperson for the EDM Project for presentation to The Department of Energy Cost & Schedule.
Collab Store 6/6/07 #1 EDMEDM Martin Cooper, Los Alamos Co-spokesperson for the EDM Project for presentation to The EDM Collaboration Los Alamos, NM June.
Response to TAC8 and Annual Review Recommendations John Haines Head of Target Division April 2, 2014.
ECOOL Meeting 03/26/10 1 Low-E cooler baseline decisions: 1.FNAL’s cooling section “as is” – with weak solenoids, correctors, etc. (to prevent over focusing.
Collab 5/26/06 #1 EDMEDM Martin Cooper, Los Alamos Co-spokesperson and Contract Project Manager for the EDM Project for presentation to The EDM Collaboration.
Atlantic Innovation Fund Round VIII February 5, 2008.
P25 Business 11/1/07 #1 Martin Cooper, Los Alamos Co-spokesperson for the EDM Project for presentation to The nEDM Collaboration MIT-Bates, Middleton,
Welcome and Presentation of Charge Steve Holmes Accelerator Advisory Committee ( May 10-12, 2005.
1 Global Design Effort: Controls & LLRF Controls & LLRF Working Group: Tuesday Session (29 May 07) John Carwardine Kay Rehlich.
Master Plan Process FY Proposed Draft. October - February Cluster Groups and Units Identify Initiatives These are general goals or outcomes that.
Collab_NSAC 4/2/03 #1 EDMEDM Martin Cooper, Los Alamos Co-spokesperson for the EDM Project for presentation to EDM Collaboration Meeting Los Alamos, NM.
Power Upgrade Project SNS September 21-22, TBM Cost Estimate Cost Estimate Schedule Approach Tom Mann October 27, 2005.
P25 Business 5/20/08 #1 Martin Cooper, Los Alamos Co-spokesperson for the EDM Project for presentation to The nEDM Collaboration Duke University, Durham,
EDMEDM C&S Review 2/11/05 #1 Martin Cooper, Los Alamos Co-spokesperson for the EDM Project for presentation to LANL Cost and Schedule Review Committee.
P25 Business 2/8/08 #1 Martin Cooper, Los Alamos Co-spokesperson for the EDM Project for presentation to The nEDM Collaboration ASU, Tempe, AZ February.
Proton-Driven Plasma Wakefield Acceleration CERN Project Structure Edda Gschwendtner, CERN Lisbon Meeting, 22 June 2012Edda Gschwendtner, CERN2.
Assembly 12/14/06 #1 Assembly and Commissioning Paul Huffman.
Collab 6/20/05 #1 EDMEDM Martin Cooper, Los Alamos Co-spokesperson for the EDM Project for presentation to The EDM Collaboration Los Alamos, NM June 20,
OMB Status 03/31/05 Monday, June 6, 2005 OMB Progress 03/31/05 Vicki Novak Tom Luedtke Gwen SykesPat DunningtonGwen Sykes Best in Government! Steps to.
Office of Nuclear Physics R&D 12/14/06 #1 Risk Based R&D Plan Martin Cooper Los Alamos.
FISCO2 – Financial and Scientific Coordination Work Package dedicated to ENSAR2 management WP leader: Ketel Turzó WP deputy: Sandrine Dubromel ENSAR2 Management.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
Collab_NSAC 4/2/03 #1 EDMEDM Martin Cooper, Los Alamos Co-spokesperson for the EDM Project for presentation to EDM Collaboration Meeting Los Alamos, NM.
Yannis K. Semertzidis Brookhaven National Laboratory New opportunities at CERN CERN, 12 May 2009 Storage Ring EDM Experiments The storage ring method can.
Cost and Schedule Paul Weinman Pacific Northwest National Laboratory.
Collaboration Business
Polices, procedures & protocols
Teacher Evaluation Timeline
Neutron and electron electric dipole moments
DOD’S PHASED SYSTEM DEVELOPMENT PROCESS
PULSE Building Renovation
Details supporting the increase
Project Overview.
Presentation transcript:

Collab 4/15/04 #1 EDMEDM Funding the Project Martin Cooper, Los Alamos Co-spokesperson for the EDM Project for presentation to The EDM Collaboration Los Alamos, NM April 15, 2004 Funding the Project

Collab 4/15/04 #2 EDMEDM Outline I)The March 1 visit to DOE II)A new R&D proposal for FY’05 III)Pushing for a FY’06 construction start IV)Getting CD0 and CD1 V)Project management

Collab 4/15/04 #3 EDMEDM I) The March 1 Visit to DOE Presentation to Jehanne Simon-Gillo, Gene Henry, Steve Steadman (DOE) and Brad Keister (NSF) I)R&D for the EDM Search - Steve Lamoreaux - 30 min. II)Studies of 3 He - Haiyan Gao - 15 min. III)Planning - Martin Cooper - 15 min.

