The NSTX-U Electric Arc Introductory comments on the process of recovery Stewart Prager May, 2015.

Slides:



Advertisements
Similar presentations
Preparation of the Self-Study and Documentation
Advertisements

Lim Sei cK.  Information!  What information is expected in a progress report?  The answer to this question depends, as you might expect, on the.
Jan 28, 2009CFS-GBL meeting 1 PM report Jan 28, 2009: Reviews –AAP –PAC (May 9 and 10, 2009) Meetings –TILC09 FALC –Madrid, Jan 19, 2009.
SOFTWARE QUALITY ASSURANCE Maltepe University Faculty of Engineering SE 410.
Upstream PID Review Alan Bross MICE CM 16 October 12, 2006.
Paul drumm; 1 st December 2004; PM&TB Report 1 Project Management & Technical Board Reports.
paul drumm; 3rd December 2004; AFC MM 1 Cost & Schedule Review I Terms of reference: –To review the Cost and schedule of the MICE Muon beam –To review.
Fundamentals of Information Systems, Second Edition
Project Execution.
LSU 01/18/2005Project Life Cycle1 The Project Life Cycle Project Management Unit, Lecture 2.
“How Industry Learns” --- Proposed Project --- Karen Paulk, ConocoPhillips, Chair, Process Safety Group & Ron Chittim, API CRE Chairs & Sponsors Workshop.
Project Sponsor Project Manager 04/24/ Major Projects Quarterly Review.
Risk Management - the process of identifying and controlling hazards to protect the force.  It’s five steps represent a logical thought process from.
Worker Focused Safety Program Violence in the Workplace Worker Training Module 5.
NCSX Project Risk Management & Contingency Analysis Chris Gruber March 13, 2008.
Level 2 Unit 6 Application of Manufacturing Techniques in Engineering Engineering Diploma Level 2 Unit 6 Application of Manufacturing Techniques in Engineering.
Executive Session Director’s CD-3b Review of the MicroBooNE Project January 18, 2012 Dean Hoffer.
National Commission for Academic Accreditation & Assessment Developmental Reviews at King Saud University and King Faisal University.
EXPLORATORY / COMPARISON TEST. What types of written information will be required? – Prerequisite – Theoretical or conceptual – Procedural – Examples.
1 Historical Perspective... Historical Perspective... Science Education Reform Efforts Leading to Standards-based Science Education.
February NSTX-U Team Meeting. Engineering Operations Feb. 11, 2014 NSTX-U In-Vessel installations and Calibrations to conclude in late March (3/28/2014)
Executive Session Director’s CD-1 Review of the Mu2e Project April 3, 2012 Elaine McCluskey.
OFFICE OF SCIENCE 2.3 Infrastructure and Installation Sims, Edwards 1.Does the conceptual design and planned implementation satisfy the performance specifications.
QA Methodology By Rajib Roy Independent Consultant Qcon.
Advanced Controls and Sensors David G. Hansen. Advanced Controls and Sensors Planning Process.
Proposals and Progress Reports Module Twenty One Copyright © 2014 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
April NSTX-U Team Meeting. Engineering Operations April 25, 2014 NSTX-U In-Vessel installations and Calibrations to conclude in mid-June to shift activities.
Fundamentals of Information Systems, Second Edition 1 Systems Development.
THE PROJECT LIFE CYCLE PROJECT MANAGEMENT LIFE CYCLE LSU 01/18/2005 PROJECT LIFE CYCLE 1.
Leblanc_03Feb09_1 MPTS Phase 4 Benoit P. LeBlanc PPPL 19 June 2009.
Progress to Date PPPL Advisory Board Meeting May 20101NSTX Upgrade – R. L. Strykowsky CD-0 Approved February 2009 The NSTX Upgrade Project organization.
Presentation on OPCA and Governance support to Gauteng Municipalities on clean audit achievements: PCC Case Study 22 May 2014.
Fermilab Presentation Greg Bock, Pepin Carolan, Mike Lindgren, Elaine McCluskey 2014 SC PM Workshop July 2014.
OWL Concept Design Review Report to ESO Council 8 th Dec 2005.
NCSX Systems Engineering Management Plan Peer Review Bob Simmons May 15, 2003.
The Research Process.  There are 8 stages to the research process.  Each stage is important, but some hold more significance than others.
NSTX Response to the Lessons Learned Report NSTX TF Coil Repair Review September 3-4, 2003 Al von Halle.
IT Project Oversight & Budgeting Task Force – Section 944 of Budget Chaired by House Appropriations & Senate Ways & Means chairs Members from fiscal committees,
DUSEL Beamline Working Group Meeting March 09, :00 AM – Snake Pit (WH2NE) By Dean Hoffer - OPMO.
Evaluate Phase Pertemuan Matakuliah: A0774/Information Technology Capital Budgeting Tahun: 2009.
NSTX NSTX Team Meeting –Masa Ono June 5, 2015 NSTX-U Team Meeting June 5, 2015 Culham Sci Ctr U St. Andrews York U Chubu U Fukui U Hiroshima U Hyogo U.
Are you looking for an opportunity to join a company that has a long history and an exciting future? A place where you can grow within an international.
Anthony Indelicato DOE-Princeton Site Office February 2014 Construction Progress Review for the NSTX Upgrade Project Construction Progress Review for the.
Development, Validation, Implementation and Enhancement for a Voluntary Protection Programs Center of Excellence (VPP CX) Capability for the Department.
Types of Reports Introductory Report Progress Reports Incident Report Feasibility Report Marketing Report Field Report Laboratory Report.
TPTF Update Trip Doggett TAC March 9, TPTF Update Meetings February 6 & 7, February 20 Attendance approximately 40 Completed review of ERCOT’s clarification.
Systems Analysis & Design 7 th Edition Chapter 2.
Update on USS Pension Fund Staff Presentations 26 th November December 2014 Will Spinks Registrar, Secretary and Chief Operating Officer.
Introductory Remarks. Beth McInerny, LLC Background Project Coordination Skills Similar Projects Contact Information Agenda: Remarks.
Anthony Indelicato DOE-Princeton Site Office December 2012 Construction Progress Review for the NSTX Upgrade Project Construction Progress Review for the.
Executive Session Director’s Conceptual Design Review of Mu2e Project May 3-5, 2011 Jim Yeck.
SC Project Review of NCSX, April 8-10, 2008 C. A. Gentile NCSX Startup (WBS 85) C.A.Gentile NCSX CD-4 Startup.
THE WATERPROOFING STANDARDS
Executive Session Director’s Conceptual Design Review of Muon g-2 Project June 5-7, 2013 Jon Kotcher.
Chapter 6: Database Project Management
NATA Foundation General Grants Program Process
Jefferson Lab Reliability Task Force and Initiatives
Global 8D Problem Solving
LCLS Linac Technical Design Review Charge
Setting Actuarial Standards
Regulatory Oversight of HOF in Finland
ISTE Workshop Research Methods in Educational Technology
Planning for IT Audit Session 4.
HIDDEN PROBLEMS UNCOVERED
Charge for the LCLS Undulator Magnet Review Committee: Nov. 14th, 2003
Preliminary Project Execution Plan
NATA Foundation General Grants Program Process
CDS-EL IRR Closeout 28 March 2019 J.G. Weisend II, Chairman.
Adherence Learning Lab: Community Conference Pre-Work
Presentation transcript:

The NSTX-U Electric Arc Introductory comments on the process of recovery Stewart Prager May, 2015

NSTX-U construction project By April 23 All construction complete (2.5 year project), External readiness review for operations complete Majority of electrical commissioning complete for CD-4

NSTX-U construction project By April 23 All construction complete (2.5 year project), External readiness review for operations complete Majority of electrical commissioning complete for CD-4 April 24 Ready for “CD-4 plasma shot” Electrical arc occurred in OH coil circuit (external to center stack magnet)

Disassembly, detailed assessment, clean-up began immediately Three internal reviews have been commissioned – internal to PPPL, but external to NSTX-U Two reviews are complete, one is longer term Detailed design for reassembly underway Expect to restart machine commisioning in about 6 weeks (exact schedule TBD)

Internal reviews On causes: technical, procedural, process Appointed April 30 Completed May 13 On technical extent of condition Appointed May 13 Completed May 22 Root cause analysis In-depth investigation of human, organizational, technical factors Appointed May 4 In progress, report expected in about one month

Chronology MayJune 4/24 arc PPPL Review causes PPPL Review Extent cond PPPL Advisory committee External review Root cause analysis (for long-term improvements) Assessment, design, reassembly restart

Review committee memberships On causes: technical, procedural, process R. Ellis (chair, ME),J. Delooper (best practices), J. Hosea (phys.), C. Neumeyer (EE), M. Bell (phys.) On technical extent of condition J. Hosea (chair, phys), R. Ellis (ME), N. Greenough (EE), D. Mueller (phys) Root cause analysis I. Zatz (chair, ME), J. Lacenere (EE), J. Malsbury (QA), M. Mardenfeld (ME)

Charge to internal review committee Root technical cause: Is the cause for the arc correctly identified and understood? Are there any other likely causes that should be more carefully considered? Are there contributing causes that also need to be addressed prior to implementing any repair or re-design work? Root procedural and process causes: Are there any procedural or process lapses that contributed to the fault – either in design/installation or in machine operations/interlocks? Are there any procedural or process improvements that should be implemented? Extent of condition: Are there any other areas of NSTX-U, not yet identified, that might have been compromised by the fault, or be subject to similar defects? Are there any other similar weaknesses in the NSTX-U design, procedures, or processes that could lead to future difficulties? Repair and design solution: Are the conceptual designs, repairs, and corrections identified by the NSTX-U team highly likely to avoid a recurrence of a similar fault? Are there other approaches that would be superior?

Internal review committee report Root technical cause Understood Root procedural and process causes Many findings and recommendations (for pre- and post- startup) Extent of condition Recommended a follow-on “task force” to answer this charge Repair and design solution Early in the design, will need to follow PPPL design review procedures A substantive, appropriately “hard-hitting” report with many recommendations Corrective action plan underway Appointed, and work completed Well underway

Internal review committee report Root technical cause Understood Root procedural and process causes Many findings and recommendations (for pre- and post- startup) Extent of condition Recommend a follow-on “task force” to answer this charge Repair and design solution Early in the design, will need to follow PPPL design review procedures A substantive, appropriately “hard-hitting” report with many recommendations Corrective action plan underway Appointed, and work completed Well underway Technical cause discussed by Stefan Gerhardt Committee report discussed by Bob Ellis Design issues discussed by Larry Dudek, Steve Raftopoulos

Technical extent of Condition Report Careful assessment of other technical risks, some to be remedied before re-start, some after Committee report discussed by Joel Hosea Mitigation of risks covered by L. Dudek, S. Raftopoulos

Root cause analysis In-depth investigation of contributing organizational, technical, and human factors Roughly a two-month study Aimed for longer-term (post re-start) improvements Goals and process described by Irv Zatz

The charges are addressed in presentations 1. Technical cause: Larry Dudek, Stefan Gerhardt 2. Procedural and process causes: Bob Ellis 3. Extent of condition: Joel Hosea, Irv Zatz 4. Repair and design solution: Steve Raftopoulos 5. Overall recovery plan: All the above, Stewart Prager