10 October 2003S. DeBarger PEP-II 2002-2003 Vacuum Failures PEP-II Machine Advisory Committee.

Slides:



Advertisements
Similar presentations
1 Vacuum Pressure Calculations. 2 Vaccalc The program vaccalc was used for all calculations. The program required three pieces of information for each.
Advertisements

Sept. 30, 2004 NIKHEF-1 Hans de Vries Status NIKHEF Mechanics Secondary vacuum box Bellows Vacuum system CO 2 cooling: Bart Verlaat.
Proton Source Workshop Booster Downtime Wednesday, December 8, 2010 T. Sullivan.
M. Jimenez AT/VAC Room Temperature (LSS) Vacuum Systems M. Jimenez.
Progress and Plan for Superconducting RF Cavity RF Group.
SPECTRAP - GSI progress report and status overview.
Status of the LARP Phase II Secondary Collimator Prototype 30 September 2013 LHC Collimation WG Meeting Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US.
1 PEP Status M. Sullivan MAC Review Nov , 2007 M. Sullivan for the PEP-II Team Machine Advisory Committee Review November 15-17, 2007 Run 6 Summary.
2E34 Meeting and MCC News IR2 Vacuum Studies (Mike Sullivan) Plans for Lattice and Optics Work (Yunhai Cai)
Slides from Mike Sullivan’s Presentation at the 2E34 Meeting.
PEP-II B Factory Machine Status and Upgrades John T. Seeman for the PEP-II Staff SLAC DOE Site Review April 9, 2003.
BPM Upgrade Presented by: Nadine Kurita Contributors: S. Smith, S. Ecklund, J. Sebek, D. Martin, R. Hettel, R. Johnson, N. Reeck, M. Kosovsky, D. Arnett.
1 IR Vacuum M. Sullivan MAC Review Jan , 2006 M. Sullivan for the Machine Advisory Committee Review January 18-20, 2006 IR Vacuum.
IR2 Vacuum Status M. Sullivan for S. Ecklund, A Fisher, S. Novokhatski, F-J Decker, A. Kulikov, S. DeBarger, U. Wienands, S. Gierman, M. Petree, many BaBarians.
June 2-4, 2004 DOE HEP Program Review 1 M. Sullivan for the PEP-II Team DOE High Energy Physics Program Review June 2-4, 2004 PEP-II Status and Plans.
Non-welded Window Option Edgar L. Black IIT August 15,2003.
Topics from this weeks 2E34 meeting M. Weaver Jan 6, 2006.
IR 2 Vacuum Update M. Sullivan for PEP-II team For the 2e34 meeting of Feb. 15, 2006.
SLAC Accelerator Department The PEP-II Accelerator John T. Seeman Assistant Director of the Technical Division Head of the Accelerator Department SLUO.
SLAC Accelerator Department The PEP-II Accelerator Status and General Plans John T. Seeman Assistant Director of the Technical Division Head of the Accelerator.
Vojtech Pacak, PEP-II MAC Review, January PEP-II RF System Status and Upgrades By: Vojtech Pacak Klystron Department PEP-II Machine Advisory.
1 IR NEG heating M. Sullivan MAC Review Dec , 2004 M. Sullivan Machine Advisory Committee Review December 13-15, 2004 IR NEG Heating and Upgrade.
IR2 and IR4 Summary PEP-II meeting Jan. 23, 2006 M. Sullivan.
IR vacuum M. Sullivan PEP-II meeting Feb. 22, 2007.
Status of the LARP Phase II Secondary Collimator Prototype 14 October 2013 LHC Collimation WG Meeting Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US LHC.
Vacuum Pressures at IR Contents Y.Suetsugu KEKB Vac. Group 1.Outline of Vacuum System at IR 2.Behavior of Pressures 3.Remedies for Heating of Vacuum Components.
Proton Source Repairs Dan Bollinger 2/1/10. Cockcroft-Walton accelerators FNAL has 2 Cockcroft-Walton Pre-accelerators (Pre-acc) that provide beam to.
1 Tetsuhiko Yorita JASRI/SPring-8 Acc. Div. SPring-8 Vacuum System Contents - Outline of Vacuum system - Pressure behavior - Some topics.
1 BROOKHAVEN SCIENCE ASSOCIATES Vacuum Systems H.C. Hseuh, Vacuum Group Leader 8 th ASAC Meeting for NSLS-II Project May 10-11, 2011.
Proton Source Vacuum Plan By David B. Augustine Ben Ogert Jr. August 30, 2011.
1 Jim Thomas - LBL The Mechanical Integration Challenge for New Tracking Detectors in STAR Jim Thomas 07/10/2006.
Experimental Beampipes: Status and Outlook Ray Veness / AT-VAC For the beampipe team With many thanks to the experiment’s installation and coordination.
