Weekly summary Summary Week 28 -12.07/19.07 M. Lamont & J. Wenninger for the OP team and for all colleagues from the various groups 8:30 meeting 1.

Slides:



Advertisements
Similar presentations
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Advertisements

Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Wednesday 12 th September Pumping, removal of vacuum equipment from tunnel in the morning TOTEM & ALFA, RP movement tests: OK 11:50 pre-cycle started,
21/05/2012LHC 8:30 meeting Overview Week 20 Injectors, LHCb polarity, Beam-Beam Coordinators: Bernhard Holzer, Jan Uythoven.
LHC progress with beam & plans. Of note since last time Transverse damper Beta beating in the ramp Collimation set-up at 450 GeV & validation LBDS – systematic.
5/11/2012LHC 8:30 meeting Summary of Week 44 Coordination: Mike Lamont & Jan Uythoven.
Monday 29 October 08:48 V/dM scan CMS end of fill #3236. Check of “fast scan”. 10:06 V/dM scan finished, start of RF studies, reducing RF voltage. 11:10.
● 08:30 Loaded by mistake squeeze function to 2 m  Dumped beams ● 10:30-13:00 Test of new algorithm for long. Emittance blow-up to minimize oscillations.
CONTENT: Beam characteristics and parameters Filling schemes Operational settings OP procedure and COLL setting Planning Shift breakdown To define the.
:00: Prepared new fill B1: Q X =0.293, Q Y =0.269; lifetime = 25h ✔ B2: Q X =0.297, Q Y =0.267; lifetime = 5h ✗ Strong 50Hz and 100hz lines.
Monday h00: End of fill #1640: 3.7 pb h14: RB S12 and S23 tripped before loading rampdown table, active filter. MPE piquet. Fip_Com_Lost.
LHC progress Report LHCC Wednesday 23 rd March 2011.
Nominal intensity bunches ● First ramp with nominal intensity bunches suffered from an instability appearing around 1.8 TeV. ● Nominal intensity bunches.
LHC Progress Friday 30 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
00:15: Stable beams fill 1883, 1.1E33 cm-2s-1.  Seems the 144 bunches beam 1 doe not fit properly on the injection kicker waveform. Systematically the.
● Main goals for week 33: – Luminosity production; – First 150 ns bunch train attempts; – Roman Pots: check movement at 3.5 TeV, with 1b; – Off momentum.
LHC Progress Thursday 29 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
09:25 Operator dump fill #2178, integrated lumi 107/108/18 nb-1. Trip of RQ4.R6 (fire heaters discharged) just after the beam dump but the QPS gave no.
From yesterday LHC status Wednesday 26 th Welcome Verena back on shift 07:08 Access in PM85 for piquet EPC (O.Fournier).  Fuse on RD2.R8 circuit.
LHC progress Sunday 3rd May 2015 Coordination: Mike Lamont, Wolfgang Hofle.
06:00 – Ongoing injection problems on beam 2  07:42 – Start of injection investigations  11:11 – Injection problem fixed. Resteering of transfer line.
Saturday 11.9 ● From Friday – Minimum required crossing angle is 100  rad in 2010 – Plenty of aperture at triplets: > 13  (n1 > 10) – Can stay with 170.
CONTENT: Beam characteristics and MP concerns BI configuration Operational settings Collimators Planning Shift breakdown Thanks to: P.Baudrenghien, G.Bellodi,
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
Injection issues overnight 10:50 Access  QPS & EPC  Vacuum leak SPS – magnet to be replaced Monday – cycling for FT and LHC only over the weekend 12:15.
04h36: Cryo problem in arc 81. Access. 09h14: Injection.  TI8 injection collimator setup.  Testing new sequence.  New version of vacuum application.
07:00 Dump fil #2219, 123 pb -1 delivered. Trim TDI parking position to +/- 55 mm in the collimator BP trimmed the temperature kicker limit to 62 degrees.
Monday 19 th March 07:33 Lost (another) beam in the squeeze, beyond 2 m, B2 hits 1/3 resonance. 08:30 Start (another) ramp  Try to correct coupling and.
Tue 23/8 – Wed 24/8 09:00 Start 90 m optics run – Preparation and verification of the collimation functions – Re-generation of functions for Transverse.
MD Planning Fri – Sat (26. – 27.8.)
Wednesday 8.9 External crossing angles:
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
Cryo Problem MD Planning Tue (1.11.) C B Day Time MD MP Tue 01:00
Wednesday September 14th
Monday :00 Stable beams 9_6_6_6 13:40 Access.
Friday 07:00 Power glitch on the EDF network. Point 8 affected.
MD25 ns - 14/12/2012 G. Arduini, H. Bartosik, G. Iadarola, G. Rumolo
LHC Morning Meeting - G. Arduini
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13
Tue :25 Beams dumped due to RF vacuum interlock
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
LHC Morning Meeting - G. Arduini
Thursday morning – optics correction
Tuesday TOTEM and transverse loss map (1) OK
Summary of Week 11: 14 – 21 March
Wednesday Morning 8: :30 end of fill study - octupole polarity inversion (Elias, Tatiana, Alexey, Georges, …): Goal: study the effect of the.
Summary of Week 16 G. Arduini, J. Wenninger
Lost at 12:05 to power converter (RTQX2.R1) problem
Friday 31st August & night
J. Uythoven, W. Venturini Delsolaro, CERN, Geneva
Week 35 – Technical Stop and Restart
Tuesday 28th September Fill 1375 ongoing 09:00 Move in Roman Pots
04-05/08/2010 End of physics at ~11:00 after 18.5 hours ~120 nb-1.
Friday morning 10:30 Optics measurements and corrections.
Friday AM Some oscillations of the cryo conditions in MSR8 perturbed the setup for injection. RF frequency interlock fixed – required a reset of RF controls.
Summary of week 19 Machine Coordinators: G. Arduini, M. Lamont Main aim: Luminosity production.
Aims for the week Recover from technical stop and precycle at 10A/s
Wednesday 10:00 test of the un-squeeze to 90 m at 4 TeV.
Rocky last 24 hours Losses Q6.R5 Orbit SIS TCDQ OK! Power converters
Thursday 04/11 - Morning Access until ~13:00 Pre-cycle Proton checks:
Saturday Nov Stop proton operation. Switch back to ions
Monday 8th December Morning used for RF work (IP z, injection), damper noise checks. Stable beams period with LHCb spectrometer OFF – lost beam after.
Monday morning 09:40 Dump fill 2838, integrated ~130 pb-1.
Monday :00 – 15:00 : Stable beams 15:30 : Recover…
Wednesday h18: 228b fill lost just before start of ramp.
Monday 26th September 7:30 Beam dump, QSP on RQX.R1, lost cryo in ITR1, 91 pb-1. Cryo recovery, needed about 1.5 h. Setting of TI2 collimators to 5 sigma.
Another Immortal Fill….
Wednesday Following the struggle with the vacuum in IR2 over the night, drop intensity to 1.2E11/bunch. Fill first B1 – pretty quiet – then B2 – quite.
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

