Pete Lynch/Dawn Johnston representing WisDOT Feb 26, 2014 –Northcentral Technical College
Project Description Routes Load Dimensions Known construction/Mitigations Communication Protocol Questions 2
256 loads - 64 four piece towers Projected Start - June Projected Duration - 8 to 10 weeks* * Depends on final loading plans/equipment rotation 3
Monthly operations calls to build and clear routes 30 days prior to first move switch to weekly check in calls LCS entries need to be timely and accurate Monitored for incidents by central office Monitored by region for program/project changes Construction, Maintenance, Bridge Postings, etc 4
Map 5
All 15’6” H or less and 14’9” W or less TOP – 220K wtg 180 L Upper Mid – 245K wtg 185 L Lower Mid – 258 wtg 180 L Base – 258 wtg 150 L 6
STH 29 June/July Structures B B Single Lane Closures 14’ restriction 1 foot shy STH 29 July-Sept Structures B Single Lane Closures 14’ restriction 1 foot shy 7
Sign Sleeve 8
9
Dan Mulder Section Chief Freight and Roadside Facilities (608) Region OSOW staff can contact BHM Staff as well 10
11