PIP- BOOSTER RF Tuner and Cavity Refurbishment 3/7/12 M. Slabaugh.
MFW Pump Discharge Check Valve OE Follow Up Dominion North Anna Power Station Gary W. Liffick FW System Engineer FSRUG, Feb 21-24, 2011.
Vet ABC Troubleshooting
IR summary M. Sullivan Nov. 3, 2011 JLAB MEIC IR workshop.
PEP-II Machine Advisory Committee Meeting SLAC, April 15-17, 2004 HOM Issues in LER Ring and IR. Recent measurements and calculations. Sasha Novokhatski.
1 HER Arc RF seals M. Sullivan MAC Review Oct , 2006 Status of HER Arc RF Seals M. Sullivan For the PEP-II team Machine Advisory Committee Review.
Accelerator and NuMI Upgrades Shutdown Update Cons Gattuso July 02, 2012 July 2, 2012 Cons Gattuso1.
NuMI NBI03 November 7-11, 2003 FNAL thin beam windows Jim Hylen / FNAL Page 1 FNAL experience with thin beam windows Issue is: Survival of window in high.
26-October-2006 PEP-II MAC Session HOM measurement and analysis S. Weathersby, A. Novokhatski HOMs in LER region 4: overview, history Collimator wake fields.
Machine status – December 28  Machine status - overview  Blue ring: ramp development  Yellow ring: obstruction update  Set-up and ramp-up.
Interaction Region Vacuum Chamber Upgrades Presented by: Scott DeBarger Contributors: D. Arnett, B. Bigornia, C. Carr, J. Langton, S. Metcalfe, D. Kharahk,
1 IR Vacuum M. Sullivan MAC Review Oct , 2006 M. Sullivan for the PEP-II team Machine Advisory Committee Review October 25-27, 2006 IR Vacuum Update.
1 Tim Michalski October 6, 2015 Engineering Issues in MEIC.
ATF2 Accelerator Status and Plans for JFY 2014 runs N. Terunuma, KEK.
High Power RF System Status By: Peter McIntosh Klystron Department PEP-II Machine Advisory Committee Review October
ILC MDI workshop January 6-8, 2004 PEP-II IR M. Sullivan 1 Interaction Region of PEP-II M. Sullivan for the ILC MDI workshop January 6-8, 2005.
Program Risks Risk Analysis Fallback Plans for the PEP-II B-Factory John T. Seeman DOE PEP-II Operations Review April 26, 2006.
SKEKB Mini Work SKEKB Vacuum System – Arc Section – Contents Y.Suetsugu KEKB Vacuum Group 1.Beam Chambers 2.Pumps: Pump, Pressure,
LAr Week Feb 2000 M. Lefebvre Milestones and Schedule General Production Readiness Review  Passed in Jan 99 Leak Test Station and Electric Test.
August 4-5, 2004 PEP-II Post Run 4 Review 1 M. Sullivan PEP-II Post Run 4 Review August 4-5, 2004 IR Summary and Issues.
1 Run7 startup M. Sullivan MAC Review Nov , 2007 M. Sullivan for the PEP-II Team Machine Advisory Committee Review November 15-17, 2007 Run 7 Startup.
Solenoid Status Paul Brindza Dec. 12, Status of work at IUCF Solenoid R&R is based on a MOU between JLAB and IUCF The MOU divides the work into.
9 October 2003S. DeBarger PEP-II Vacuum Status PEP-II Machine Advisory Committee.
CM2 Helium Circuit Vacuum Leak & Repair Tug Arkan, 6/18/
RF Module Update MICE Collaboration Meeting 44 Andrew Lambert Lawrence Berkeley National Laboratory March 30 th, 2016.
November 16-18, 2004 Belle High Luminosity Workshop 1 M. Sullivan High Luminosity workshop (HL6) November 16-18, 2004 IR Vacuum Summary and Issues.
Proton PMG September 3 rd 2015 Cons Gattuso AD Shutdown Manager.
MI/RR Shutdown 2012 Dec Gev Lines/Injection region: Staging equipment, cleaning and prepping new part to start vacuum work. Preparing to modify the.
PEP- II Linac Accelerator Systems Department Status and Plans for PEP-II John Seeman SLAC Particle and Particle-Astrophysics DOE HEPAP P5 Review April.
Report Technical Director Storage-Ring-Installation Completed
Long Shutdown for the LHC: Vacuum Beam Pipes
CEPC Vacuum System Dong Haiyi 2017/11/5.
The situation for the coated magnets and what we learned in the LS1 installation: M.Taborelli, for TE-VSC.
A.Kulikov SLAC MAC review October 2003
PEP-II Status and Plans e+e- Factories Workshop
Interaction Region Design Options e+e- Factories Workshop
Accelerator R&D Results from the B-factory
CEPC Vacuum Systems Design Consideration
Presentation transcript:

10 October 2003S. DeBarger PEP-II Vacuum Failures PEP-II Machine Advisory Committee

S. DeBarger 10 October 2003 Elliptical Vacuum Valve Failure On 23 Jan 03, LER elliptical vacuum valves, PR02 VACV 1153 & PR02 VACV 3044 would not fully open following 2 Hour ROD. Both valves had damage to their RF seals and actuating mechanisms. The valves were removed and replaced with spool pieces. Failure is attributed to deficiencies in the design of the RF shields, compounded by a workmanship defect in one valve. Beam Time Lost hours Current Status Valves repaired by VAT using existing RF seal design. Spare valve installed at VACV 3044 location. Gap rings at this location have been replaced with gap rings of the correct size. Existing elliptical and round valves show heating by the beam. This is not adequately measured.

S. DeBarger 10 October 2003 LER Frangible Link On 19 Apr 03, pressure at the IP became elevated. Beam was unrunnable due to high LER Backgrounds. Leak discovered on upstream LER Frangible Link. Several attempts to VacSeal were short-lived; finally the leaking bellows module was replaced. During replacement of the leaking bellows, a second bellows module was found to have damaged RF fingers. Both bellows were replaced with spares and reinstalled. Failure is attributed to mishandling of the bellows during or after installation, causing the RF fingers to lose contact with the beampipe. It is possible that corrosion also played a part in the failure. Beam Time Lost47.50 hours Current Status New spare modules being fabricated using existing design New bellows restraints for transportation & for normal operation to be designed and fabricated

S. DeBarger 10 October 2003 Mystery Pressure Bump Near IP On 26 Apr 03, pressure at the IP became elevated. During leakchecking, pressure improved. No leak was located. Lots of speculation … could this be the first appearance of a problem that would resurface? Beam Time Lost hours

S. DeBarger 10 October 2003 LER Arc 1 Pumping Chamber On 9 May 03, pressure near PR02 VP1151 rose. Leakchecking revealed a leak in a weld prep on the pumping chamber aluminum extrusion. Attempts to seal the leak with VacSeal or to establish a guard vacuum were unsuccessful. Replaced the leaking chamber on 17 May 03. Beam Time Lost48.50 hours Current Status Chamber to be repaired

S. DeBarger 10 October 2003 Q2 Chamber On 27 Jun 03, pressure began to rise at the IP. Initial attempts to leakcheck did not locate a leak. By 4 Jul 03, the pressure had risen to the level. Additional leakchecking revealed a water-to- vacuum leak in the Forward Q2 chamber. Radial Ion Pump PR02 VP3012 failed on the 29 th, possibly related to leakchecking activities. Failure traced to a crack in the water-cooled mask due to a material defect Beam Time Lost 50.1 hours Current Status Chamber replaced with older version of the same chamber After removal, discovered that the NEG pump had been overheated at some time, damaging the NEG material Chamber repair appears not to be an option Evaluating the performance of the installed chamber and comparing to future running scenarios