Weekly summary Summary Week /19.07 M. Lamont & J. Wenninger for the OP team and for all colleagues from the various groups 8:30 meeting 1

General performance ● Start of the week : operation with 8/9 bunches per beam, 9E10/b. – 6 colliding pairs for ATLAS, CMS and LHCb. ● Tuesday : switch to 12 bunch operation, 9E10/b. – 8 colliding pairs for ATLAS, CMS and LHCb. – Peak luminosity 1.4E30 cm-2s-1 ● Thursday : switch to 13 bunch operation, 9E10/b. – 8 colliding pairs for ATLAS, CMS and LHCb. – Stored energy : 660 kJ. – Peak luminosity : 1.6E30 cm-2s-1 for fill 1233 on Sunday. – Expected luminosity 1.7E30 cm-2s-1 for nominal emittances. – Longest fill : 19 hours. ● Attempt to add an extra ½ intensity bunch for LHCf on Thursday. – Aborted, running late in the night, longer than expected beam position interlock check. 8:30 meeting 2

Record fill :30 meeting 3 In stable beams for 19 hours L at end: 0.7E30 cm-2s-1

Good periods ! 8:30 meeting 4

Integrated L (M. Ferro-Luzzi) 8:30 meeting 5 Does not include the weekend !

● Beam intensity lifetimes in collision between 25 and 125 hours. – Initially lifetime degradation when switching on transverse damper on B2, fixed by RF team during the week (better noise performance). – In the last fills dampers had positive or no effect on lifetime. – Fill with very equal TOTAL intensity tend to perform better. ● Losses in collisions. – Bunch intensity losses have still been observed in collisions, but they became less frequent in the second half of the week. – Changes: – Damper ON (but not always). – Larger Q split B1-B2 : from to – Manual luminosity optimization. Beams in collisions 6 8:30 meeting

Bunch 1 loss at start of fill 1232: almost 50% 8:30 meeting 7

TOTEM - roman pots ● Roman pots were moved into the beam during stable beams. – First to 30 sigma H and V. – Night Wednesday to Thursday: 25 sigma in V. – At 25 sigma candidate elastic events were observed. – No problems for operation, but some issues with stability of front-end software (diagnostics only – interlocking not affected). 8:30 meeting 8