Collab 4/15/04 #4 EDMEDM R&D Request for FY'04 and FY'05 FY'04$300k Pre-conceptual engineering on challenging issues Removing the "and a miracle happens here" FY'05$750k Continuing R&D at universities Conceptual engineering in preparation for the technical, cost and schedule review Project management for review

Collab 4/15/04 #5 EDMEDM Budget for the Experiment Estimated costs in FY04$k Project: Neutron EDM FY03 FY04FY05FY06FY07FY08FY09FY10FY11 Total Pre-R&D R&D375 CDR375 PED/ EDIA1, ,366 Cons4,4692, ,956 Preops TEC5,7043,9771,64111,322 TPC ,7043,9771, ,948 Planned redirect Needed New Funds ,7043,9771, ,948

Collab 4/15/04 #6 EDMEDM Schedule for the Experiment March 1, 2004R&D Report to DOE June 1, 2004Proposal Submission to DOE September 1, 2004CD0 on favorable review February 1, 2005CDR Submission to DOE March 1, 2005Technical, cost and schedule review April, 2005CD1 on favorable review November, 2005First construction funds available Spring 2008Commissioning begins

Collab 4/15/04 #7 EDMEDM SNS Risk Analysis QuantitySymbolDesignDegradedEDM LossEDM Limit [95% CL] Wall Loss Time ww >2,000 s +500 s1.8 Particle ID30:1 +2:14 Background / Signal2:15: He Relaxation Time 33 30,000 s *3,000 s He Initial PolarizationP3P3 99% *90% SQUID Noise 1  0 * * 10  Trapped Fields  B/B ** 5 x Electric FieldE50 kV/cm ***25 kV/cm2 1.0 Quadrature+ Under study * Positive evidence ** Likely OK *** Proven OK x e*cm Murphey's Law (4 worst) x e*cm

Collab 4/15/04 #8 EDMEDM Collaboration Proposal The team has entered a very active period of R&D to evaluate the challenges of building a successful experiment. It is our judgment that all technical problems can be overcome in the period between now and the beginning of construction. Progress report sent at the end of the first week of February. More results were presented today. The EDM Collaboration strongly urges the DOE Office of Nuclear Physics to submit the EDM project to Congress for construction in fiscal 2006.

Collab 4/15/04 #9 EDMEDM II) A New R&D Proposal for FY’05 InstitutionSubjectFunds Berkeley$ Caltech Duke HMI a Harvard Illinois b Leiden c Los Alamos c Engineering, project management, CDR 375 NIST a NC State a Oak Ridge Simon Fraser b Total$750k

Collab 4/15/04 #10 EDMEDM III) Pushing for a FY’06 Const. Start Doug thinks we should... I asked, "When is the date you would like to have an R&D proposal for FY'05? Is there a deadline? During our presentation in Germantown, I discussed submitting a real proposal for the construction of the EDM experiment fairly soon. Would your office now welcome a formal proposal from our collaboration? I suggested a June time frame." Jehanne responded, "I'm afraid that it is too early in the FY2006 budget process for us to give you definite guidance. We had to deal with an unprecedented number of budget scenarios this year, and various projects are in or out, depending on the scenario. At this point, we are very interested in your FY05 needs, which are not identified in the FY05 President's budget. I think we are now beyond the pre-conceptual R&D phase, so we will be approaching additional funding cautiously in the absence of a commitment to do the project at this moment. None-the-less, a prioritized plan that discusses the needs for 05 and the risks the R&D tasks are addressing, accompanied by task description, schedule, deliverable, who, cost etc, would be very interesting. In a cover letter, it would also be interesting to assess the impact to the project and collaboration if this R&D funding were not supported in 05, given that there are no funds earmarked for this activity, in as quantitative and concise of a manner as possible. "We will keep you in the loop and provide you with as much information as we can over the next many months."

Collab 4/15/04 #11 EDMEDM IV) Getting CD0 and CD1 The Proposal - Should be the path to CD0 1.Pre-proposal 2.R&D update 3."This is Jehanne Simon-Gillo and Gene Henry is also in the room..." Source of operating funds Commitments of researchers - Fraction of time for research, fraction of research time for EDM Time scale for MOUs Facility modifications Cost breakdown with an "honest-to-God" contingency analysis A more clear description of milestones

Collab 4/15/04 #12 EDMEDM IV) Getting CD0 and CD1 The R&D project in preparation for the CDR Complete the polarized 3 He relaxation studies Measure the UCN storage time Demonstrate particle ID Tidy up preliminary measurements Improve light collection from the measuring cell Demonstrate 3 He injection into superfluid He Observe 3 He magnetization with SQUIDs Depolarized 3He removal Design the beam splitter/state-selector and address other neutron transport issues The CDR - Should be the path to CD1 Results from the nearly completed R&D project Latest technical design A carefully scrubbed cost and schedule

Collab 4/15/04 #13 EDMEDM V) Project management Employ a professional project planner at LANL 2 days/week Planner will work closely with LANL physicists and engineers to establish initial cost and schedule Work package leaders must be selected soon!! Work package leaders will work with the planner to do the next iteration on the budget. The work packages will be iterated a number of times between the proposal and the CDR Work package leaders should expect paperwork