Hump vs. GSM signal in the tunnel ● Circulating beam (single nominal bunch) available at ~16:25 Started to switch OFF GSM network in the tunnel in the following order: – Sector 12 + TI2 Sector 23 Sector 34 sector 45 Sector 56 Sector 67 Sector 78 Sector 81 + TI8 + UX15 ● By 17:24 all GSM transmitters in the tunnel were OFF No significant modification on the hump amplitude By 18:00 the GSM network was re-established (for a total interruption of 1.5 h) This test was possible thanks to the contribution of IT/CS (A. Pascal, F. Chapron). Test organized by G. Arduini on Thursday

Hump vs. GSM signal in the tunnel ● Typical slow drift in frequency as observed in other occasions, but no significant change in amplitude GSM OFF – B2V GSM OFF – B2H GSM ON – B2V GSM ON – B2H

● SPS multi-bunch cycle – SPS cycle with 4 injections is ready. – Adjusted extraction kicker delays to extract ALL 4 bunches. – Extraction to upstream TEDs for both B1 and B2. – Extraction to TI2 downstream ok. – Everything looking ok – next step is injection into the LHC. ● Multi-bunch injection into LHC – Delayed to after the technical stop. Suffered from booster MPS, SPS vacuum and expert availability issues. Multi-bunch injection 11 8:30 meeting

Ghost bunches ● Small ghost bunches around main bunches reported by the experiments. – Intensity at the level of 0.1% of the main bunch. ● Ghost bunches confirmed measurements of the RF group. – Bunches extend up to  -80 ns. Spacing is 5 ns. – Abort gap population is below 5E6 p/bucket (except for messy 80 ns). 8:30 meeting 12

Capture losses ● After a problem to due an energy mismatch build up by the orbit FB at injection, it was suggested by RF to adapt the RF frequency at injection to balance the energy errors of ring1 and ring2. – Injection fRF changed by +5 Hz. – Lower capture losses. – A better match could be obtained with orbit correctors after the technical stop. – Capture losses will become more critical as we inject more beam ! 8:30 meeting 13

‘Big’ problems ● PS booster MPS problem. – Filling of LHC did not suffer too much, some refills were delayed. – Solved Wednesday evening. ● SPS vacuum problem : dipole in cell 406 – Vacuum problem appeared Thursday in the SPS. – Survived the weekend, running just below the threshold of the ion pumps. Multi-bunch injection tests foreseen Friday had to be postponed. 8:30 meeting 14

Smaller problems ● The usual zoo. – PC trips dumping the beams. – Spurious sector trips. – 2 Quench heater PS to be repaired (access). – Ventilation in CMS cavern. – Servers dying. – MKI. – TDI motors. – Orbit FB: off, NaN, instability. – Electrical networks triggering FMCMs. 8:30 meeting 15

Feedbacks ● LHC operation depends critically on the feedbacks. – Tune and orbit. ● Performance is generally excellent, still some hick-ups. – Orbit correction kicks suddenly report back as ‘NaN’ – beam lost in squeeze. – Sudden instability observed in one fill – beam saved (see next slide). – Orbit feedback tends to shift systematically the orbit correctors, and therefore shift the energy. Caused a problem at injection Friday morning, the 2 beams being mismatched in energy: large amounts of un-captured beam. 8:30 meeting 16

Orbit in the ramp fill :30 meeting 17 ● Orbit correction becomes unstable – seems to be coming from IR4. ● Orbit FB switches off. ● Switch on worked, instability disappeared! Very good stability 50  m rms !!

● Orbit clean-up at injection – Injection orbit and corrector settings re-seeded wrt reference. RMS deviations back to 0.1 mm, corrector settings cleaner (Saturday). ● Orbit and separation effects at 3.5 TeV – Following the orbit cleanup, the separation corrections no longer worked – luminosities were 0 at start of fill 1232 ! – Orbit changes have been propagated to 3.5 TeV by OFB (most likely). – New settings had to be found, because the older settings did not match. Tedious in ALICE (3 hours !). – Inspection and comparison of the orbits in stable beams of a few fills of the week revealed significant fill to fill differences in the IRs (up to mm) – must establish stricter correction policy, refresh references more frequently and improve the separation bump collapse procedure/settings. Orbit effects 18 8:30 meeting

This week ● Technical stop ● Beam setting up and operation – One dump with pilot bunch at 450 GeV and at 3.5 TeV for dump validation. – One ramp with 1 bunch of 9E10 / beam to validate modifications of SMP system (‘relaxed expert Setup Beam Flag limit [x4]). – Multi-bunch injection. – Energy matching ring1 and ring2. – Orbit and procedure clean-up at end of squeeze  collisions. – Loss maps for collimation. – Orbit feedback tests. – 10 A/s for pre-cycle and ramp-down (tbc). – Could dream of 24 bunches per beam. 8:30 meeting 19